Inspection sequence, scheduling, and re-inspection fees for building permits in Eagle, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
200 Broadway, PO Box 609, Eagle, CO 81631
Phone
970-328-9565
Office hours
General Building Division line (970) 328-9565; Inspection Hotline (970) 328-9626 (must call by 4:00 PM for next available inspection date). Due to limited staff capacity, the Town's own Building Department page states initial response times for phone calls and emails are approximately 3-5 business days. In-person appointments are recommended and should be scheduled by phone or email rather than walk-in. Chief Building Official: Dan Brown.

Published scheduling rules

  • All plan submittals and inspection requests for registered contractors go through the Community Core online portal; paper plans are not accepted. (Residential Building Permit (New Construction))
  • Inspections are scheduled directly with the State's assigned inspector, not the Town's Inspection Hotline (Electrical Permit)
  • Applications, plan uploads, and inspection requests are submitted via the Town's Community Core online portal; paper plans are not accepted (Commercial Building Permit (New Construction, Additions, Alterations & Tenant Finish))

Inspection sequence

Applies to: Commercial Building Permit (New Construction, Additions, Alterations & Tenant Finish)

  1. 1

    Footing/Foundation

    Before concrete pour; scheduled via the Inspection Hotline (970) 328-9626 or the Community Core portal — call by 4:00 PM for the next available inspection date

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Town-administered trade rough-ins before concealment; rough and final electrical inspections are scheduled separately with the Colorado State Electrical Board (DPO), not the Town

  4. 4

    Final Inspection / Certificate of Occupancy

    All work complete per approved plans and applicable codes; Certificate of Occupancy ($100) issued on passing — a Temporary C/O ($250) is available per the 2026 Fee Schedule

Applies to: Residential Addition / Interior Remodel Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour, per 48-inch minimum frost depth

  2. 2

    Rough Frame

    Framing complete, connection to existing structure verified

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment

  4. 4

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour, per 48-inch minimum frost depth

  2. 2

    Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment (rough electrical is scheduled separately with the Colorado DPO, not the Town)

  4. 4

    Final Inspection

    All work complete per approved plans and applicable codes; Certificate of Occupancy issued on passing

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Scheduled directly with the State-assigned electrical inspector, not the Town

  2. 2

    Final Inspection

    State inspector verifies devices, panel labeling, and energization

Applies to: EV Charger / EVSE Permit (State of Colorado Electrical Board)

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed (if applicable); scheduled directly with the State-assigned electrical inspector, not the Town

  2. 2

    Final

    Charger circuit/unit installed, breaker sized correctly, energized; State inspector verifies devices and energization

Applies to: Fire Sprinkler and Fire Alarm System Permit

  1. 1

    Rough-In Inspection

    Included in the standard permit fee package; scheduled directly with GEFPD's Prevention Office, not the Town

  2. 2

    Final Inspection

    Included in the standard permit fee package; additional inspections beyond the included final are billed at $55.00/hour, 2-hour minimum

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: Solar PV Permit (Split Town/State Jurisdiction)

  1. 1

    Town Building Inspection (Structural/Racking)

    Town of Eagle Building Department inspects the structural/racking portion of the installation

  2. 2

    State Electrical Inspection

    Colorado State Electrical Board (DORA) inspects the interconnection/electrical work, since this is not handled by the Town

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Eagle building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Eagle building permits

Get alerts for Eagle

We'll email you when Eagle's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.