Solar / Electrical / Gas / Cell Tower Permit in Pima, Arizona

Required for solar photovoltaic installations, electrical work, gas-line work, and cell tower installations within Town of Pima limits. Applicants must separately coordinate utility interconnection approval with Graham County Electric (the local rural electric cooperative). Applications are submitted through the Town's iWorq Citizen Portal.

Verified 2026-07-23 · Source

When you need this permit

  • Permit required for solar, electrical, cell tower, and gas work within Town of Pima limits
  • Applicant is responsible for obtaining separate approval with Graham County Electric (the rural electric cooperative) for utility interconnection where applicable
  • Submitted via the Town of Pima iWorq Citizen Portal
  • A completed Building & Sub-Contractors Information form and Plot Plan may be required depending on project scope

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Solar PermitTown of Pima Schedule of Fees and Charges (New Fee Schedule.pdf, found live 2026-07-23), Planning and Zoning table. Plus the $100.00 Administrative Fee (added to all permits except the Fence Permit).
$225.00
Solar Electrical Panel Up GradeIn addition to the Solar Permit fee. Town of Pima Schedule of Fees and Charges, Planning and Zoning table.
$50.00
Electrical UpgradeTown of Pima Schedule of Fees and Charges, Planning and Zoning table — the general fee for electrical work filed under this combined permit category (no further electrical sub-categories are itemized).
$50.00
Communication TowersCovers the Cell Tower portion of this combined permit category. Town of Pima Schedule of Fees and Charges, Planning and Zoning table.
$150.00 per modification
Administrative FeeAdded to all permits under this category except the Fence Permit. Town of Pima Schedule of Fees and Charges, Planning and Zoning table.
$100.00
Gas Permit (verified-negative — no distinct fee line item)Chased 2026-07-23 against the Town's live Schedule of Fees and Charges (New Fee Schedule.pdf), which itemizes Solar, Solar Panel Upgrade, Electrical Upgrade, and Communication Towers fees but has no separate 'Gas' or 'Gas Permit' line item. Gas-line work filed under this combined Solar/Electrical/Gas/Cell Tower category most likely falls under the general Electrical Upgrade fee ($50.00) plus the $100.00 Administrative Fee, but the schedule does not say so explicitly — confirm the exact gas-specific fee with the Planning & Zoning Administrator (928-322-4860, building@pimatown.az.gov) before budgeting.
Not separately itemized

Review timeline

Plan review
Not published — contact the department

How long did your Solar / Electrical / Gas / Cell Tower Permit permit actually take in Pima?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring/piping inspection prior to enclosure, where applicable

  2. 2

    Final

    Final inspection and utility interconnection verification

See the full Pima inspection guide — scheduling & re-inspection fees →

Tips

  • Coordinate utility interconnection approval with Graham County Electric early — this is a separate step from the Town's own permit review and is explicitly called out on the Town's iWorq portal application description.
  • This permit type covers a broad mix of trade work (solar, electrical, gas, cell tower) under a single application category on the iWorq portal, unlike larger cities that split these into separate permit types.

Frequently asked questions

Pima requires a solar / electrical / gas / cell tower permit for: Permit required for solar, electrical, cell tower, and gas work within Town of Pima limits; Applicant is responsible for obtaining separate approval with Graham County Electric (the rural electric cooperative) for utility interconnection where applicable; Submitted via the Town of Pima iWorq Citizen Portal; A completed Building & Sub-Contractors Information form and Plot Plan may be required depending on project scope. If your project isn't listed, confirm with Town of Pima Planning & Zoning Department — Building Division at 928-485-2611 before starting work.

Per the Town's own live Schedule of Fees and Charges: Solar Permit $225.00 (plus $50.00 more for a Solar Electrical Panel Upgrade), general Electrical Upgrade $50.00, and Communication Towers $150.00 per modification — each plus the $100.00 Administrative Fee added to nearly all permit types. No separate dollar figure is itemized specifically for gas-line work under this combined category; confirm with the Planning & Zoning Administrator (928-322-4860, building@pimatown.az.gov).

Pima does not publish a plan-review timeline for this permit. Contact Town of Pima Planning & Zoning Department — Building Division at 928-485-2611 for current turnaround.

You'll need: Solar/Electrical/Gas/Cell Tower Permit Application. Depending on your project, Pima may also ask for: Graham County Electric Approval. See the required-documents checklist on this page for details on each.

Pima requires 2 inspection(s) for a solar / electrical / gas / cell tower permit, in order: Rough-In, Final. Schedule each through Town of Pima Planning & Zoning Department — Building Division (928-485-2611).

Apply through Town of Pima Planning & Zoning Department — Building Division at 110 W. Center St. / PO Box 426, Pima, AZ 85543. Phone: 928-485-2611, email: building@pimatown.az.gov. Office hours: Planning & Zoning Administrator: Joe Carpenter, 928-322-4860, building@pimatown.az.gov. The Planning & Zoning Board meets the 3rd Tuesday of each month at 7:00 PM. Building, Addition/Remodel, and Solar/Electrical/Gas/Cell-Tower permit applications (plans required as uploads) plus Sign/Fence permits are submitted through the Town's online iWorq Citizen Portal (pimaaz23.portal.iworq.net/portalhome/pimaaz23); a paper Mobile/Manufactured Home Installation Permit application and a Building & Sub-Contractors Information form are also available directly from the Town.. Official information: https://www.pimatown.az.gov/departments/planning_and_zoning.php.

