New Residential Building Permit — Castle Pines, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://www.castlepinesco.gov/city-services/city-departments/community-development/building-department-faqs/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
New Residential Building Permit in Castle Pines, Colorado
Required for new single-family or duplex residential construction in Castle Pines. Categorized as a Plan Review Permit under the 2021 IRC/IBC as locally adopted; requires two identical, scaled, stamped drawing sets.
Verified 2026-07-06 · Source
When you need this permit
- Plan Review Permit track: two identical drawing sets required, showing all structural components, drawn to scale
- Two foundation drawings stamped by a Colorado-licensed engineer or architect required for residential construction
- Site plan required showing dimensions, setbacks, easements, utilities, other structures, and distances to property lines
- Energy Code Compliance Report (energycodes.gov) or REScheck calculations required
- All contractors (general, electrical, plumbing, mechanical) must hold a current City of Castle Pines contractor license; electrical and plumbing contractors must additionally hold current Colorado DORA Electrical Board / Plumbing Board licenses Contractor
- Total project valuation (materials + labor, including owner labor at fair market value) must be accurately estimated on the application
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 4 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation
After trenches excavated, reinforcement in place, forms erected, prior to concrete pour
- 2
Underground
Prior to covering any piping or wiring and prior to placing concrete
- 3
Rough Trade (plumbing/mechanical/electrical)
After rough installation complete, prior to covering; may be combined with rough frame
- 4
Rough Frame
After roof, framing, fire stopping, sheathing, draft stopping, bracing, and fasteners in place
- 5
Insulation
After insulation placed, prior to covering walls
- 6
Final Inspection
After construction is complete
See the full Castle Pines inspection guide — scheduling & re-inspection fees →
Tips
- Residential additions and new construction both require two foundation drawings stamped by a Colorado-licensed engineer or architect — budget for that stamped-plan cost before submittal.
- Castle Pines' review timeline (5 days residential, 10 days commercial) is an actual published SLA, not a generic estimate — unusual candor for a Colorado home-rule jurisdiction.
- The 100% work-without-permit penalty fee (Ordinance No. 23-02) is a full doubling of your building permit fee if construction starts before the permit is issued.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Castle Pines building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Castle Pines
New Residential Building Permit in other cities
Compare new residential building permit fees across Colorado →
Look up this fee in a different city →