How to schedule

Inspections are requested through the building department below.

Address
Florence Municipal Center, 600 West 3rd Street, Florence, CO 81226
Phone
(719) 784-4848
Office hours
Main City Hall line (719) 784-4848 (option 6 reaches the Building Inspector directly); Fax (719) 784-0228. Building Inspector: David Wales, David.Wales@florencecolorado.org. Permit applications and supporting documents may also be submitted to john.vernetti@florencecolorado.org per the Building Permits page.

Published scheduling rules

  • Florence's own Building Permits page contact for permit submission is listed as john.vernetti@florencecolorado.org, while the Building Department's general contact is David Wales (Building Inspector) at building@florencecolorado.org / David.Wales@florencecolorado.org — both may be relevant depending on whether the inquiry is about submittal logistics or inspection scheduling. (General)

Inspection sequence

Applies to: Commercial / Industrial / Multi-Family Tenant Improvement Permit

  1. 1

    Foundation

    Per engineered, site-specific foundation plan

  2. 2

    Framing

    Structural framing per stamped architect/engineer plans

  3. 3

    Final Inspection

    All work complete per approved plans and applicable codes

Applies to: Deck / Covered Patio Permit

  1. 1

    Footing/Foundation

    Before concrete pour, if new footings are required

  2. 2

    Framing

    Deck/patio framing, ledger connection, and guardrail/handrail framing before cover or final

  3. 3

    Final Inspection

    Completed structure inspected for compliance with the 2006 IBC as adopted

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (additions with new footings only)

    Before concrete pour, per engineered foundation plan

  2. 2

    Framing

    Framing complete, connection to existing structure verified

  3. 3

    Final Inspection

    All work complete per approved plans

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    Before concrete pour; foundation must match the engineered, site-specific foundation plan

  2. 2

    Framing

    Structural framing complete before cover, per approved floor/roof framing plans

  3. 3

    Final Inspection

    All work complete per approved plans and the 2006 IBC/IECC as adopted; scheduled by phone at (719) 784-4848

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, venting, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Rooftop Solar Photovoltaic Permit

  1. 1

    Final Inspection (structural/mounting)

    Racking and roof penetration/mounting verified by the City

  2. 2

    State Electrical Inspection

    Electrical interconnection and equipment inspected separately by DORA under the State Electrical Permit

Florence building permits

Get alerts for Florence

We'll email you when Florence's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.