Fire Sprinkler and Fire Alarm System Permit in Holbrook, Arizona

New or modified automatic fire sprinkler and fire alarm systems in the City of Holbrook are plan-reviewed and permitted by the Arizona Office of the State Fire Marshal (OSFM), not by the City. Holbrook's own City Code Chapter 5, Article 5-2 (Sec. 5-2-5) adopts the 2018 NFPA Fire Code as part of the City's general building-code chapter, and the City separately operates its own Fire Department (suppression/emergency response, Chief Alex Baker) -- but neither of those facts gives Holbrook OSFM-recognized jurisdiction over fire-protection-system plan review and permitting. Under A.R.S. § 37-1383(A)(5), OSFM enforces the state fire code statewide except in a city of 100,000 or more persons that has enacted an ordinance to assume that jurisdiction from OSFM; Holbrook's 2020 Census population is 4,858, and Holbrook does not appear on OSFM's own published list of 'Cities with Enacted Ordinances' with assumed jurisdictional authority (Chandler, Gilbert, Goodyear, Glendale, Mesa, Scottsdale, Surprise, and Yuma, all far larger cities). The underlying City of Holbrook Building Permit for the structure itself (this file's commercial-building-permit or residential-building-permit entry) is still required in parallel and does not substitute for the OSFM fire-system permit.

Verified 2026-08-04 · Source

When you need this permit

  • New installation or modification of an automatic fire sprinkler system, fire alarm system, or other fire-protection system in Holbrook must be submitted directly to the Arizona Office of the State Fire Marshal (OSFM) for plan review and permitting under the State Fire Code -- not to the City of Holbrook Building Department or the City's Fire Department
  • OSFM has this jurisdiction because Holbrook (2020 Census population 4,858) does not meet the 100,000-person population threshold under A.R.S. § 37-1383(A)(5) required for a city to assume fire-code jurisdiction from OSFM, and Holbrook is not listed on OSFM's own 'Cities with Enacted Ordinances' page (which names only Chandler, Gilbert, Goodyear, Glendale, Mesa, Scottsdale, Surprise, and Yuma)
  • All OSFM plan applications, permits, and payments must be processed through OSFM's online Permit and Plan portal (Permit Self Service) -- paper applications are no longer accepted by OSFM
  • A separate OSFM plan review fee is charged for each fire-protection system reviewed, even if multiple systems (e.g., sprinkler and alarm) are included in one submitted plan set (Arizona Administrative Code R4-36-202(A)(2))
  • OSFM shall determine within 5 business days of receipt whether a permit application/plan submission is administratively complete, and shall grant or deny the permit within 60 calendar days after the submission is determined complete (Arizona Administrative Code R4-36-303(A))
  • A permittee must commence work within 180 days after OSFM permit issuance or apply in writing to OSFM for an extension, or the permit becomes invalid (Arizona Administrative Code R4-36-303(A)(3))
  • The underlying City of Holbrook Building Permit for the structure itself is still required in parallel, per City Code Sec. 5-1-1 and the City's Fee Schedule Section 2-1 -- the OSFM fire-system permit does not replace it
  • The City of Holbrook's own Fee Schedule (adopted November 15, 2025, Sections 2-1 through 2-14 and 3-1 through 3-4) contains no fire-sprinkler or fire-alarm-specific fee line of its own, consistent with fire-system permitting sitting with OSFM rather than the City

