Re-Roof Permit in Florence, Colorado

Required for re-roofing projects in Florence. The City imposes a firm advance-notice requirement: all re-roofing projects must submit the application and required documentation at least three (3) business days prior to the scheduled start date.

Verified 2026-07-06 · Source

When you need this permit

  • ALL RE-ROOFING PROJECTS MUST SUBMIT THE APPLICATION AND REQUIRED DOCUMENTATION AT LEAST THREE (3) BUSINESS DAYS PRIOR TO THE SCHEDULED START DATE (stated in capital letters on the Building Permits page)
  • Signed copy of contract or estimate sheet with the homeowner required alongside the Building Permit Application
  • Note: the same Building Permits page also contains a second, inconsistent sentence stating 'at least two days prior to the scheduled start date' — the three-business-day requirement is stated first and in emphasis, and is treated as the governing figure in this file; the inconsistency itself is flagged rather than silently resolved

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Plan Check Fee / Building Permit FeeNo separate flat re-roof fee is published; billed via the general Building Permit Application line items
Not published as a numeric table

Review timeline

Plan reviewFlorence’s published plan-review target
3+ business days

How long did your Re-Roof Permit permit actually take in Florence?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Roof Inspection

    Completed roof inspected for compliance with the 2006 IBC as adopted

See the full Florence inspection guide — scheduling & re-inspection fees →

Tips

  • Submit your re-roof application and signed contractor estimate at least 3 business days before your planned start date — the City states this requirement in capital letters, treating it as a hard minimum, not a suggestion.
  • Have your roofing contractor's signed contract or written estimate ready at submittal; it's explicitly required alongside the Building Permit Application for this permit type.

Frequently asked questions

The City of Florence's Building Permits page states that all re-roofing projects must submit the application and required documentation at least three (3) business days prior to the scheduled start date.

In Florence, the published Plan Check Fee / Building Permit Fee is: Not published as a numeric table. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Florence's published plan-review target for a re-roof permit is 3+ business days.

You'll need: Building Permit Application; Signed Contract or Estimate Sheet. See the required-documents checklist on this page for details on each.

Florence requires 1 inspection(s) for a re-roof permit, in order: Final Roof Inspection. Schedule each through City of Florence Building Department ((719) 784-4848).

Apply through City of Florence Building Department at Florence Municipal Center, 600 West 3rd Street, Florence, CO 81226. Phone: (719) 784-4848, email: building@florencecolorado.org. Office hours: Main City Hall line (719) 784-4848 (option 6 reaches the Building Inspector directly); Fax (719) 784-0228. Building Inspector: David Wales, David.Wales@florencecolorado.org. Permit applications and supporting documents may also be submitted to john.vernetti@florencecolorado.org per the Building Permits page.. Official information: https://www.cityofflorenceco.gov/building-department.

Florence, Colorado has adopted: 2006 International Building Code (IBC) — City of Florence Building Department page states plainly: 'The City of Florence follows the 2006 International Building Code'; 2006 International Energy Conservation Code (IECC) — per the Building Permit Application Submittal Checklist (PDF): 'Energy Code – City of Florence adopts the 2006 Edition of the International Energy Conservation Code'; Florence Municipal Code Title 15 (Buildings and Construction), Section 15.04.040: 'The requirement for obtaining building permits relative to the construction, alteration, moving, demolition, repair, maintenance, and use of any building or structure within the City of Florence shall be governed by the most recent adopted edition of the appropriate adopted codes and building standards, including amendments thereto.' Per Municode search indexing of Title 15, Chapter 15.08 (amendments) is where local amendments to the 2006 IBC are set forth (Section 15.08.010).; Electrical: 2023 National Electrical Code (NEC) — administered by the State of Colorado, NOT the City (see localAmendments). Source: City of Florence Building Department page, linking to the Colorado Division of Professions and Occupations (DORA) Electrical Board page, which states the current adopted edition as the 2023 NEC.; Plumbing: 2021 (Colorado) Plumbing Code — administered by the State of Colorado, NOT the City. Source: City of Florence Building Department page, linking to the DORA Plumbing Board page, which lists the 2021 edition.; No separate local IRC, IMC, IFGC, or IFC edition is published by the City on its Building Department or Building Permits pages, or in the Building Permit Application Submittal Checklist — only the 2006 IBC (general building code) and 2006 IECC (energy code) are explicitly named by the City itself. The zero-tolerance policy governing this corpus prohibits inferring an IRC/IMC/IFGC/IFC edition the City has not itself published; note this as a gap rather than assuming a matching 2006 cycle for the unlisted codes.; HB22-1362 (Colorado statewide energy code floor, effective for jurisdictions adopting/updating codes on specified triggers starting July 2023 for larger jurisdictions and July 2026 for smaller ones) does not appear reflected on the City's Building Department page or Submittal Checklist, both of which still affirmatively state the 2006 IECC as current and were the live, actively-maintained pages as of this review (2026-07-06) — checked directly, no updated energy code notice found. Flagged honestly rather than assumed; Florence's population (under the HB22-1362 tiered compliance triggers) and its home-rule status both bear on whether/when the floor applies, but the City has not published any code update reflecting it as of this review.. Local amendments apply — see the Florence overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Florence building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.