Required for new commercial and industrial building construction in Queen Creek, reviewed against the 2021 IBC as adopted by the Town of Queen Creek. Tenant improvement work to an existing commercial building is NOT covered by this permit type: the Town publishes a separate, distinctly named 'Commercial Tenant Improvements' submittal-requirements page and checklist (see this file's commercial-tenant-improvement-permit entry), even though both scopes are ultimately submitted on the same generic Permit Application form with a 'RESIDENTIAL / NON-RESIDENTIAL' checkbox rather than a project-type-specific form.

Verified 2026-08-01 · Source

When you need this permit

  • Building permit required for new commercial/industrial building construction Town-wide, reviewed against the 2021 IBC and Town of Queen Creek amendments
  • Per the Town's Commercial/Industrial Project Submittal Requirements page: 'It is the owner's responsibility to obtain a permit by completing an application... submitted online along with the electronic site plans, building plans, specifications, and other applicable and required construction documents'
  • Each building requires a separate application and building permit
  • Electronic construction plans must be in PDF format, maximum plan size 36" x 48", drawn to scale; plans prepared by a registrant (Architect or Engineer) must contain a legible imprint of the registrant's seal and signature
  • Cover sheet must include a code summary/list of design codes, description of the work covered, property description (legal description, street address, suite number), the Building Code Use/Occupancy designation, and a list of deferred items/special inspections if applicable, per Section 7.1.5 of the Town Building Code
  • Applicant must provide an estimated construction valuation for the proposed work
  • Fire sprinklers, fire alarms, and commercial kitchen hood fire suppression systems are explicitly NOT covered by this permit — per the Town's own page note, they 'require separate Fire permits'
  • A Town of Queen Creek Business License is required before opening for business and must be displayed conspicuously on site (courtesy notice on the Town's Commercial Requirements page)
  • Apply via the Development Nexus / Accela Citizen Access online portal

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Commercial Building Permit Fee — Based on Valuation (New Construction)Town of Queen Creek Commercial/Industrial Project Submittal Requirements page: 'Final Plan Review and Building Permit Fees: Fees are calculated after plan review using the square footage valuation of construction published annually by the International Code Council.' Cross-referenced against the Town-wide Fee Table mechanism already verified in this file's localAmendments and residential-building-permit entry, both citing the Development Services Fee Schedule — Valuation Data (effective 4/1/2026).
Per the Town's own Fee Table, applied against the greater of the ICC-published square-footage Valuation Data (by commercial occupancy/construction type) or the applicant's declared project valuation — the same Town-wide valuation-banded Fee Table documented in this file's residential-building-permit entry (e.g., $69.00 for the first $2,000 of valuation plus $11/additional $1,000 to $40,000, scaling to $18,327 for the first $5,000,000 plus $1/additional $1,000 thereafter). The specific ICC per-square-foot rate for commercial occupancy/construction-type classifications (e.g., B, M, S) could not be independently re-extracted this session — the Town's Valuation Data / Development Services Fee Schedule PDFs (documents 40835 and 40807) returned only page-count metadata with no extractable text via this session's available fetch tools (direct fetch blocked by the Town's Akamai WAF; Wayback Machine has no snapshot of document 40807). Omitted rather than invented; the dollar-banded Fee Table mechanism itself is verified Town-wide from this file's other entries, which did successfully extract it.
Commercial Plan Review FeeTown of Queen Creek Commercial/Industrial Project Submittal Requirements page: 'Plan review fees are collected at the 1st review submittal based on the declared construction valuation.' Percentage figure per the Town-wide Development Services Fee Schedule (effective 4/1/2026) documented elsewhere in this file.
65% of the applicable permit fee (this file's Town-wide Plan Review Fees convention), collected at the 1st review submittal based on the declared construction valuation
Third and Subsequent Plan ReviewsTown of Queen Creek Commercial/Industrial Project Submittal Requirements page: 'All third and subsequent submittals will require additional plan review fees.' Percentage per the Town of Queen Creek Development Services Fee Schedule (effective 4/1/2026).
15% of the applicable permit fee, due at submittal (Town-wide rule documented elsewhere in this file)
Fire Sprinkler / Fire Alarm Plan Review (separate Fire permit — not included in this Building Permit's fee)Town of Queen Creek Fire Sprinkler and Fire Alarm Submittal Requirements page (under Commercial Requirements): 'Plan review fees are collected at the time of submittal and are calculated by the square footage of the building/suite.'
Calculated by the square footage of the building/suite; collected at time of submittal

