Sign / Monument Permit in Unincorporated Pinal County, Arizona

Unincorporated Pinal County regulates signs on two separate tracks that both apply to the same sign. (1) Building Safety issues a sign building permit under Article 9 of Building Permit Fee Schedule No. 071013-BPFS, but only when the sign meets ALL of the article's criteria (50 sq ft or more, solid material) — or independently when it exceeds 8 feet in height, or when the Building Official determines an attached sign is of significant weight/height. (2) The Planning Division charges its own flat zoning sign fees ($57.00 per sign type; $1,187 for a Comprehensive Sign Package) under the Planning Division Fee Schedule. Signs connected to commercial electrical power (neon, illuminated) require an electrical permit regardless of the size/material criteria.

Verified 2026-08-16 · Source

When you need this permit

  • A building permit is required for signs meeting ALL of: (a) area of 50 sq ft or more, and (b) composed of solid material such as wood, metal or similar (signs of cloth, cardboard, vinyl or other flexible, lightweight material are NOT considered solid material)
  • Signs with a height greater than 8 ft measured from grade to the top of the sign, and made of solid material, require a permit regardless of area
  • Signs attached to an existing building or structure that do not meet the criteria above still require a permit if they are of significant weight or height that could create a danger if displaced, as determined by the Building Official
  • Exception: signs with connections to electrical power from a commercial source (e.g. neon, illuminated) require an electrical permit regardless of the criteria above; UL listing/verification applies
  • Monument/Sign Permit Application must state type of sign (directional, free standing, wall mounted, flag pole, illuminated, other), height of sign, number of faces, and total square feet of sign
  • Application must state existing use and proposed use of the property, plus parcel number, legal description (subdivision/unit/block/lot, section/township/range), and parcel size
  • Application must identify whether sign illumination will require installation of a new meter
  • Contractor license number and class required on the application Contractor
  • Permits are picked up at the Florence office; applications are not accepted via mail or e-mail (submit online through the Citizen Access Portal or in person)
  • Separate Planning Division sign approval and fee apply in addition to the Building Safety permit — see the Planning Division Fee Schedule (Signs section)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Sign permit fee — by sign area (Article 9, Section 901, Sign Fee Schedule)Building Permit Fee Schedule No. 071013-BPFS, Article 9 (Sign Permit Fees), Section 901 — read from a 200-dpi page render of page 12 of 13, not from text extraction. Source: https://www.pinal.gov/DocumentCenter/View/475. Note the schedule as printed does not compute the plan review column at a uniform 65% of the permit fee in every row (e.g. the 101–110 sq ft row prints $49.60 / $30.29); the figures above are reproduced exactly as published rather than recomputed.
0–90 sq ft: $42.00 permit / $27.30 plan review; 91–100: $45.10 / $29.32; 101–110: $49.60 / $30.29; 111–120: $54.15 / $35.19; 121–130: $58.65 / $38.12; 131–140: $63.15 / $41.05; 141–150: $67.65 / $43.97; 151–160: $72.15 / $46.90; 161–170: $76.65 / $49.82; 171–180: $81.20 / $52.78; 181–190: $85.70 / $55.71; 191–200: $90.20 / $58.63
Sign permit fee — over 200 sq ftFee Schedule No. 071013-BPFS, Article 9 (page 12 of 13, read from render).
$90.20 plus $4.50 for each additional 10 sq ft, or portion thereof; plan review fee 65% of the calculated permit fee
Illuminated sign surchargeFee Schedule No. 071013-BPFS, Article 9 (page 12 of 13, read from render).
Add $22.00 for signs supplied by one branch circuit; add $4.25 for each additional branch circuit to the same sign
Planning Division zoning sign feesPinal County Planning Division Fee Schedule, SIGNS section — published as a live HTML fee table on the county's own site (no PDF extraction involved). Source: https://www.pinal.gov/230/Fee-Schedule. These are separate from, and in addition to, the Building Safety Article 9 sign permit fee.
Signs and Temporary Signs: $57; On-Site Signs: $57; Off-Site Directional Signs: $57; Comprehensive Sign Package: $1,187
Resubmittal of a denied or withdrawn sign applicationPinal County Planning Division Fee Schedule, 'Resubmittal of Project Fees' — the definition names Sign Permits, Temporary Signs and Comp Sign Review among the project types that fall within the County's official Project Review Time frames and therefore qualify for the 50% resubmittal rate.
50% of the original fees that have not been refunded

Review timeline

Plan reviewUnincorporated Pinal County’s published plan-review target
10–45 business days

How long did your Sign / Monument Permit permit actually take in Unincorporated Pinal County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Footing / Foundation (free-standing and monument signs)

    Before concrete pour for sign footings — verify depth, dimensions and reinforcement per approved plans and the 2018 IBC as adopted

  2. 2

    Electrical (illuminated signs)

    Wiring and branch circuit(s) serving an illuminated sign inspected under the separate electrical permit required by Article 9's illumination exception, per the 2017 NEC as adopted

  3. 3

    Final

    Sign erected per approved plans; schedule via the automated inspection line 520-866-6299 (call before midnight the day before for next-working-day inspection)

See the full Unincorporated Pinal County inspection guide — scheduling & re-inspection fees →

