Durango building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Durango, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
949 E 2nd Avenue, Durango, CO 81301
Phone
970-375-5000
Office hours
Not published on the Building Division pages as of the last verification; main City Hall line 970-375-5000. General building-permit questions: Building@DurangoCo.Gov. Fee-schedule calculation questions: 970-375-4850.

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Addition / Remodel)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    City-inspected trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado Electrical Board, and fire alarm/sprinkler systems by DFPD

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans; separate state electrical final and DFPD life-safety sign-offs are also required before occupancy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Foundation (if new footings)

    Before concrete pour, for additions with new foundation elements

  2. 2

    Rough Framing

    Framing complete and tied into existing structure before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado Electrical Board, not the City

  4. 4

    Final Inspection

    All City-permitted work complete per approved plans

Applies to: Residential Building Permit (New Single-Family Residence or Duplex)

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment (plumbing and mechanical are inspected by the City; electrical rough-in is inspected separately by the State of Colorado Electrical Board)

  4. 4

    Final Inspection

    All City-permitted work (building, plumbing, mechanical) complete per approved plans and applicable codes; a separate final electrical inspection and sign-off is required from the State of Colorado Electrical Board before occupancy

Applies to: Commercial Tenant Improvement / Tenant Finish Permit

  1. 1

    Rough Framing (interior partitions)

    New interior walls and structural modifications before cover

  2. 2

    Rough Plumbing / Mechanical

    City-inspected trade rough-ins before concealment; electrical rough-in is inspected separately by the State of Colorado Electrical Board, and fire alarm/sprinkler modifications by DFPD

  3. 3

    Final Inspection

    All City-permitted work complete per approved plans; separate state electrical final and DFPD life-safety sign-offs also required before the space opens

Applies to: Plumbing / Gas Line Permit

  1. 1

    Rough Plumbing

    Pipe, drain, waste, and vent installation before concealment

  2. 2

    Gas Line Pressure Test

    City-completed inspection verifying the gas line holds pressure before the gas provider will connect service

  3. 3

    Final Inspection

    Fixtures connected, no leaks, proper venting verified

Applies to: EV Charger / EVSE Permit (State of Colorado Electrical Board)

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/unit installed, breaker sized correctly, energized

Applies to: Fire Sprinkler / Fire Alarm System Permit (Durango Fire Protection District)

  1. 1

    Rough-In Inspection

    Piping, wiring, and device placement inspected before concealment, per the governing system's DFPD plan review/permit

  2. 2

    Acceptance Test / Final Inspection

    System operational and code-compliant, verified by DFPD before the permit closes; water-tank installations specifically require an acceptance test per the DFPD fee schedule's own description of that permit type

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, and equipment placement before concealment

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Re-inspection fees

Plumbing / Gas Line PermitReinspection Fee · Effective 07/01/2026, applies to all failed inspections City-wide, paid before the final inspection phase
$125.00
Mechanical / HVAC PermitReinspection Fee · Effective 07/01/2026
$125.00
Roofing Permit (Roof Replacement)Reinspection Fee · Effective 07/01/2026
$125.00
Commercial Building Permit (New Construction / Addition / Remodel)Reinspection Fee · Effective 07/01/2026, paid before the final inspection phase
$125.00 per failed inspection
Commercial Tenant Improvement / Tenant Finish PermitReinspection Fee · Effective 07/01/2026, paid before the final inspection phase
$125.00 per failed inspection

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Durango building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Durango building permits

Get alerts for Durango

We'll email you when Durango's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.