Commercial Building Permit (New Construction) — Centennial, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://www.centennialco.gov/Government/Departments/Building
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Commercial Building Permit (New Construction) in Centennial, Colorado
Required for any new commercial buildings or developments in Centennial ('Commercial New' classification, which the City's Building Permit Review Schedule also applies to commercial additions). Reviewed against the currently adopted 2021 IBC and Centennial Municipal Code Chapter 18 local amendments (Sec. 18-2-30 climatic/geographic design criteria: 30 psf non-reducible snow load, 115 mph wind speed). Plans must be signed and sealed by a Colorado registered design professional. A SEPARATE application and permit from South Metro Fire Rescue is required for most commercial projects — the only exceptions are commercial one-stop permits, commercial roof/re-roof permits, and commercial window/door permits.
Verified 2026-08-02 · Source
When you need this permit
- 'Commercial New' classification covers 'any new commercial buildings or developments', per the City's Building Permit Classifications page
- Complete signed and sealed (by a Colorado registered design professional) architectural plans, structural plans, and material specifications must be submitted online to Centennial's Self-Service Portal
- Online application must include contractor name/phone/address, owner name/address/phone, a designated contact person, project address, and estimated project value (all materials and labor)
- Site plan (recommended scale 1/8" = 1'-0") showing all new and existing structures, lot dimensions, building footprint with dimensions to property lines, north arrow, easements, all parking including accessible spaces/access aisles/curb ramps, accessible route from the public way, and any retaining walls (which require separate permits)
- Architectural plans must include occupancy classification(s) for all portions of the building, mixed-use design approach, construction type, dimensioned area/height drawings, means-of-egress details with occupant loads, exit signage/egress lighting, accessibility scoping, special-occupancy details (covered mall, high-rise, mezzanine, atrium, public garage), fire-resistive construction details, and plastic/insulation/safety-glazing details
- Structural submittal must include a soils report (soil type, allowable bearing pressure, foundation type), signed and sealed structural calculations, local design load criteria per Centennial Municipal Code Sec. 18-2-30 Table R301.2(1), foundation/superstructure details, and provisions for required special inspections
- Mechanical, electrical, and plumbing plans must each be complete, signed and sealed by a Colorado registered design professional, per the City's Commercial Plans Checklist (detailed line-item requirements published for each discipline)
- General details of required fire protection systems are a DEFERRED SUBMITTAL to South Metro Fire Rescue — a separate application and permit from South Metro Fire Rescue is required for most commercial projects
- Prior to permit issuance, a Building Materials Use Tax deposit must be paid: the City estimates 50% of project valuation as materials and collects City Use Tax of 2.5% plus Arapahoe County Use Tax of 0.25% on that amount; reconciliation is due within 90 days of CO or final inspection
- Permits and contractor licenses must be applied for online; contractors performing work must be licensed by the City of Centennial Contractor
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 5 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Footing/Foundation
Foundation work verified before concrete pour; a Foundation Compliance Form is published among the City's Commercial Guides and Checklists
- 2
Special Inspections (IBC Chapter 17)
Provisions for required special inspections must be identified in the structural submittal per the City's Commercial Plans Checklist; conducted by the owner's special inspection agency during construction
- 3
Rough Trades (framing, mechanical, electrical, plumbing)
Rough inspections of structural framing and MEP systems before concealment; scheduled online via the City's inspection portal. The City does not publish a fixed enumerated commercial inspection sequence — the exact card is set at permit issuance
- 4
Final / Certificate of Occupancy
All inspections passed, Building Division notified by email, then CO (or 30-day TCO, $800) requested via the Commercial CO/TCO Request Application; Use Tax reconciliation due within 90 days of CO or final inspection
See the full Centennial inspection guide — scheduling & re-inspection fees →
Tips
- Budget for the South Metro Fire Rescue track from day one: most commercial projects need a separate SMFR application and permit (fire protection systems are a deferred submittal to SMFR), and only commercial one-stop, roof/re-roof, and window/door permits are exempt.
- The Use Tax deposit (2.75% combined on 50% of valuation) is often the largest single line item at issuance on a big commercial job — larger than the permit fee itself above roughly $1M valuation.
- There is NO separate large-office or multi-tenant-building permitting track for the Denver Tech Center corridor — the City's published classification list is exhaustive, and all new commercial construction (any size) runs through the single 'Commercial New' 15-business-day track; commercial ADDITIONS also use this 15-day row rather than the 10-day alterations row.
- Submit plans as PDFs online — paper commercial plans incur a $3.00-per-page conversion surcharge.
- Pre-submittal meetings are highly encouraged by City staff for any size/type of project (303-754-3321); permits are active for 180 days once issued.
- Retaining walls shown on the site plan require their own separate permits.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Centennial building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Centennial.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Centennial
Commercial Building Permit (New Construction) in other cities
Compare commercial building permit (new construction) fees across Colorado →