Review timeline

Plan reviewQueen Creek’s published plan-review target
Up to 5 business days

How long did your Commercial Building Permit (New Construction) permit actually take in Queen Creek?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation/Footing

    Before concrete pour; verifies footing/foundation reinforcement per approved plans

  2. 2

    Structural Frame / MEP Rough-In

    Structural framing/connections and mechanical, electrical, and plumbing rough-in verified before concealment, per 2021 IBC as adopted by the Town

  3. 3

    Special Inspections (if applicable)

    Performed per the approved Special Inspection Certificate by the design professional/testing agency of record

  4. 4

    Final / Certificate of Occupancy

    Completed work verified against approved plans before occupancy; a Town of Queen Creek Business License is separately required before opening for business

See the full Queen Creek inspection guide — scheduling & re-inspection fees →

Tips

  • As of August 2026, the Town of Queen Creek does not appear to publish a permit-specific plan review turnaround time for new commercial/industrial construction. A direct check of the Commercial Requirements, Commercial Tenant Improvements, Building Applications, Development Nexus Resource Center, and Development Nexus FAQ pages found no dedicated, numbered commercial review-timeline table (unlike some neighboring Arizona jurisdictions). Contact Development Services (480-358-3003) or a Permit Technician (480-358-3050) directly for a project-specific timeline.
  • Tenant improvement work is NOT part of this permit type — see this file's separate commercial-tenant-improvement-permit entry. Both scopes use the same generic Permit Application (checked 'NON-RESIDENTIAL'), but the Town publishes genuinely distinct submittal-requirements pages/checklists for each, with different required cover-sheet content and (for TI only) a licensed-commercial-contractor restriction.
  • Fire sprinklers, fire alarms, and commercial kitchen hood suppression systems are billed and reviewed under a separate Fire permit track, priced by building/suite square footage — not part of this Building Permit's fee.
  • Contact a Permit Technician (480-358-3050) for a fee estimate before submission; plan review fees are collected at the 1st review submittal based on declared valuation, with additional fees required for the 3rd and subsequent submittals.

Frequently asked questions

Queen Creek requires a commercial building permit (new construction) for: Building permit required for new commercial/industrial building construction Town-wide, reviewed against the 2021 IBC and Town of Queen Creek amendments; Per the Town's Commercial/Industrial Project Submittal Requirements page: 'It is the owner's responsibility to obtain a permit by completing an application... submitted online along with the electronic site plans, building plans, specifications, and other applicable and required construction documents'; Each building requires a separate application and building permit; Electronic construction plans must be in PDF format, maximum plan size 36" x 48", drawn to scale; plans prepared by a registrant (Architect or Engineer) must contain a legible imprint of the registrant's seal and signature; Cover sheet must include a code summary/list of design codes, description of the work covered, property description (legal description, street address, suite number), the Building Code Use/Occupancy designation, and a list of deferred items/special inspections if applicable, per Section 7.1.5 of the Town Building Code; Applicant must provide an estimated construction valuation for the proposed work; Fire sprinklers, fire alarms, and commercial kitchen hood fire suppression systems are explicitly NOT covered by this permit — per the Town's own page note, they 'require separate Fire permits'; A Town of Queen Creek Business License is required before opening for business and must be displayed conspicuously on site (courtesy notice on the Town's Commercial Requirements page); Apply via the Development Nexus / Accela Citizen Access online portal. If your project isn't listed, confirm with Town of Queen Creek Development Services Department — Building Safety Division at 480-358-3003 before starting work.

No. Fire sprinklers, fire alarms, and commercial kitchen hood fire suppression systems require separate Fire permits, with their own plan review fee calculated by the square footage of the building/suite, per the Town's Fire Sprinkler and Fire Alarm Submittal Requirements page.

As of August 2026, the Town does not publish a permit-specific commercial review timeline. The Town's Building Safety division reports a division-wide target of processing 99-100% of building permits (residential, commercial, and industrial combined) within 5 days from plan review completion to applicant notification, per the FY2025/26 Adopted Budget Book — but this is an aggregate figure, not a commercial-specific guarantee, and a large commercial project will realistically take longer. Contact Development Services (480-358-3003) or a Permit Technician (480-358-3050) for a project-specific estimate.

You'll need: Permit Application; Construction Documents (Site Plan, Building Plans, Specifications); Contractor Declaration Form. Depending on your project, Queen Creek may also ask for: Special Inspection Certificate. See the required-documents checklist on this page for details on each.

