Required for heating, cooling, and ventilation equipment installation or replacement. Governed by the 2021 International Mechanical Code as adopted. Air Conditioning System and Furnace Replacement qualify as 1-Stop Permits.

Verified 2026-07-06 · Source

When you need this permit

  • Governed by the 2021 IMC as adopted (Municipal Code Chapter 18, Article IV)
  • Air Conditioning System, Furnace Replacement, and Gas Fireplace installation qualify as 1-Stop Permits (no drawings required)
  • Separate mechanical permits are not required where mechanical work is included within a general building permit for the structure (IMC Sec. 106.1 local amendment)
  • Contractors must hold a City of Castle Pines Class G Mechanical/HVAC/Warm-Air & Ventilation Contractor registration; all electrical work within a mechanical/HVAC project must be performed by a State of Colorado Licensed Master Electrician Contractor

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee (mechanical billed under general valuation-based schedule)
Per 2026 Fee Schedule Table 1-A valuation tiers
Contractor License Fee — Class G Mechanical/HVAC
$75.00 annually
Douglas County / Castle Pines Use Tax
1% / 3.75% of 50% of project value, respectively

Review timeline

Plan reviewCastle Pines’s published plan-review target
Up to 1 business days

How long did your Mechanical / HVAC Permit permit actually take in Castle Pines?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Mechanical

    Ductwork, flues, equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

See the full Castle Pines inspection guide — scheduling & re-inspection fees →

Tips

  • Furnace and AC replacements are 1-Stop Permits in Castle Pines — no drawings needed, and typically issued within 24 hours once fees are paid, unlike a full mechanical plan review.

Frequently asked questions

Castle Pines requires a mechanical / hvac permit for: Governed by the 2021 IMC as adopted (Municipal Code Chapter 18, Article IV); Air Conditioning System, Furnace Replacement, and Gas Fireplace installation qualify as 1-Stop Permits (no drawings required); Separate mechanical permits are not required where mechanical work is included within a general building permit for the structure (IMC Sec. 106.1 local amendment); Contractors must hold a City of Castle Pines Class G Mechanical/HVAC/Warm-Air & Ventilation Contractor registration; all electrical work within a mechanical/HVAC project must be performed by a State of Colorado Licensed Master Electrician. If your project isn't listed, confirm with City of Castle Pines Building Department (Community Development Department, Building Division) at 303-705-0227 before starting work.

In Castle Pines, the published Building Permit Fee (mechanical billed under general valuation-based schedule) is: Per 2026 Fee Schedule Table 1-A valuation tiers. Additional published fees: Contractor License Fee — Class G Mechanical/HVAC — $75.00 annually; Douglas County / Castle Pines Use Tax — 1% / 3.75% of 50% of project value, respectively. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Castle Pines's published plan-review target for a mechanical / hvac permit is Up to 1 business days.

You'll need: Building/Mechanical Permit Application; City of Castle Pines Contractor License (Class G). See the required-documents checklist on this page for details on each.

Castle Pines requires 2 inspection(s) for a mechanical / hvac permit, in order: Rough Mechanical, Final Inspection. Schedule each through City of Castle Pines Building Department (Community Development Department, Building Division) (303-705-0227).

Apply through City of Castle Pines Building Department (Community Development Department, Building Division) at 7437 Village Square Drive, Suite 200, Castle Pines, CO 80108. Phone: 303-705-0227, email: BuildingDept@castlepinesco.gov. Office hours: Monday through Thursday 8:00 a.m. to 12:00 p.m. and 1:00 p.m. to 4:30 p.m.; Friday 8:00 a.m. to 12:00 p.m. Fax 303-688-9414..

Castle Pines, Colorado has adopted: 2021 International Building Code (IBC), Chapters 1-35 inclusive, exclusive of Appendices — adopted by Ordinance No. 23-02 (Feb. 28, 2023), City of Castle Pines Municipal Code Chapter 18, Article I; 2021 International Residential Code (IRC), 1st printing; Chapter 11 of the 2018 edition of the International Residential Code (retained separately alongside the 2021 IRC per Ordinance No. 23-02's title recitals — Chapter 11 of the IRC covers energy efficiency; the City kept the 2018 version of this chapter rather than adopting the 2021 IRC's Chapter 11 wholesale); 2020 National Electrical Code (NEC) — City of Castle Pines Municipal Code Chapter 18, Article III, Sec. 18-3-10, adopted pursuant to Title 31, Article 16, Part 2, C.R.S., 'as adopted, amended and updated to the most current edition by the Colorado State Electrical Board from time to time' per the authority in Article 23 of Title 12, C.R.S. — the City ties its NEC edition to whatever the Colorado State Electrical Board currently recognizes, rather than freezing a single print edition; 2021 International Mechanical Code (IMC), Chapters 1-15 inclusive — Article IV; 2021 International Plumbing Code (IPC), Chapters 1-13 inclusive — Article V; 2021 International Fire Code (IFC) — adopted by Ordinance No. 23-07 (2023); enforced by the South Metro Fire Rescue Fire Protection District, which Ordinance No. 23-02/23-07 designates as the Fire Marshal's Office / fire code official for the City; 2021 International Fuel Gas Code (IFGC); 2018 International Energy Conservation Code (IECC); 2021 International Swimming Pool and Spa Code (ISPSC); 2021 International Existing Building Code (IEBC); Note on code-adoption sourcing: the 2021 IBC/IRC/IMC/IPC/IFGC/IECC(2018)/ISPSC/IEBC + 2020 NEC list above is drawn directly from the recitals and Sections 1-5 of Ordinance No. 23-02 (a scanned/image PDF, read via rendered page images since it is not machine-text-extractable), the definitive code-adoption ordinance for Chapter 18 of the Municipal Code. The City's own Building Department FAQ page states more casually that the City 'is currently under the 2021 International Building Code/International Residential Code and the 2023 National Electrical Code' — this FAQ-page NEC reference (2023) is NOT used as the governing citation in this file because it conflicts with the specific, dated ordinance text (2020 NEC, floating to the State Electrical Board's current edition); the ordinance is treated as authoritative and the FAQ's '2023 NEC' is noted as a likely informal/rounded reference to whatever edition the State Electrical Board currently recognizes, consistent with the ordinance's own floating-adoption mechanism.; HB22-1362 (Colorado statewide energy code floor via updated model electrical/energy provisions): no City of Castle Pines ordinance, code-adoption page, or fee schedule references HB22-1362 or a specific electric-vehicle-readiness / electrification-readiness local amendment as of this review (Ordinance No. 23-02 predates HB22-1362's later compliance deadlines and does not mention it); not asserted as inapplicable, simply unconfirmed for this jurisdiction after checking the governing ordinance and the Building Department's public-facing pages directly.. Local amendments apply — see the Castle Pines overview page for the full list.

No. Furnace Replacement is explicitly listed as a 1-Stop Permit, meaning no drawings or plan review are required; it is typically issued within 24 hours of a complete, paid application.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Castle Pines building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.