Fire Sprinkler and Fire Alarm Permit — Centennial, Colorado · Requirements sheet
Verified 2026-08-13 · Source: https://www.southmetro.org/development-construction
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Fire Sprinkler and Fire Alarm Permit in Centennial, Colorado
Fire code (2021 IFC) in Centennial is enforced by South Metro Fire Rescue (SMFR), a separate special fire protection district headquartered in Centennial itself (9195 E. Mineral Ave.) — NOT the City Building Division. All fire sprinkler and fire alarm permits (new installation, alteration, and modification) are submitted, reviewed, and inspected directly through SMFR's own Accela Permit Portal, a genuinely separate process and fee schedule from the City's Self-Service Portal used for building/electrical/plumbing/mechanical permits documented elsewhere in this file.
Verified 2026-08-13 · Source
When you need this permit
- Fire sprinkler and fire alarm permits are handled entirely by South Metro Fire Rescue (SMFR), not the City of Centennial Building Division; applications are submitted through SMFR's own Accela Permit Portal (aca-prod.accela.com/SOUTHMETROFIRE), a separate system from the City's EnerGov-based Self-Service Portal
- SMFR's stated plan review turnaround-time GOAL is comments back to the applicant within 5 business days or less, 90% of the time; projects with higher complexity or during high-volume periods may take longer — this is a published goal, not a guaranteed maximum
- Over-the-Counter (OTC) same-day plan review is available for qualifying scopes if requested at submittal: (1) alterations to existing wet-pipe fire sprinkler systems, light or ordinary hazard classification, up to 50 sprinkler heads, with no impact to the hydraulic design; (2) fire alarm system alterations involving substitution/relocation of up to 25 devices or the new addition of up to 10 devices; (3) emergency replacement of all or part of a fire alarm control panel or dialer (except where the building has a smoke management or smoke control system); (4) access control systems involving a maximum of 20 access points. Submissions received by 11:00 a.m. receive comments by the end of that business day
- New fire sprinkler and new fire alarm systems installed with new construction or a tenant improvement are billed under SMFR's occupancy-and-size-tiered 'New Construction and Tenant Improvements' fee table rather than the smaller per-system 'Modification' fee lines used for alterations to an already-installed system
- Construction inspections are scheduled via the Accela Permit Portal; requests received by 4:00 p.m. are conducted the next business day unless a later date (up to 5 business days out) is requested
- All SMFR-issued permits and approved plans must remain on-site for the duration of the project; if not present when the inspector arrives, the inspection will not be performed and re-inspection fees may apply
- SMFR does not conduct construction inspections that involve activating fire alarm notification devices in occupied buildings; where the scope requires this, an 'After Hours Inspection' must be requested at least 2 business days in advance, at an additional fee per SMFR's current fee schedule
- Performing sprinkler or alarm work without a permit or approval results in a fee of two times (2x) the amount of the original permit fee
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough-In / System Inspection
Piping, heads, wiring, and panel installed before concealment; scheduled via the Accela Permit Portal; requests received by 4:00 p.m. are conducted the next business day
- 2
Final / Acceptance
System tested per the applicable NFPA standard; approved plans and the issued permit must be on-site or the inspection will not be performed
See the full Centennial inspection guide — scheduling & re-inspection fees →
Tips
- This is a genuinely separate agency, portal, and fee schedule from the City of Centennial Building Division: fire sprinkler and alarm permits go through South Metro Fire Rescue's own Accela Permit Portal, not the City's Self-Service Portal used for the building/electrical/plumbing/mechanical permits documented elsewhere in this file.
- South Metro Fire Rescue is headquartered in Centennial itself (9195 E. Mineral Avenue, Centennial CO 80112), reinforcing (alongside this file's existing codesAdopted/localAmendments entries) that SMFR is Centennial's fire-code Authority Having Jurisdiction, not an outside contractor.
- New sprinkler/alarm systems tied to new construction or a tenant improvement are NOT billed under the smaller 'Modification' fee lines — they're billed under SMFR's much larger occupancy-and-size-tiered 'New Construction and Tenant Improvements' table instead.
- Ask specifically for Over-the-Counter (OTC) review when submitting a qualifying small alteration (up to 50 sprinkler heads, up to 25 substituted/relocated or up to 10 new alarm devices) — same-day comments if submitted by 11 a.m., versus the standard 5-business-day-or-less goal.
- SMFR will not perform an inspection that activates fire alarm notification devices in an occupied building during a routine visit — budget for a separate After-Hours Inspection request (2 business days advance notice, additional fee) if your scope requires live activation testing.
- Skipping the permit doesn't just risk a stop-work order — SMFR explicitly doubles the assessed fee for work performed without a permit or approval.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centennial building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Centennial
Fire Sprinkler and Fire Alarm Permit in other cities
Compare fire sprinkler and fire alarm permit fees across Colorado →
Look up this fee in a different city →