Residential Building Permit (New Construction) — Puyallup, Washington · Requirements sheet
Verified 2026-09-16 · Source: https://ecode360.com/47719887
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Puyallup, Washington
Required for new one- and two-family dwellings and townhouses in Puyallup, reviewed under whichever edition of the International Residential Code the Washington State Building Code Council currently adopts in Chapter 51-51 WAC.
Verified 2026-09-16 · Source
When you need this permit
- Reviewed under “the current edition of the International Residential Code … as adopted by the Washington State Building Code Council in Chapter 51-51 WAC” (PMC 17.04.030) — the city names no edition year
- IRC Section R104 is amended to add R104.12, under which the building official has no duty to verify or establish lot lines or setback lines
- Fire sprinklers are NOT triggered by house size: PMC 17.36.020 excepts “a building that has three or less dwelling units”
- Applications expire 180 days after the city determines the application COMPLETE, extendable in 90-day periods for good cause (PMC 17.04.120(1))
- Permits expire if work is not commenced within 180 days, if work stops for 180 days, or two years after issuance regardless of progress (PMC 17.04.120(2))
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
PMC 17.04.080(1): “All fees and charges for permits, approvals, inspections or other services or items related to this title shall be established and amended from time to time by executive order of… Show full citationHide
PMC 17.04.080(1): “All fees and charges for permits, approvals, inspections or other services or items related to this title shall be established and amended from time to time by executive order of the city manager.” The code therefore publishes no dollar amount and none is asserted here. NOTE THE AUTHORITY: Puyallup sets fees by EXECUTIVE ORDER OF THE CITY MANAGER, where most Washington cities in this set use a city council resolution. Ask Development Services for the current executive order.PMC 17.04.080(4): where work has commenced without a permit the city may perform a special investigation and impose a fee “in an amount that compensates the city for performing the investigation”. Show full citationHide
PMC 17.04.080(4): where work has commenced without a permit the city may perform a special investigation and impose a fee “in an amount that compensates the city for performing the investigation”. It is payable “whether or not a permit or approval is subsequently issued.” No amount is published.PMC 17.04.080(2): building permit fees for construction, alteration and repairs of single-family or duplex dwellings MAY be waived when ALL of three conditions apply — the structure “is intended for… Show full citationHide
PMC 17.04.080(2): building permit fees for construction, alteration and repairs of single-family or duplex dwellings MAY be waived when ALL of three conditions apply — the structure “is intended for low-income families”, the construction “involves some volunteer labor”, and the builder is “an organization classified as a 501(c) nonprofit organization by the Internal Revenue Service.”Review timeline
Inspection process
Tips
- Get your own survey. Puyallup amends both the building and residential codes to say the building official “shall have no duty to verify or establish lot lines or setback lines”, and that no such duty “shall be implied”. An issued permit is not a finding that your house is legally sited, and the city has written that down twice so it cannot be argued.
- Watch which clock you are on. The application clock runs 180 days from the day the city calls your application COMPLETE, not from the day you filed it — so an incomplete submittal does not quietly burn your time, but it does not start it either.
- Sprinklers are unlikely to be your problem here. PMC 17.36.020 turns on 10,000 square feet, 40 feet of height or four stories, and then excepts any building with three or fewer dwelling units — so an ordinary house falls outside it on two grounds at once.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-09-16.
Codes & ordinances
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Puyallup building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Puyallup's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Puyallup yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Puyallup lands. Privacy.
Other permits in Puyallup
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Washington →
Look up this fee in a different city →