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

OSFM Plan Submission Fee -- each plan submittedArizona Administrative Code R4-36-202(A)(1)(a), current text as published by the Arizona Secretary of State (Supp. 26-1, effective April 13, 2026 rulemaking).
$210
OSFM Plan Submission Fee -- each supplement or re-review of a previously submitted planArizona Administrative Code R4-36-202(A)(1)(b).
$30
OSFM Plan Review Fee -- New Automatic Fire Sprinkler SystemArizona Administrative Code R4-36-202(A)(2)(a).
$375 (servicing under 10,000 sq ft); $450 (10,000-50,000 sq ft); +$450 per additional 50,000 sq ft or portion thereof; +$200 per floor level serviced above or below ground level
OSFM Plan Review Fee -- Modification of Existing Fire Sprinkler SystemArizona Administrative Code R4-36-202(A)(2)(b).
$75 (1-20 heads); $100 (21-50 heads); $250 (51-100 heads); $300 (101-500 heads); +$100 per additional 100 heads; +$200 per floor level
OSFM Plan Review Fee -- New Fire Alarm SystemArizona Administrative Code R4-36-202(A)(2)(k).
$225 (up to 1,000 sq ft); $300 (1,001-2,000 sq ft); $450 (2,001-10,000 sq ft); $500 (10,001-50,000 sq ft); +$200 per additional 50,000 sq ft; +$200 per floor level; +50% of the calculated fee for smoke detection throughout the serviced area
OSFM Plan Review Fee -- Modification of Existing Fire Alarm SystemArizona Administrative Code R4-36-202(A)(2)(l).
$100 (adding 1-5 devices); $150 (adding 6+ devices)
OSFM Permit Issuance Fee -- Fire Protection PermitArizona Administrative Code R4-36-202(A)(3)(a) -- the actual permit-issuance line item, separate from the plan-submission and plan-review fees above.
$30 per system permitted
OSFM Re-inspection FeeArizona Administrative Code R4-36-202(A)(4), charged when OSFM must re-inspect due to a missed/cancelled inspection (without 24 hours' notice) or a failed inspection.
$164 minimum, +$82 per each 25 miles (or portion) of travel beyond the first 25 miles required to reach the site
City of Holbrook Building Permit fees (underlying structure)The City's Fee Schedule (adopted November 15, 2025) has no dedicated fire-sprinkler/alarm fee line -- the City-side cost for a fire-system project is only the general Section 2-1 building permit fee for the structure, separate from and in addition to OSFM's fees above.
See this jurisdiction's commercial-building-permit / residential-building-permit entries

Review timeline

Plan reviewHolbrook’s published plan-review target
5–65 business days

How long did your Fire Sprinkler and Fire Alarm System Permit permit actually take in Holbrook?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    OSFM Field Inspection (Fire Protection System)

    The holder of an OSFM operational or construction permit is entitled to inspections as prescribed in Arizona Administrative Code Title 4, Chapter 36; scheduled via OSFM's own online Inspection Request form

  2. 2

    OSFM Re-inspection (if required)

    Billed at OSFM's re-inspection fee rate if a scheduled inspection is missed/cancelled without 24 hours' notice, or if the site fails inspection

  3. 3

    City of Holbrook Final Inspection

    Required under the parallel City building permit before the structure may be occupied and a Certificate of Occupancy issued; billed at the City's standard $75 inspection fee if no other fee is specifically indicated. Does not substitute for OSFM's own fire-system inspection

See the full Holbrook inspection guide — scheduling & re-inspection fees →

Tips

  • The City of Holbrook does not issue fire sprinkler or fire alarm permits itself, even though it has its own Fire Department (Chief Alex Baker, 100 Airport Road) and has adopted the 2018 NFPA Fire Code as part of its own building-code chapter (City Code Sec. 5-2-5). Neither fact transfers OSFM's statutory fire-protection-system permitting jurisdiction to the City -- that requires a population of 100,000+ and an OSFM-recognized assumption ordinance, which Holbrook (population 4,858) does not have.
  • OSFM's process is entirely online via its Permit Self Service portal -- this is distinct from the City's own GOGov permit platform used for the underlying building permit.
  • Sprinkler and alarm plan-review fees are calculated separately by system and by size/head-count/device-count tier under Arizona Administrative Code R4-36-202 -- get an exact quote from OSFM for your specific system size rather than assuming a flat fee.
  • You still need the City of Holbrook's own building permit for the underlying structure (Fee Schedule Section 2-1) in parallel with the OSFM fire-system permit -- one does not substitute for the other.
  • Holbrook's own Building Department page and Fee Schedule were checked directly for any fire-sprinkler/alarm-specific fee line and none was found, consistent with this being an OSFM-administered permit rather than a City one.