Tips

  • Read Article 9's criteria carefully before assuming you need a Building Safety sign permit: the 50 sq ft / solid-material test is conjunctive, so a large vinyl or cloth banner does not trigger the building permit — but a solid-material sign taller than 8 feet does, regardless of area.
  • Budget for TWO county fees on the same sign: the Building Safety Article 9 permit fee (area-based) and the Planning Division's flat zoning sign fee ($57 per sign type, or $1,187 for a Comprehensive Sign Package).
  • Any sign wired to commercial power — neon or otherwise illuminated — needs an electrical permit even if it is under 50 sq ft and under 8 feet tall. The illuminated surcharge ($22.00 for the first branch circuit, $4.25 each additional) is charged on top of the area-based sign fee.
  • The application asks whether sign illumination will require a new meter — sort that out with your utility before applying, because the utility runs its own separate equipment inspection that county clearance does not substitute for.

Frequently asked questions

You need a Building Safety sign building permit if the sign is 50 sq ft or more AND made of solid material such as wood or metal; or if it is made of solid material and taller than 8 ft measured from grade to the top of the sign, regardless of area; or if the Building Official determines an attached sign is of significant weight or height that could create a danger if displaced. Signs of cloth, cardboard, vinyl or other flexible lightweight material are not 'solid material' for this test. Separately, any sign connected to commercial electrical power requires an electrical permit regardless. Source: Building Permit Fee Schedule No. 071013-BPFS, Article 9 (https://www.pinal.gov/DocumentCenter/View/475)

Building Safety charges by sign area under Article 9: $42.00 for 0–90 sq ft up to $90.20 for 191–200 sq ft, plus $4.50 for each additional 10 sq ft over 200 sq ft, with a separate plan review fee shown per row. Illuminated signs add $22.00 for the first branch circuit and $4.25 for each additional branch circuit. The Planning Division charges its own flat zoning sign fee of $57 (or $1,187 for a Comprehensive Sign Package). Sources: https://www.pinal.gov/DocumentCenter/View/475 and https://www.pinal.gov/230/Fee-Schedule

Unincorporated Pinal County's published plan-review target for a sign / monument permit is 10–45 business days.

You'll need: Monument/Sign Permit Application. Depending on your project, Unincorporated Pinal County may also ask for: Property Owner Authorization Form. See the required-documents checklist on this page for details on each.

Unincorporated Pinal County requires 3 inspection(s) for a sign / monument permit, in order: Footing / Foundation (free-standing and monument signs), Electrical (illuminated signs), Final. Schedule each through Pinal County Building Safety Division (Community Development Department) (520-509-3555).

Apply through Pinal County Building Safety Division (Community Development Department) at 85 N. Florence Street, 1st Floor, Florence, AZ 85132 (mailing: P.O. Box 749, Florence, AZ 85132). Phone: 520-509-3555. Office hours: Monday–Friday 8:00 AM – 4:30 PM (Florence office). District offices in Apache Junction, Oracle, and Casa Grande are listed on department bulletins but noted as closed for Community Development as of the most recent published bulletin (Information Bulletin 004, Oct 2022) — confirm current district-office status by phone before visiting. Toll-free: 1-800-208-6897. Automated inspection line: 520-866-6299 (call before midnight the day before to get the next working day; areas of Mammoth, San Manuel, Dudleyville, Kearny, Superior & Top of the World are inspected only on Wednesdays).. Official information: https://www.pinal.gov/189/Building-Safety.

Unincorporated Pinal County, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9 for cities, A.R.S. §11-861 et seq. for counties). Pinal County's Building Safety Division administers construction codes directly for all unincorporated areas of the county under Pinal County Development Services Code Title 6, Chapter 6.05, and — per confirmed intergovernmental agreements (IGAs) — for the incorporated towns of Kearny, Superior, and Mammoth, which do not run their own building departments. Source: Pinal County Ordinance No. 121819-BCO (adopted 18 December 2019, effective 30 days later) and Information Bulletin 011 (Dec 2022), which lists Mammoth, San Manuel, Dudleyville, Kearny, Superior & Top of the World as areas the department directly inspects.; 2018 International Building Code (IBC), adopted with Pinal County amendments (Ordinance No. 121819-BCO, Exhibit A), including adopted Appendix I (Patio Covers), Appendix J (Grading), and Appendix K (ICC Electrical Code).; 2018 International Residential Code (IRC), adopted with Pinal County amendments (Ordinance No. 121819-BCO, Exhibit B), including adopted Appendices A, B, C, H, J, N, P, and S.; 2018 International Property Maintenance Code (IPMC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit C).; 2018 International Mechanical Code (IMC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit D).; 2018 International Plumbing Code (IPC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit E).; 2017 National Electrical Code (NEC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit F), including adopted Annex H (Administration and Enforcement).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit J).; 2018 International Energy Conservation Code (IECC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit I).; 2018 International Fuel Gas Code (IFGC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit G).; 2018 International Fire Code (IFC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit H), including adopted Appendix B (Fire Flow Requirements) and Appendix D (Fire Apparatus Access).. Local amendments apply — see the Unincorporated Pinal County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-08-16.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Pinal County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.