EV Charger / EVSE Permit — Centennial, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.centennialco.gov/Government/Departments/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / EVSE Permit in Centennial, Colorado
Centennial has no standalone EV-charger/EVSE permit type or fee line item. Installing electric vehicle charging equipment is electrical work, governed by the 2023 National Electrical Code (NEC) as currently adopted by the City, and per the electrical-permit entry it is billed under the City's 'All Other Electrical Fees' table (Electrical Fee Table Section B) — the same value-based category used for garage and shop circuits, PV service connections, and temporary meters, not the living-area-based residential table. The published figure is $100.00 flat for an installation valued at $2,000 or less, from the City's Building Permit Fee Schedule PDF. That schedule does not itemize an EV-charger-specific line, and the City's 'One-Stop Permit' fast-track is limited to 'Electric Service Change' (replacement of a service or its components without additional load), which does not obviously extend to new EV charger circuits since those typically add load rather than replace existing service — confirm with the City before assuming the fast-track applies. Separately, Colorado's HB24-1173 (C.R.S. Sec. 31-23-316) requires municipalities with population 10,000+ — Centennial's 2020 Census population is approximately 108,300 — to adopt a standardized EV-charging LAND-USE permitting process, adopt the state's model land use code, or formally opt out, by December 31, 2025. No ordinance or resolution addressing that requirement appears in the City's Municode library, its Council legislative history, or the Colorado Energy Office's compliance page.
Verified 2026-07-20 · Source
When you need this permit
- EV charger circuit installation is electrical work; apply online through the Centennial Self-Service Portal using the standard Electrical Permit Application
- Governed by the 2023 NEC as currently adopted by the City of Centennial
- Electrical contractors must be licensed by the Colorado Electrical Board and register with the City on the Electrical Registration Form (no City registration fee) Contractor
- Billed under the 'All Other Electrical Fees' (non-living-area installations) value-based table, since an EV charger circuit is not a living-area square-footage item
- If the installation is limited to a pure service change with no added load, it may qualify for the City's One-Stop Permit fast track -- not independently confirmed as applying to EV chargers specifically
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
City of Centennial Building Permit Fee Schedule (PDF), Electrical Fee Table Section B; Show full citationHide
City of Centennial Building Permit Fee Schedule (PDF), Electrical Fee Table Section B; based on total cost to customer of labor, materials, and items. No distinct EV-charger line item exists -- billed under this general non-living-area electrical category, same as garage/shop circuits, PV service connections, and temporary metersReview timeline
Inspection process
- 1
Rough-In
New circuit wiring, box placement, and panel connections before walls are closed, if applicable
- 2
Final
Charger unit installed, devices connected, panel labeled per the 2023 NEC as adopted
See the full Centennial inspection guide — scheduling & re-inspection fees →
Tips
- An EV charger circuit is billed under Centennial's 'All Other Electrical Fees' (non-living-area) table, not the living-area square-footage residential electrical table -- expect a flat $100 minimum fee for installations valued at $2,000 or less.
- Confirm with the Building Division whether your specific EV charger installation (especially if it involves only a service change, no new load) can qualify for the City's same-day One-Stop Permit track, since that classification is currently named only for 'Electric Service Change' work.
- Centennial's population exceeds the 10,000-resident threshold that triggers HB24-1173's land-use EV-charging permitting-process compliance requirement (deadline December 31, 2025), but no distinct compliance ordinance was found published as of the last verification -- this doesn't change the electrical permit fee itself, but confirm current land-use process status with the City if installing publicly-accessible charging infrastructure.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centennial building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Property Access
Centennial's permit history is searchable by address
152,757 permits on record for Centennial, 2005–2026 — searchable by street address, with permit type, status, issued date and valuation where the city publishes them.
Other permits in Centennial
EV Charger / EVSE Permit in other cities
Compare ev charger / evse permit fees across Colorado →
Look up this fee in a different city →