Frequently asked questions

Holbrook requires a fire sprinkler and fire alarm system permit for: New installation or modification of an automatic fire sprinkler system, fire alarm system, or other fire-protection system in Holbrook must be submitted directly to the Arizona Office of the State Fire Marshal (OSFM) for plan review and permitting under the State Fire Code -- not to the City of Holbrook Building Department or the City's Fire Department; OSFM has this jurisdiction because Holbrook (2020 Census population 4,858) does not meet the 100,000-person population threshold under A.R.S. § 37-1383(A)(5) required for a city to assume fire-code jurisdiction from OSFM, and Holbrook is not listed on OSFM's own 'Cities with Enacted Ordinances' page (which names only Chandler, Gilbert, Goodyear, Glendale, Mesa, Scottsdale, Surprise, and Yuma); All OSFM plan applications, permits, and payments must be processed through OSFM's online Permit and Plan portal (Permit Self Service) -- paper applications are no longer accepted by OSFM; A separate OSFM plan review fee is charged for each fire-protection system reviewed, even if multiple systems (e.g., sprinkler and alarm) are included in one submitted plan set (Arizona Administrative Code R4-36-202(A)(2)); OSFM shall determine within 5 business days of receipt whether a permit application/plan submission is administratively complete, and shall grant or deny the permit within 60 calendar days after the submission is determined complete (Arizona Administrative Code R4-36-303(A)); A permittee must commence work within 180 days after OSFM permit issuance or apply in writing to OSFM for an extension, or the permit becomes invalid (Arizona Administrative Code R4-36-303(A)(3)); The underlying City of Holbrook Building Permit for the structure itself is still required in parallel, per City Code Sec. 5-1-1 and the City's Fee Schedule Section 2-1 -- the OSFM fire-system permit does not replace it; The City of Holbrook's own Fee Schedule (adopted November 15, 2025, Sections 2-1 through 2-14 and 3-1 through 3-4) contains no fire-sprinkler or fire-alarm-specific fee line of its own, consistent with fire-system permitting sitting with OSFM rather than the City. If your project isn't listed, confirm with City of Holbrook Building Department at 928-524-6225 before starting work.

Fees are itemized by system type and size under Arizona Administrative Code R4-36-202: a new sprinkler system plan review ranges from $375 (under 10,000 sq ft) up to $450+ for larger/multi-floor systems, and a new fire alarm system plan review ranges from $225 (up to 1,000 sq ft) up to $500+ for larger systems, plus a flat $210 plan submission fee and a $30-per-system permit issuance fee -- all paid to OSFM, separate from the City of Holbrook's own building permit fee for the structure.

By rule (Arizona Administrative Code R4-36-303(A)), OSFM has 5 business days to determine administrative completeness and then up to 60 calendar days after that to grant or deny the permit -- a statutory ceiling of roughly 65 days. OSFM's own site separately reports an average review time of about 45 days in current practice.

You'll need: OSFM Permit Application (via Permit Self Service online portal); Fire-protection system shop drawings; City of Holbrook Building Permit Application. See the required-documents checklist on this page for details on each.

Holbrook requires 3 inspection(s) for a fire sprinkler and fire alarm system permit, in order: OSFM Field Inspection (Fire Protection System), OSFM Re-inspection (if required), City of Holbrook Final Inspection. Schedule each through City of Holbrook Building Department (928-524-6225).

Apply through City of Holbrook Building Department at City Hall, 465 1st Avenue, Holbrook, AZ 86025. Phone: 928-524-6225, email: rtissaw@holbrookaz.gov. Office hours: Monday - Thursday, 7 a.m. - 5 p.m. (City Hall is closed Fridays on a 4-day/40-hour week; the City's Fee Schedule separately prices Special/Emergency Inspections performed on Fridays at $75/hour, minimum 1 hour, consistent with City Hall's normal 4-day week). Building Inspector Richard Tissaw (joined November 2024) oversees permitting. Applications are submitted via the City's online GOGov permit and licensing platform (app.govoutreach.com/holbrookcityaz/public/permits) or in person/by phone at City Hall.. Official information: https://holbrookaz.gov/departments/building-department/.

