Change of Use / Change of Occupancy Permit — Castle Pines, Colorado · Requirements sheet
Verified 2026-08-13 · Source: https://www.castlepinesco.gov/wp-content/uploads/2019/08/Castle-Pines-Building-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Change of Occupancy Permit in Castle Pines, Colorado
Castle Pines has no standalone 'Change of Use' checkbox on its Building Permit Application — the six Permit Type options are Over the Counter, Demolition, Residential Alteration, Commercial Alteration, New Residential, and New Commercial. Instead, the application's own governing certification language explicitly requires that 'Any change in the use or occupancy of the building or structure must be approved prior to proceeding with construction,' and a change of use is processed as a Commercial Alteration (if plan review is triggered) or an Over-the-Counter permit (if not), governed by 2021 IEBC Chapter 10 (Change of Occupancy) as locally adopted.
Verified 2026-08-13 · Source
When you need this permit
- Any change in the use or occupancy of a building or structure must be approved by the City prior to proceeding with construction — explicit certification language on the standard City of Castle Pines Building Permit Application, signed by the applicant
- No distinct 'Change of Use' checkbox exists among the application's six Permit Type options (Over the Counter, Demolition, Residential Alteration, Commercial Alteration, New Residential, New Commercial); a change of use is submitted under Commercial Alteration if construction or plan review is triggered, or under Over the Counter if the use change itself requires no plans
- Governed by 2021 IEBC (International Existing Building Code) Chapter 10, Change of Occupancy, as locally adopted by Ordinance No. 23-02; IEBC Section 1001.2 requires an updated Certificate of Occupancy reflecting the new use or occupancy classification
- Both Planning & Zoning and the Building Department must independently sign off — the City's Building Permit Application form carries two separate 'For Office Use Only' approval blocks, one for Planning & Zoning and one for the Building Department, each with its own signature and date-approved line
- A Zoning Verification Letter is available (and advisable before applying) to confirm the proposed new use is permitted in the property's zoning district
- If the new use changes the building's fire/life-safety occupancy classification, South Metro Fire Rescue — the City's designated fire code official — separately reviews the change under its own published 'Change of Use' fire-code review fee, distinct from and in addition to the City's own building/zoning review (see this file's fire-sprinkler-alarm-permit entry)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection / Certificate of Occupancy Update
Confirms the new use or occupancy classification complies with applicable code requirements under 2021 IEBC Chapter 10 and the current IBC use and occupancy provisions; results in an updated Certificate of Occupancy per IEBC Sec. 1001.2
See the full Castle Pines inspection guide — scheduling & re-inspection fees →
Tips
- There is no 'Change of Use' checkbox on Castle Pines' Building Permit Application — use the Commercial Alteration track if any construction or plan review is triggered, or Over the Counter if not, and make sure the Scope of Work field clearly documents the use change so Planning & Zoning catches it during their separate sign-off.
- A $55 Zoning Verification Letter is the cheapest way to confirm your intended new use is actually allowed in the property's zoning district before committing to a lease or purchase and applying for the permit itself.
- If your new use changes the building's fire/life-safety occupancy classification, budget separately for South Metro Fire Rescue's own Change of Use fire-code review fee (about $588 total) — this is on top of, not instead of, the City's building and zoning fees.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-13.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Castle Pines building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Castle Pines
Change of Use / Change of Occupancy Permit in other cities
Compare change of use / change of occupancy permit fees across Colorado →
Look up this fee in a different city →