Queen Creek requires 4 inspection(s) for a commercial building permit (new construction), in order: Foundation/Footing, Structural Frame / MEP Rough-In, Special Inspections (if applicable), Final / Certificate of Occupancy. Schedule each through Town of Queen Creek Development Services Department — Building Safety Division (480-358-3003).

Apply through Town of Queen Creek Development Services Department — Building Safety Division at Municipal Services Building, 22358 S. Ellsworth Road, Queen Creek, AZ 85142. Phone: 480-358-3003, email: development@QueenCreekAZ.gov. Office hours: Monday - Thursday, 7 a.m. - 6 p.m.; closed Fridays (Town offices closed Friday-Sunday). Applications are submitted electronically through the Development Nexus / Accela Citizen Access online portal (aca-prod.accela.com/QC). Building inspections are scheduled through Development Nexus or by phone/text; the cutoff for next-business-day inspection requests is 6:00 p.m. Inspection hours are 6 a.m.-1:30 p.m. Mon-Thu and 6-10 a.m. Fri (September-May), and 5:30 a.m.-12 p.m. Mon-Thu and 5:30-10 a.m. Fri (June-August). Building Official: Michael Williams, CBO, Building Safety Manager, Michael.Williams@QueenCreekAZ.gov, 480-358-3009.. Official information: https://www.queencreekaz.gov/government/development-services/building-safety.

Queen Creek, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-jurisdiction authority under state enabling statutes (A.R.S. Title 9 for municipalities). The Town of Queen Creek is an independently incorporated town (not administered by Maricopa or Pinal County for permitting purposes) that adopts and administers its own construction codes through its Development Services Department / Building Safety Division. Source: Town of Queen Creek Building Safety page (queencreekaz.gov/government/development-services/building-safety) and Building Codes page.; 2021 International Building Code (IBC), as published by the International Code Council, adopted by the Town of Queen Creek with an effective date of January 1, 2023; applications submitted on or after April 1, 2023 must be designed to the 2021 edition. Source: Town of Queen Creek Building Codes page (queencreekaz.gov/government/development-services/building-safety/building-codes).; 2021 International Residential Code (IRC), adopted by the Town of Queen Creek effective January 1, 2023 (mandatory for submittals from April 1, 2023). Source: Town of Queen Creek Building Codes page.; 2021 International Mechanical Code (IMC), adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2020 National Electrical Code (NEC), as published by the National Fire Protection Association, adopted by the Town of Queen Creek — one edition behind the 2021 ICC family (the Town has not moved to the 2023 NEC as of this review). Source: Town of Queen Creek Building Codes page.; 2021 International Plumbing Code (IPC), adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2021 International Fuel Gas Code (IFGC), adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2021 International Existing Building Code (IEBC), adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2021 International Energy Conservation Code (IECC), adopted by the Town of Queen Creek effective January 1, 2023, governing energy-efficiency requirements. Source: Town of Queen Creek Building Codes page.; 2021 International Property Maintenance Code, adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2021 International Urban-Wildland Interface Code, adopted by the Town of Queen Creek effective January 1, 2023. Source: Town of Queen Creek Building Codes page.; 2021 International Pool and Spa Code, adopted by the Town of Queen Creek effective January 1, 2023, governing swimming pool and spa construction and barrier requirements. Source: Town of Queen Creek Building Codes page.; 2021 International Fire Code (IFC), adopted by the Town of Queen Creek effective January 1, 2023 as the Town's uniform fire code, administered by Fire Prevention within Development Services (see the Fire Prevention section of the Development Services Fee Schedule for operational/construction permit fees). Source: Town of Queen Creek Building Codes page; Town of Queen Creek Development Services Fee Schedule (Valuation Data, effective 4/1/2026), Fire Prevention section.; 2021 code adoption included Town-specific amendments; the Town's official '2021 Amendments' document and the original 2012 adopting Ordinance 539-13 / Resolution 969-13 / Exhibit A are both published on the Building Codes page for reference. Source: Town of Queen Creek Building Codes page (2021 Amendments PDF, and 2012 Ordinance/Resolution/Exhibit A PDFs).. Local amendments apply — see the Queen Creek overview page for the full list.

Yes in substance, though not in application form: both use the same generic Permit Application (checked 'NON-RESIDENTIAL'), but the Town publishes two separately named, genuinely distinct submittal-requirements pages — 'Commercial/Industrial Project Submittal Requirements' for new construction and 'Commercial Tenant Improvements' for build-outs of existing tenant spaces — each with different required cover-sheet content, and the TI page adds a licensed-commercial-contractor restriction not stated on the new-construction page. See this file's commercial-tenant-improvement-permit entry.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Queen Creek.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.