How to schedule
Inspections are requested through the building department below.
- Address
- Municipal Services Building, 22358 S. Ellsworth Road, Queen Creek, AZ 85142
- Phone
- 480-358-3003
- Office hours
- Monday - Thursday, 7 a.m. - 6 p.m.; closed Fridays (Town offices closed Friday-Sunday). Applications are submitted electronically through the Development Nexus / Accela Citizen Access online portal (aca-prod.accela.com/QC). Building inspections are scheduled through Development Nexus or by phone/text; the cutoff for next-business-day inspection requests is 6:00 p.m. Inspection hours are 6 a.m.-1:30 p.m. Mon-Thu and 6-10 a.m. Fri (September-May), and 5:30 a.m.-12 p.m. Mon-Thu and 5:30-10 a.m. Fri (June-August). Building Official: Michael Williams, CBO, Building Safety Manager, Michael.Williams@QueenCreekAZ.gov, 480-358-3009.
- Website
- Official site
Published scheduling rules
- Inspection scheduling cutoff for next-business-day service is 6:00 p.m.; requests after the cutoff move to the second business day — this is the basis for the 1-2 business day review/turnaround window on straightforward stand-alone electrical work with no plan-review step. (Electrical Permit)
- A stand-alone AC/HVAC unit swap with no other scope change is typically a counter/portal-issued permit with an inspection-only turnaround, consistent with the Town's 1-2 business day next-business-day inspection scheduling cutoff (6:00 p.m.). (Mechanical / HVAC Permit)
Inspection sequence
Applies to: Residential Building Permit (New Single-Family Construction)
- 1
Foundation/Footing
Before concrete pour; job card and field-set plans must be on site
- 2
Framing
Structural framing and connections per 2021 IRC/IBC as adopted by the Town; job card must be posted near the front door once the structure is framed
- 3
Rough-In (Plumbing/Electrical/Mechanical)
Combination trade rough-in inspection before walls are closed
- 4
Final / Certificate of Occupancy
All work complete per approved plans; Residential Certificate of Occupancy issued ($40 fee)
Applies to: Residential Addition / Remodel Permit
- 1
Foundation/Footing
Required before concrete pour for additions
- 2
Framing
Structural connections to existing structure
- 3
Final
Completed work verified against approved plans
Applies to: Swimming Pool and Spa Permit
- 1
Pre-Gunite / Steel
In-ground pool structural steel and plumbing rough-in before gunite/shotcrete
- 2
Barrier/Fence
Verifies compliance with pool barrier requirements (height, gates, self-latching hardware, or equivalent alternative) before the pool holds water
- 3
Final
Completed pool/spa and barrier verified against approved plans and the 2021 International Pool and Spa Code
Applies to: Electrical Permit
- 1
Rough-In
Wiring, box placement, and panel connections before walls are closed
- 2
Final
Devices installed and connections verified per 2020 NEC as adopted by the Town
Applies to: EV Charging Station Permit (Electrical Permit)
- 1
Rough-In (if applicable)
Wiring, box placement, and panel connections before walls are closed
- 2
Final
EVSE breaker sizing, GFCI protection (where applicable), and connections verified per 2020 NEC Article 625 as adopted by the Town
Applies to: Mechanical / HVAC Permit
- 1
Rough-In
Ductwork and equipment placement before walls closed
- 2
Final
Equipment operational, clearances and combustion air verified
Applies to: Plumbing Permit
- 1
Rough-In
After pipes installed, before walls closed
- 2
Final
Fixtures connected, water heater and gas connections verified, no leaks
Applies to: Re-Roofing Permit
- 1
Roof Inspection (In-Progress)
Verifies sheathing, flashing, underlayment, and material installation
- 2
Final Roof Inspection
Completed roofing work verified against approved permit/material listing
Applies to: Single Family Residential Solar Photovoltaic (PV) System Permit
- 1
Rough Electrical / Racking Attachment
Conduit runs, wire sizing, disconnect placement, and roof/racking attachment before energizing
- 2
Final
Panel mounting, roof penetration sealing, electrical connections, and interconnection point verified
Final inspection only: Demolition Permit, Fence and Wall Permit
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Queen Creek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Queen Creek building permits
Get alerts for Queen Creek
We'll email you when Queen Creek's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.