Commercial Tenant Improvement / Tenant Finish Permit in Northglenn, Colorado

Required for tenant finish-out and remodels of existing commercial space in Northglenn. The City's Building Division (via SAFEbuilt) publishes a dedicated 'Commercial Tenant Finish/Remodel Plan Submittal Procedure' checklist — genuinely lighter than the New Commercial checklist (no site plan or soils report required) — that covers both tenant finish and commercial remodel scope in one combined process. CommunityCore's Pull a Permit page lists 'Tenant Finish'/'Tenant Finishes' and 'Commercial Remodels' as separate line items under its 'Plan Review Permit' category, but the underlying SAFEbuilt submittal document treats them as one procedure.

Verified 2026-08-02 · Source

When you need this permit

  • Building permit application must state project description, square footage, total project valuation, electrical valuation, use of surrounding spaces, type of construction, and occupancy group
  • Architectural, structural, electrical, and mechanical/plumbing plans must each bear the original seal of a Colorado-licensed architect or engineer per C.R.S. 12-4-112, unless specifically exempted; electronic stamps are accepted
  • Architectural plans are required and must include floor plan, wall section details, building section, fire-rating details, and code summary
  • Structural plans are required only for structural changes: removal of bearing walls, openings in bearing walls, floor systems for storage, etc.
  • Electrical plans are required for adding circuits, service upgrades, or emergency lighting, and must include load calculations, one-line diagrams, and fault current analysis
  • Mechanical plans are required for any HVAC changes: change of equipment, relocation and/or replacement of ductwork or refrigeration piping
  • Plumbing plans are required for any changes to sewers, drains, vents, water piping, roof drains, or gas piping within the building
  • Documentation showing compliance with the 2021 IECC (Energy Code) is required
  • Tenant finish-outs that are restaurants or commercial kitchens carry the same additional requirements as new commercial construction: grease interceptor, sprinklers over 5,000 SF, Type I/II hoods, occupant-load-50+ egress rules, health department approval, and a seating plan
  • 'Tenant Finish' is a CommunityCore 'Plan Review Permit' category — documents must be uploaded to the portal's Documents tab before application submittal, unlike the same-visit Quick Permit track used for most standalone trade work
  • All contractors must hold a current City of Northglenn contractor license and be listed on the permit before issuance Contractor
  • The Fees & Taxes page explicitly confirms the plan check fee 'is collected on commercial jobs (both new and tenant finish)'
  • Although not required, SAFEbuilt advises a pre-submittal meeting with SAFEbuilt and the fire protection district before formally applying

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (general Valuation Chart, same schedule used for all Northglenn permit types)No separate tenant-finish-specific fee table is published; billed under the same Valuation Chart as new commercial construction and residential work. City of Northglenn Fees & Taxes page
$23.50 minimum, scaling per the valuation tiers
Plan Review FeeFees & Taxes page explicitly states the plan check fee is collected on commercial jobs, both new and tenant finish
65% of the Building Permit Fee
Use Tax
Total valuation x 50% (assumed materials share) x 4% assessed rate
Reinspection Fee
$75/hour

Review timeline

Plan reviewNorthglenn’s published plan-review target
14–30 business days

How long did your Commercial Tenant Improvement / Tenant Finish Permit permit actually take in Northglenn?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical/Plumbing/Mechanical

    Trade rough-ins before concealment, where applicable to the scope of work

  2. 2

    Framing (if structural changes)

    Bearing wall removal/openings or new floor systems for storage, if applicable

  3. 3

    Fire Protection System Inspection

    If a fire protection system is part of the design; coordinated with North Metro Fire Rescue District

  4. 4

    Health Department Approval

    Required as a Certificate of Occupancy prerequisite for restaurant/food-service tenant finishes; approval documentation must be on the jobsite before final inspection

  5. 5

    Final Inspection

    All work complete per approved plans and applicable codes

See the full Northglenn inspection guide — scheduling & re-inspection fees →

Tips

  • Northglenn's tenant finish/remodel submittal package is genuinely lighter than its new-construction package — no site plan or soils report is required, and structural/electrical/mechanical plans are only required if that discipline's scope is actually touched.
  • The City's own SAFEbuilt-authored checklist bundles 'tenant finish' and 'remodel' into one combined submittal procedure, even though CommunityCore's permit-type picker lists 'Tenant Finish' and 'Commercial Remodels' as separate line items — expect the same document requirements either way.
  • Restaurant/food-service tenant finishes trigger the same extra requirements as new commercial restaurant construction (grease interceptor, hood types, sprinklers over 5,000 SF, health department sign-off) — budget for these even on a small buildout.
  • No tenant-finish-specific review timeline is published — the same 14-20 (under $1M) / 21-30 (at or above $1M) business day commercial tiers that apply to new construction govern tenant finish plan review.