Holbrook, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (e.g., A.R.S. Title 9 for municipalities). The City of Holbrook runs its own Building Department, independent of Navajo County, and issues its own construction permits within city limits. Source: City of Holbrook Building Department page (holbrookaz.gov/departments/building-department/).; The City of Holbrook's own published Fee Schedule (adopted November 15, 2025, superseding the September 1, 2025 edition; figures unchanged between the two) states that Building Permit Fees (Commercial/Residential/New/Remodel/Accessory Building) and the Residential Solar System Fee are calculated 'based on IBC/UBC Building Data-IRC 2018 Charts and Formulas,' confirming the 2018 edition of the ICC family of codes (International Building Code / International Residential Code) is the City's current operative code basis for permit valuation. Source: City of Holbrook Fee Schedule, adopted November 15, 2025 (Section 2-1, Section 2-3).; CONFIRMED 2026-07-23 via live-rendered Municode session (the platform is a JavaScript SPA that returns an empty shell to non-browser requests, but renders fully in a real browser): Holbrook City Code Chapter 5 (Building and Construction), Article 5-2 'Uniform Codes,' was repealed and re-enacted in its entirety by Ordinance No. 25-01, § 1 (adopted January 22, 2025) — replacing the former Art. 5-2 (§§ 5-2-1—5-2-13), which had derived from Ordinance 10-11, Ordinance 11-11, and Ord. No. 24-03, § 1 (adopted May 22, 2024). As codified (Supp. No. 2, Update 1, online content updated February 19, 2026; codified through Ordinance No. 25-09, enacted December 10, 2025), Article 5-2 adopts by reference: § 5-2-1 the 1997 Uniform Code for the Abatement of Dangerous Buildings; § 5-2-2 the 2018 International Building Code (IBC), including Appendix J (Grading) and Appendix K (Administrative Provisions — Mechanisms for Enforcement of NFPA 70 National Electrical Code); § 5-2-3 the 1997 Uniform Code for Building Conservation; § 5-2-4 the 2017 edition of the National Electrical Code (NOT 2018 — this is the one code title in the chapter on an older edition year than the rest); § 5-2-5 the 2018 edition of the NFPA Fire Code; § 5-2-6 the 2018 International Fuel Gas Code (IFGC); § 5-2-7 the 2018 International Mechanical Code (IMC); § 5-2-8 the 2018 International Residential Plumbing Code (the codified section title, verbatim); and § 5-2-9 the 2018 International Residential Code (IRC), including Appendices A, B, G, H, J, L, M, P, and Q. Chapter 5 also contains Article 5-1 'Permits and Fees' (§ 5-1-1: a building/construction permit is required whenever the cost of construction, remodeling, or improvement exceeds $1,000, excepting floor/wall-covering replacement, window replacement, roofing, and painting — Ordinance 10-11; § 5-1-4: permit fees are set from time to time by council resolution, i.e. the Fee Schedule) and Article 5-3 'Drainage and Retention Criteria' (stormwater/grading design criteria, unrelated to permit fees or code editions). No climatic/geographic design-criteria table (wind speed, seismic design category, etc.) or plan-review turnaround-time language exists anywhere in Chapter 5's text. Ordinances subsequent to 25-09 (No. 26-01 and No. 26-02, both adopted May 13, 2026) amend Chapter 6 and Chapter 3 respectively — neither touches Chapter 5, so the code editions above remain the most current. Source: Holbrook, AZ Municode Library, Chapter 5 — Building and Construction (library.municode.com/az/holbrook/codes/city_code?nodeId=CH5BUCO), live-rendered 2026-07-23.; Manufactured homes, mobile homes, and factory-built buildings are regulated directly by the State of Arizona (A.R.S. § 41-4001 et seq., Arizona Department of Fire, Building and Life Safety / Office of Manufactured Housing) for construction/installation standards; the City of Holbrook's own building permit process governs on-site placement, foundation/tie-down, and zoning compliance, consistent with statewide practice for Arizona home-rule municipalities. Source: Arizona Department of Fire, Building and Life Safety Office of Manufactured Housing statutory authority (A.R.S. § 41-4001 et seq.); City of Holbrook Building Department confirms it issues its own local permits independent of the County.. Local amendments apply — see the Holbrook overview page for the full list.

No. Even though Holbrook has its own Fire Department and has adopted the 2018 NFPA Fire Code in its own building-code chapter, the Arizona Office of the State Fire Marshal (OSFM) retains statutory jurisdiction over fire-protection-system plan review and permitting here, because Holbrook's population (4,858 per the 2020 Census) is far below the 100,000-person threshold A.R.S. § 37-1383(A)(5) requires for a city to assume that jurisdiction, and Holbrook is not on OSFM's own list of cities that have done so. New or modified fire sprinkler and fire alarm systems must be submitted to OSFM directly, in parallel with the City's own building permit for the structure.

Sources & verification

Verified against official sources. Last reviewed 2026-08-04.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Holbrook building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.