Durango building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Durango, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
949 E 2nd Avenue, Durango, CO 81301
Phone
970-375-5000
Office hours
Not published on the Building Division pages as of this review; main City Hall line 970-375-5000. General building-permit questions: Building@DurangoCo.Gov. Fee-schedule calculation questions: 970-375-4850.

Inspection sequence

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, for additions with new foundation elements

  2. 2

    Rough Framing

    Framing complete and tied into existing structure before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado Electrical Board, not the City

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans

Applies to: Residential Building Permit (New Single-Family Residence or Duplex)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment (plumbing and mechanical are inspected by the City; electrical rough-in is inspected separately by the State of Colorado Electrical Board)

  4. 4

    Final Inspection

    All City-permitted work (building, plumbing, mechanical) complete per approved plans and applicable codes; a separate final electrical inspection and sign-off is required from the State of Colorado Electrical Board before occupancy

Applies to: Plumbing / Gas Line Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Gas Line Pressure Test

    City-completed inspection verifying the gas line holds pressure before the gas provider will connect service

  3. 3

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: EV Charger / EVSE Permit (State of Colorado Electrical Board)

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/unit installed, breaker sized correctly, energized

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Re-inspection fees

Plumbing / Gas Line PermitReinspection Fee · Effective 07/01/2026, applies to all failed inspections City-wide, paid before the final inspection phase
$125.00
Mechanical / HVAC PermitReinspection Fee · Effective 07/01/2026
$125.00
Roofing Permit (Roof Replacement)Reinspection Fee · Effective 07/01/2026
$125.00

Durango building permits

Get alerts for Durango

We'll email you when Durango's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.