Sign Permit in Northglenn, Colorado
City of Northglenn Unified Development Ordinance (UDO), Chapter 11, Section 11-4-10 (Signs) requires a permit before any sign is erected, mounted, displayed, remodeled, reconstructed, maintained, or moved within the City, except as expressly exempted. Applications go to the Building Department; the Director must approve or deny a complete application within seven days, per Section 11-4-10(d)(2)(C).
Verified 2026-08-14 · Source
When you need this permit
- No sign shall be erected, mounted, displayed, remodeled, reconstructed, maintained, or moved without first securing a permit from the City, per Sec. 11-4-10(d)(1)
- Application obtained from and submitted to the Building Department, per Sec. 11-4-10(d)(2)(A)
- Sign permit fees are based on the building permit fees in the International Building Code in place at the time of application; sign valuation is determined using the Colorado State Tax Commission Manual in effect at application time, per Sec. 11-4-10(d)(2)(B)
- All electrical work on a sign must be performed by a Colorado-licensed electrician under a separate valid City electrical permit — no electrical work may be performed without one, per Sec. 11-4-10(b)(3) Contractor
- Certain small/unobtrusive signs are exempt from a permit (e.g., building directory signs up to 15 sq ft, certain directional signs, flags meeting specified limits, small balloon groupings) but remain subject to all other applicable code provisions
- A denied applicant is contacted within three days to explain the reason; if no agreement is reached, a written notice of denial is prepared within 10 days of the decision, describing appeal rights
- Denials may be appealed to the Board of Adjustment per Sec. 11-6-7(d)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
See the full Northglenn inspection guide — scheduling & re-inspection fees →
Tips
- The Director's 7-day clock only starts once the application is COMPLETE — an incomplete submittal doesn't start the countdown, so submit a fully documented application to get the fastest turnaround.
- Sign permit fees piggyback on the IBC building-permit fee table applied to the sign's valuation (per the Colorado State Tax Commission Manual) rather than a flat sign-specific fee — get your contractor's sign valuation figure ready before applying.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Northglenn building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Northglenn
Sign Permit in other cities
Compare sign permit fees across Colorado →