EV Charger / Electric Vehicle Charging Station Permit (State-Administered) — Florence, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.cityofflorenceco.gov/building-department
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
EV Charger / Electric Vehicle Charging Station Permit (State-Administered) in Florence, Colorado
Electrical permits within Florence city limits — including an EV charging station (Level 1/2 EVSE) circuit — are issued and scheduled entirely by the State of Colorado Department of Regulatory Agencies (DORA) Electrical Board, NOT by the City of Florence, exactly as documented in the electrical-permit entry. No EV-specific permit, provision, or fee exists at either the City or State level; EV charger wiring is simply electrical work subject to the standard state-administered process.
Verified 2026-07-20 · Source
When you need this permit
- Electrical permits for EV charger/EVSE circuits are issued and scheduled by the State of Colorado DORA, per the City of Florence Building Department page: 'Electrical and Plumbing permits and inspections are issued and scheduled by the State of Colorado Department of Regulatory Agencies (DORA)'
- Governed by the 2023 National Electrical Code (NEC), per DORA's Electrical page as linked by the City
- Per state statute, only a licensed/registered Electrical Contractor — not the homeowner — may pull the permit and perform the work, except where the homeowner is personally performing work permitted under state homeowner exemptions Owner-builder
- If the EV charger is installed with a rooftop solar system, the City requires a copy of the State Electrical Permit as part of the City's own Building Permit Application package for the structural/racking portion — see rooftop-solar-pv-permit entry
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Rough and Final Electrical Inspection
Scheduled directly through the State of Colorado DORA Electrical Board, not the City of Florence Building Department
See the full Florence inspection guide — scheduling & re-inspection fees →
Tips
- Do not attempt to obtain an EV charger permit through the City of Florence Building Department — it is not the issuing authority for electrical work of any kind. Go directly to the DORA Electrical Board (https://dpo.colorado.gov/Electrical).
- If you are a homeowner hiring an electrical contractor for the EV charger, your contractor — not you — is responsible for obtaining the state permit.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Florence
EV Charger / Electric Vehicle Charging Station Permit (State-Administered) in other cities
Look up this fee in a different city →