Frequently asked questions

Northglenn requires a commercial tenant improvement / tenant finish permit for: Building permit application must state project description, square footage, total project valuation, electrical valuation, use of surrounding spaces, type of construction, and occupancy group; Architectural, structural, electrical, and mechanical/plumbing plans must each bear the original seal of a Colorado-licensed architect or engineer per C.R.S. 12-4-112, unless specifically exempted; electronic stamps are accepted; Architectural plans are required and must include floor plan, wall section details, building section, fire-rating details, and code summary; Structural plans are required only for structural changes: removal of bearing walls, openings in bearing walls, floor systems for storage, etc.; Electrical plans are required for adding circuits, service upgrades, or emergency lighting, and must include load calculations, one-line diagrams, and fault current analysis; Mechanical plans are required for any HVAC changes: change of equipment, relocation and/or replacement of ductwork or refrigeration piping; Plumbing plans are required for any changes to sewers, drains, vents, water piping, roof drains, or gas piping within the building; Documentation showing compliance with the 2021 IECC (Energy Code) is required; Tenant finish-outs that are restaurants or commercial kitchens carry the same additional requirements as new commercial construction: grease interceptor, sprinklers over 5,000 SF, Type I/II hoods, occupant-load-50+ egress rules, health department approval, and a seating plan; 'Tenant Finish' is a CommunityCore 'Plan Review Permit' category — documents must be uploaded to the portal's Documents tab before application submittal, unlike the same-visit Quick Permit track used for most standalone trade work; All contractors must hold a current City of Northglenn contractor license and be listed on the permit before issuance; The Fees & Taxes page explicitly confirms the plan check fee 'is collected on commercial jobs (both new and tenant finish)'; Although not required, SAFEbuilt advises a pre-submittal meeting with SAFEbuilt and the fire protection district before formally applying. If your project isn't listed, confirm with City of Northglenn Building Division (operated under contract by SAFEbuilt) at 303.450.8745 before starting work.

In Northglenn, the published Building Permit Fee (general Valuation Chart, same schedule used for all Northglenn permit types) is: $23.50 minimum, scaling per the valuation tiers. Additional published fees: Plan Review Fee — 65% of the Building Permit Fee; Use Tax — Total valuation x 50% (assumed materials share) x 4% assessed rate; Reinspection Fee — $75/hour. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City does not publish a tenant-finish-specific timeline; 'Tenant Finish' falls under the same Plan Review Permit category as new commercial construction, so the published commercial figures apply: 14-20 business days for jobs under $1 million, 21-30 business days for jobs at or above $1 million.

You'll need: Building Permit Application (CommunityCore); Architectural Plans; 2021 IECC Energy Code Compliance Documentation. Depending on your project, Northglenn may also ask for: Structural Plans; Electrical Plans; Mechanical/Plumbing Plans. See the required-documents checklist on this page for details on each.

Northglenn requires 5 inspection(s) for a commercial tenant improvement / tenant finish permit, in order: Rough Electrical/Plumbing/Mechanical, Framing (if structural changes), Fire Protection System Inspection, Health Department Approval, Final Inspection. Schedule each through City of Northglenn Building Division (operated under contract by SAFEbuilt) (303.450.8745).

Apply through City of Northglenn Building Division (operated under contract by SAFEbuilt) at 11701 Community Center Drive, Northglenn, CO 80233. Phone: 303.450.8745, email: building@northglenn.org. Office hours: Weekdays, 8:30 a.m. to 4:30 p.m., except holidays; Inspection Request Line 303.450.8748 (call before 4 p.m. for next-work-day scheduling). Official information: https://www.northglenn.org/government/departments/building/.

Northglenn, Colorado has adopted: 2021 International Building Code (IBC), adopted by reference and locally amended — City of Northglenn Building Division code list, https://www.northglenn.org/government/departments/building/index.php; 2021 International Residential Code (IRC), adopted by reference and locally amended, including a locally-filled Table R301.2(1) Climatic and Geographic Design Criteria — source PDF: https://cms7files.revize.com/northglennco/IRC%202021.pdf; 2021 International Existing Building Code (IEBC); 2021 International Fire Code (IFC); 2021 International Mechanical Code (IMC); 2021 International Plumbing Code (IPC); 2021 International Fuel Gas Code (IFGC); 2021 International Energy Conservation Code (IECC); 2021 International Property Maintenance Code (IPMC); 2021 International Swimming Pool and Spa Code (ISPSC); 2023 National Electrical Code (NEC), adopted by reference and locally amended; 2017 ICC A117.1 Accessible and Usable Buildings and Facilities; 1997 Uniform Code for the Abatement of Dangerous Buildings, as amended; Municode Northglenn Chapter 10 (Building Regulations) governs adoption: Article 10-1 (Building Department administration), Article 10-2 (IBC amendments), Article 10-7 (IFGC), Article 10-8 (IRC amendments), Article 10-11 (IECC), Article 10-16 (IPMC), Article 10-17 (IEBC), Article 10-18 (Contractor Licenses) — https://municode.northglenn.org/ch10/chapter_10.html; NOTE (per City's own Building Division page): Northglenn is scheduled to adopt the suite of 2024 ICC codes by summer 2026 and the 2026 NEC immediately following State of Colorado adoption (slated for adoption August 2026) — confirm current edition in force at time of permitting. Local amendments apply — see the Northglenn overview page for the full list.

Yes, it's a distinct process with its own City-published checklist ('Commercial Tenant Finish/Remodel Plan Submittal Procedure'), and the required submittal package is lighter — no site plan or soils report, and structural/electrical/mechanical plans are only required for the disciplines actually affected by the scope. Fees (general Valuation Chart, 65% plan review fee) and the commercial review timeline are the same as new construction.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Northglenn.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.