Pima, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The Town of Pima independently operates its own Planning & Zoning Department / Building Division with its own Planning & Zoning Board, building inspector, building official, permit intake (iWorq portal), and Certificate of Occupancy process — it is NOT administered by Graham County. Source: Town of Pima Planning and Zoning page (pimatown.az.gov/departments/planning_and_zoning.php); Town of Pima Building & Sub-Contractors Information form (references 'the building department,' 'building inspector,' 'ordinances of the Town of Pima,' and a Certificate-of-Occupancy requirement 'obtained from the building inspector').; CODE EDITION CONFIRMED, AND RE-VERIFIED 2026-07-23 WITH A CHAPTER-NUMBERING CORRECTION: the Town's own 'Town Code' PDF, linked live from the Town Code page (current filename 'Town Code 2024_edited_3-23-2026.pdf' as of both the 2026-07-16 and 2026-07-23 passes), directly fetched and text-extracted again on 2026-07-23, confirms Chapter 7 (Building) is organized as: Article 7-1 Building Code, 7-2 Electrical Code, 7-3 Mechanical Code, 7-4 Plumbing Code, 7-5 Building Officials, 7-6 Utility Hookups, 7-7 Building Inspections, 7-8 Residential Code, 7-9 Uniform Fire Code, 7-10 Fuel Gas Code, 7-11 Existing Building Code, 7-12 Sewer Service Taps, 7-13 Certificate of Occupancy Requirements. This CORRECTS the prior pass's claim that Article 7-6 is the Residential Code — Article 7-6 is actually 'Utility Hookups' (a short unlawful-hookup-without-a-permit provision); the Residential Code is Article 7-8. Exact adoption language confirmed by direct quote: Article 7-1 Sec. 7-1-1, 'That certain code entitled International Building Code, 2009 edition is hereby adopted as the Building Code of the Town of Pima'; Article 7-8, 'That certain code entitled International Residential Code, 2009 Edition ... is hereby adopted as Residential Code of the Town of Pima'; and Article 7-11, 'That certain code entitled International Existing Building Code, 2009 Edition ... is hereby adopted as the Existing Building Code of the Town of Pima.' NEWLY CONFIRMED on this pass (previously missing from this file): Article 7-2 adopts 'International Electrical Code (70), 2011 Edition, published by the National Fire Protection Association' (i.e. NFPA 70 / National Electrical Code, 2011 Edition — NOT a 2009-family ICC code, and a different, newer edition than the rest of Chapter 7); Article 7-3 adopts the International Mechanical Code, 2009 Edition; Article 7-4 adopts the International Plumbing Code, 2009 Edition; Article 7-9 adopts the International Fire Code, 2009 Edition (the code text attributes publication to NFPA, quoted as written); Article 7-10 adopts the International Fuel Gas Code, 2009 Edition. No Municode/American Legal Publishing/CivicPlus code library exists for the Town of Pima — the Town's own compiled PDF Code of Ordinances is the sole publication. PENDING CHANGE FLAGGED, NOT YET LAW: the Town of Pima Planning & Zoning Commission, at its regular meeting July 21, 2026 (Minutes of the Regular Meeting of the Planning & Zoning Commission, Tuesday, July 21, 2026), voted unanimously to recommend that the Town Council adopt a new building code under attached Ordinance 2026-05, with P&Z Administrator Joe Carpenter stating that Graham County, the Town of Thatcher, and the City of Safford are all adopting the same new code and that Pima had not yet done so; the specific proposed code edition was not stated in the minutes text and the attached ordinance exhibit is a scanned/image-only PDF not machine-readable in this pass. As of 2026-07-23 this is only a Commission recommendation — the Town Council's own posted agendas/minutes run through July 14, 2026 (before the July 21 P&Z recommendation) with no August 2026 meeting yet posted, so Ordinance 2026-05 has NOT yet been voted on by Council and the 2009 IBC/IRC/IEBC + 2011 NEC editions quoted above remain the currently codified, live law. Recheck this file after a Town Council vote on Ordinance 2026-05 is posted.; Manufactured/mobile home installation is separately regulated: units are subject to the Arizona Mobile and Manufactured Housing Standards Board's statewide rules (1980 Revision cited on the Town's own application form) for the unit itself, with the Town issuing a separate local installation permit (siting, utility connections, accessory structures, plot plan, and pressure testing per Uniform Plumbing Code 1979 Edition Sec. 1206-2, per the Town's own application form). Source: Town of Pima Application for Mobile/Manufactured Home Installation Permit.. Local amendments apply — see the Pima overview page for the full list.

No. Graham County Electric is the local rural electric cooperative and only handles utility interconnection approval. The Town of Pima's own Planning & Zoning Department / Building Division issues the actual permit through its iWorq Citizen Portal.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pima building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare solar / electrical / gas / cell tower permit fees across Arizona

Look up this fee in a different city →

Embed this data card →

Now live

Build your Pima project checklist

Describe your project once and get every permit, document, and fee it triggers in Pima — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →