Rooftop Solar Photovoltaic Permit in Florence, Colorado

Required for solar photovoltaic installations in Florence. The City's building permit for a solar installation requires a copy of the State Electrical Permit (since electrical work itself is DORA-administered) alongside engineered structural documentation for roof-mounted systems.

Verified 2026-07-06 · Source

When you need this permit

  • Building Permit Application required for the solar installation scope
  • Copy of the State Electrical Permit required (electrical interconnection work is separately permitted through DORA, not the City)
  • Engineered Stamped Structural Letter required specifically for roof-mounted units
  • Engineered Stamp Design Plans required

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 4 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Check Fee / Building Permit FeeBilled via the general Building Permit Application line items; the electrical portion is billed separately by DORA
Not published as a numeric table

Review timeline

Plan review
Not published — contact the department

How long did your Rooftop Solar Photovoltaic Permit permit actually take in Florence?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection (structural/mounting)

    Racking and roof penetration/mounting verified by the City

  2. 2

    State Electrical Inspection

    Electrical interconnection and equipment inspected separately by DORA under the State Electrical Permit

See the full Florence inspection guide — scheduling & re-inspection fees →

Tips

  • You will need TWO permits for a solar installation in Florence: the City's Building Permit (structural/mounting) and a separate State of Colorado DORA Electrical Permit (interconnection/wiring) — the City explicitly requires a copy of the State Electrical Permit as part of its own application package.
  • Have your engineered stamped structural letter and design plans ready before submitting — both are required specifically for roof-mounted systems, per the City's Building Permits page.

Frequently asked questions

Yes. The City's Building Permit Application for a solar installation requires a copy of the State Electrical Permit, because electrical work in Florence is administered entirely by the State of Colorado DORA Electrical Board, not the City.

In Florence, the published Plan Check Fee / Building Permit Fee is: Not published as a numeric table. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Florence does not publish a plan-review timeline for this permit. Contact City of Florence Building Department at (719) 784-4848 for current turnaround.

You'll need: Building Permit Application; Copy of State Electrical Permit; Engineered Stamped Structural Letter; Engineered Stamp Design Plans. See the required-documents checklist on this page for details on each.

Florence requires 2 inspection(s) for a rooftop solar photovoltaic permit, in order: Final Inspection (structural/mounting), State Electrical Inspection. Schedule each through City of Florence Building Department ((719) 784-4848).

Apply through City of Florence Building Department at Florence Municipal Center, 600 West 3rd Street, Florence, CO 81226. Phone: (719) 784-4848, email: building@florencecolorado.org. Office hours: Main City Hall line (719) 784-4848 (option 6 reaches the Building Inspector directly); Fax (719) 784-0228. Building Inspector: David Wales, David.Wales@florencecolorado.org. Permit applications and supporting documents may also be submitted to john.vernetti@florencecolorado.org per the Building Permits page.. Official information: https://www.cityofflorenceco.gov/building-department.

Florence, Colorado has adopted: 2006 International Building Code (IBC) — City of Florence Building Department page states plainly: 'The City of Florence follows the 2006 International Building Code'; 2006 International Energy Conservation Code (IECC) — per the Building Permit Application Submittal Checklist (PDF): 'Energy Code – City of Florence adopts the 2006 Edition of the International Energy Conservation Code'; Florence Municipal Code Title 15 (Buildings and Construction), Section 15.04.040: 'The requirement for obtaining building permits relative to the construction, alteration, moving, demolition, repair, maintenance, and use of any building or structure within the City of Florence shall be governed by the most recent adopted edition of the appropriate adopted codes and building standards, including amendments thereto.' Per Municode search indexing of Title 15, Chapter 15.08 (amendments) is where local amendments to the 2006 IBC are set forth (Section 15.08.010).; Electrical: 2023 National Electrical Code (NEC) — administered by the State of Colorado, NOT the City (see localAmendments). Source: City of Florence Building Department page, linking to the Colorado Division of Professions and Occupations (DORA) Electrical Board page, which states the current adopted edition as the 2023 NEC.; Plumbing: 2021 (Colorado) Plumbing Code — administered by the State of Colorado, NOT the City. Source: City of Florence Building Department page, linking to the DORA Plumbing Board page, which lists the 2021 edition.; No separate local IRC, IMC, IFGC, or IFC edition is published by the City on its Building Department or Building Permits pages, or in the Building Permit Application Submittal Checklist — only the 2006 IBC (general building code) and 2006 IECC (energy code) are explicitly named by the City itself. The zero-tolerance policy governing this corpus prohibits inferring an IRC/IMC/IFGC/IFC edition the City has not itself published; note this as a gap rather than assuming a matching 2006 cycle for the unlisted codes.; HB22-1362 (Colorado statewide energy code floor, effective for jurisdictions adopting/updating codes on specified triggers starting July 2023 for larger jurisdictions and July 2026 for smaller ones) does not appear reflected on the City's Building Department page or Submittal Checklist, both of which still affirmatively state the 2006 IECC as current and were the live, actively-maintained pages as of this review (2026-07-06) — checked directly, no updated energy code notice found. Flagged honestly rather than assumed; Florence's population (under the HB22-1362 tiered compliance triggers) and its home-rule status both bear on whether/when the floor applies, but the City has not published any code update reflecting it as of this review.. Local amendments apply — see the Florence overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.