EV Charger / EVSE Permit in Unincorporated Pinal County, Arizona

Pinal County does not publish a distinct EV charger/EVSE fee line. Installing electric vehicle charging equipment in unincorporated Pinal County requires a Mechanical/Plumbing/Electrical (MPE) Electrical Permit under the 2017 NEC with county amendments, billed under the Article 4 unit-fee schedule (Fee Schedule No. 071013-BPFS): a flat issuance fee plus itemized per-service and per-fixture fees. A typical Level 2 EV charger circuit is billed as a new circuit/service item under this same schedule.

Verified 2026-07-20 · Source

When you need this permit

  • Mechanical/Plumbing/Electrical (MPE) Application required for EV charger/EVSE circuit installation in unincorporated Pinal County
  • Site plan noting placement of any new panel/subpanel (location on structure) required with application
  • Utility companies require their own separate inspection/clearance of service equipment in addition to county clearance
  • Documentation should show location of electric meter, electric panel, and new charging station, plus a one-line diagram with conductor/conduit sizes and overcurrent protection calculations, consistent with the county's general electrical permit submittal requirements
  • No distinct EV charger/EVSE fee line, expedited timeline, or SolarAPP+-style instant-permitting platform was found published by the county as of this review

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Electrical permit issuanceFee Schedule No. 071013-BPFS, Article 4 — same base issuance fee documented on this jurisdiction's Electrical Permit entry; no distinct EV charger/EVSE fee line is published.
$42.00 (plus $6.50 per supplemental permit on an unexpired original permit)
Services 600V or less, ≤200 amps (typical EV charger circuit/service)Fee Schedule No. 071013-BPFS, Article 4, Section 7.
$27.25 each
Receptacle/switch/lighting outlets and fixturesFee Schedule No. 071013-BPFS, Article 4, Sections 1-2 — applicable if the EVSE is billed as a fixture/outlet rather than under the service fee.
$1.00 each for first 20; $0.65 each additional

Review timeline

Plan reviewTypical estimate — confirm current times with the Unincorporated Pinal County building department
~10–45 business days

How long did your EV Charger / EVSE Permit permit actually take in Unincorporated Pinal County?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In / Service Inspection

    EVSE circuit and any service/panel work inspected before wall cover or energizing; call the automated inspection line (520-866-6299) before midnight the day before

  2. 2

    Final

    All EVSE electrical work complete and operational per 2017 NEC

See the full Unincorporated Pinal County inspection guide — scheduling & re-inspection fees →

Tips

  • Pinal County has no distinct EV charger/EVSE fee — installation is billed under the same Article 4 unit-fee schedule as any other electrical permit: a $42 issuance fee plus itemized per-service/per-fixture fees.
  • County clearance does not guarantee the utility company will energize your service — utilities have their own separate equipment inspection requirements, same as for any other electrical service work.

Frequently asked questions

Unincorporated Pinal County requires an ev charger / evse permit for: Mechanical/Plumbing/Electrical (MPE) Application required for EV charger/EVSE circuit installation in unincorporated Pinal County; Site plan noting placement of any new panel/subpanel (location on structure) required with application; Utility companies require their own separate inspection/clearance of service equipment in addition to county clearance; Documentation should show location of electric meter, electric panel, and new charging station, plus a one-line diagram with conductor/conduit sizes and overcurrent protection calculations, consistent with the county's general electrical permit submittal requirements; No distinct EV charger/EVSE fee line, expedited timeline, or SolarAPP+-style instant-permitting platform was found published by the county as of this review. If your project isn't listed, confirm with Pinal County Building Safety Division (Community Development Department) at 520-509-3555 before starting work.

No distinct EV charger/EVSE fee line item is published. Installation is billed as a standard MPE Electrical Permit under the Article 4 unit-fee schedule: a $42 issuance fee plus itemized per-service fees (e.g., $27.25 for a service up to 200 amps). Source: Building Permit Fee Schedule No. 071013-BPFS.

Plan review for an ev charger / evse permit in Unincorporated Pinal County typically runs 10–45 business days. This is an estimate, not a published figure — confirm current review times with Pinal County Building Safety Division (Community Development Department) at 520-509-3555.

You'll need: Mechanical/Plumbing/Electrical (MPE) Application. Depending on your project, Unincorporated Pinal County may also ask for: Information Bulletin 011 — MEP Permits. See the required-documents checklist on this page for details on each.

Unincorporated Pinal County requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In / Service Inspection, Final. Schedule each through Pinal County Building Safety Division (Community Development Department) (520-509-3555).

Apply through Pinal County Building Safety Division (Community Development Department) at 85 N. Florence Street, 1st Floor, Florence, AZ 85132 (mailing: P.O. Box 749, Florence, AZ 85132). Phone: 520-509-3555. Office hours: Monday–Friday 8:00 AM – 4:30 PM (Florence office). District offices in Apache Junction, Oracle, and Casa Grande are listed on department bulletins but noted as closed for Community Development as of the most recent published bulletin (Information Bulletin 004, Oct 2022) — confirm current district-office status by phone before visiting. Toll-free: 1-800-208-6897. Automated inspection line: 520-866-6299 (call before midnight the day before to get the next working day; areas of Mammoth, San Manuel, Dudleyville, Kearny, Superior & Top of the World are inspected only on Wednesdays).. Official information: https://www.pinal.gov/189/Building-Safety.

Unincorporated Pinal County, Arizona has adopted: Arizona has NO statewide mandatory building code floor for general construction — code adoption is a per-city/county authority under state enabling statutes (A.R.S. Title 9 for cities, A.R.S. §11-861 et seq. for counties). Pinal County's Building Safety Division administers construction codes directly for all unincorporated areas of the county under Pinal County Development Services Code Title 6, Chapter 6.05, and — per confirmed intergovernmental agreements (IGAs) — for the incorporated towns of Kearny, Superior, and Mammoth, which do not run their own building departments. Source: Pinal County Ordinance No. 121819-BCO (adopted 18 December 2019, effective 30 days later) and Information Bulletin 011 (Dec 2022), which lists Mammoth, San Manuel, Dudleyville, Kearny, Superior & Top of the World as areas the department directly inspects.; 2018 International Building Code (IBC), adopted with Pinal County amendments (Ordinance No. 121819-BCO, Exhibit A), including adopted Appendix I (Patio Covers), Appendix J (Grading), and Appendix K (ICC Electrical Code).; 2018 International Residential Code (IRC), adopted with Pinal County amendments (Ordinance No. 121819-BCO, Exhibit B), including adopted Appendices A, B, C, H, J, N, P, and S.; 2018 International Property Maintenance Code (IPMC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit C).; 2018 International Mechanical Code (IMC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit D).; 2018 International Plumbing Code (IPC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit E).; 2017 National Electrical Code (NEC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit F), including adopted Annex H (Administration and Enforcement).; 2018 International Swimming Pool and Spa Code (ISPSC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit J).; 2018 International Energy Conservation Code (IECC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit I).; 2018 International Fuel Gas Code (IFGC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit G).; 2018 International Fire Code (IFC), adopted with amendments (Ordinance No. 121819-BCO, Exhibit H), including adopted Appendix B (Fire Flow Requirements) and Appendix D (Fire Apparatus Access).. Local amendments apply — see the Unincorporated Pinal County overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Pinal County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.