Building / Addition / Remodel Permit — Pima, Arizona · Requirements sheet
Verified 2026-07-23 · Source: https://www.pimatown.az.gov/departments/planning_and_zoning.php
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Building / Addition / Remodel Permit in Pima, Arizona
Required for new construction, additions, and remodels within Town of Pima limits. Applications, including uploaded building plans, are submitted through the Town's iWorq Citizen Portal. The Town's own compiled Code of Ordinances (Article 7-1 Building Code, Article 7-6 Residential Code, Article 7-11 Existing Building Code — linked live from the Town Code page) adopts the 2009 International Building Code, 2009 International Residential Code, and 2009 International Existing Building Code by reference; confirm with the Building Division whether later amendments apply before design.
Verified 2026-07-23 · Source
When you need this permit
- Building permit required for building, addition, and remodel work within Town of Pima limits
- Building plans must be uploaded as part of the online application submittal via the iWorq Citizen Portal
- A completed Building & Sub-Contractors Information form is required, listing the owner and all trade contractors/subcontractors (General, Excavating, Concrete, Mason, Framing, Drywall, Painting, HVAC, Electrical, Plumbing, Roofing) with name, address, phone, and business-license/bond status
- A Plot and Drainage Plan (Exhibit A) is required showing structures, utilities, septic/well locations, setbacks, easements, and drainage/retention details
- Construction must commence within 6 months and be completed within 1 year of the application date
- Occupancy of any space is prohibited until a Certificate of Occupancy is obtained from the Town's building inspector
- Power of Attorney form required if the applicant is not the property owner acting directly
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough Plumbing
Per Town Code Article 7-7 (Building Inspections) and Article 7-13 (Certificate of Occupancy Requirements): must pass an air or water test before the trench may be covered
- 2
Pre-Concrete
All rebar, fiber bar, mesh, etc. must be in place before concrete pour
- 3
Framing/Roofing
Structural framing and roofing inspection; catwalk in attic for all appliances must be in place
- 4
Mechanical/Electrical
Must be completed before drywall installation
- 5
Drywall
Inspected for nail-off before tape and texture
- 6
Final / Certificate of Occupancy
Must be move-in ready: GFCIs correctly located and operational, all flooring installed, smoke detectors operational, garage doors installed and operational, all appliances installed and operational, all receptacle cover plates installed. Certificate of Occupancy is issued only once all inspections have passed; occupancy before CO issuance is expressly prohibited. Applicants must call Town Hall during business hours with a minimum of 24-hour notice for each inspection.
See the full Pima inspection guide — scheduling & re-inspection fees →
Tips
- The Town of Pima's own Building & Sub-Contractors Information form gives the clearest confirmation that Pima runs its own building department: it references 'the building department,' a 'building inspector,' and 'ordinances of the Town of Pima' directly, and requires a Certificate of Occupancy before any space may be occupied.
- Applications are submitted online via the iWorq Citizen Portal; the portal's public application descriptions do not list fee amounts or code editions — the Town's live Schedule of Fees and Charges PDF (New Fee Schedule.pdf, found 2026-07-23) is the actual fee source instead.
- Construction must start within 6 months of the application date and be completed within 1 year — plan your permit timing accordingly.
- The Town Code (Section 7-1-3) also treats driveways, sidewalks, and non-sight-obscuring fences (chain link, barbed wire, lattice, etc.) as requiring a building permit, in addition to the more obvious new-construction/addition/remodel categories.
- The Town's Planning & Zoning Commission voted July 21, 2026 to recommend the Town Council adopt a new, unspecified building code edition (Ordinance 2026-05), aligning with Graham County, the Town of Thatcher, and the City of Safford; as of 2026-07-23 the Town Council has not yet voted on it, so the 2009 IBC/IRC/IEBC editions cited above still apply. Recheck for a Council vote before relying on this for a project spanning late 2026.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Pima building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Pima
Building / Addition / Remodel Permit in other cities
Compare building / addition / remodel permit fees across Arizona →
Look up this fee in a different city →
Now live
Build your Pima project checklist
Describe your project once and get every permit, document, and fee it triggers in Pima — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →