Change of Use (Zoning Clearance and Certificate of Occupancy) in Queen Creek, Arizona
Queen Creek regulates change of use, but does NOT publish a standalone permit product called a 'Change of Use Permit' — there is no change-of-use application form on the Town's Building Requirements/Checklists/Applications page and no change-of-use line item in the adopted Development Services Fee Schedule. Instead the Zoning Ordinance routes a change of use through two existing authorizations. Section 3.2.C.1 (Zoning Clearance and Building Permit) states: 'No person shall construct any structure, use any land, or change the use of any structure or land until a zoning clearance has been obtained from the Development Services Department and a building permit had been obtained from the Building Department.' Section 3.2.L.1 (Certificate of Occupancy) states: 'No vacant land or building shall be occupied or used (including change of use) or hereafter erected or structurally altered until a certificate of occupancy has been issued by the Building Official.' The Ordinance defines CHANGE IN USE as 'A change from one (1) principal use of a building or land to another principal use of the building or land whether or not there is an increase in the size of the existing building or extent of the use of the land.' A third, narrower reference exists at Section 2.7.C.1, which uses the phrase 'change of use permit' only in the non-conforming-use context: 'A change of use permit may be granted for non-conformity only if the change in use is to principal use permitted in the district. Once the change from non-conformity to a principal permitted use is completed, no conversion to the previous non-conforming use shall be permitted.'
Reviewed 2026-08-15 · Source
When you need this permit
- Zoning Ordinance Section 3.2.C.1: no person shall change the use of any structure or land until a zoning clearance has been obtained from the Development Services Department AND a building permit has been obtained from the Building Department
- Zoning Ordinance Section 3.2.L.1: no building shall be occupied or used (including change of use) until a certificate of occupancy has been issued by the Building Official
- Zoning Ordinance Section 3.2.C.4.b: the proposed building plan shall be in conformance with the land uses permitted in the zoning district in which the development project will be constructed
- Zoning Ordinance Section 3.2.C.5 (Validity): the building permit is valid for the use for which the zoning clearance was granted, as long as the use complies with applicable codes, provided that within six (6) months of issuance of the clearance a certificate of occupancy has been obtained; a new zoning clearance and any applicable fee are required for any approved project that did not commence construction within that six-month period
- Zoning Ordinance Section 3.2.L.2.a: the applicant shall submit the required materials with a request for final inspection, to the Planning Administrator
- Where the change of use involves physical work, the work is permitted under the Town's ordinary building/tenant-improvement track (see this file's commercial-tenant-improvement-permit entry) — including the requirement that each tenant space have its own application and building permit
- Fire sprinklers, fire alarms, and commercial kitchen hood fire suppression are permitted separately by Fire Prevention (see this file's fire-sprinkler-alarm-permit entry); a change to a higher-hazard occupancy commonly triggers those
- A Town of Queen Creek Business License is separately required before opening for business
- For a non-conforming use, Zoning Ordinance Section 2.7.C.1 permits a change of use only where the new use is a principal use permitted in the district, and the change is one-way — reverting to the former non-conforming use is not permitted
- Where the change of use is to a use requiring discretionary approval, a Conditional Use Permit may be required (Zoning Ordinance Section 3.5); the fee schedule prices Conditional Use at $250 + $30/acre + $50 fire review for residential and $1,000 + $30/acre + $50 fire review for commercial
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection / Certificate of Occupancy
Per Zoning Ordinance Section 3.2.L.2.a, the applicant submits the required materials with a request for final inspection to the Planning Administrator; the Certificate of Occupancy is then issued by the Building Official before the space may be occupied under the new use.
See the full Queen Creek inspection guide — scheduling & re-inspection fees →
Tips
- There is no form called 'Change of Use' in Queen Creek. The Town's published Applications list (Permit Application, Master Community Permit Application, Standard Plan Permit Guidelines, Permanent Sign Permit Application) contains no change-of-use application, and the adopted fee schedule contains no change-of-use line. The change of use is authorized through a zoning clearance plus a building permit plus a Certificate of Occupancy.
- A change of use needs a Certificate of Occupancy EVEN IF you do no construction. Zoning Ordinance Section 3.2.L.1 covers occupancy 'including change of use' independently of whether the building was erected or structurally altered — and the fee schedule prices exactly that case at $75/hour with a two-hour minimum ('Occupancy verification (no construction required)').
- The zoning clearance has a six-month clock. Under Section 3.2.C.5 the building permit is valid only for the use the zoning clearance was granted for, and a certificate of occupancy must be obtained within six months of the clearance being issued; otherwise a new zoning clearance and any applicable fee are required.
- Changing out of a legal non-conforming use is a one-way door: Section 2.7.C.1 allows the change only if the new use is a principal permitted use in the district, and once completed 'no conversion to the previous non-conforming use shall be permitted.'
- If you are unsure whether the new use is permitted in the district, the published instrument is a Zoning Confirmation Letter or Zoning Interpretation Letter at $250 each, rather than an application you can file and have rejected.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-08-15.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Queen Creek building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Queen Creek
Change of Use (Zoning Clearance and Certificate of Occupancy) in other cities
Compare change of use (zoning clearance and certificate of occupancy) fees across Arizona →
Look up this fee in a different city →
Now live
Build your Queen Creek project checklist
Describe your project once and get every permit, document, and fee it triggers in Queen Creek — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →