EV Charger / EVSE Permit (State of Colorado Electrical Board) in Durango, Colorado

Installation of an electric vehicle charging station in Durango is electrical work and, like the photovoltaic/interconnection portion of a solar installation documented on the solar-pv-permit entry, is permitted directly by the State of Colorado Electrical Board (DORA), NOT the City of Durango Building Division. Under Colorado Revised Statutes § 12-23-117, electrical inspection is a matter of statewide concern: the state sets a uniform fee schedule, and a municipality may charge no more than 15% above the state's own fee — no local government may impose any other separate fee or charge related to electrical permits/inspections. The state's own valuation-based/square-footage-based electrical fee schedule has NO distinct 'EV charger,' 'electric vehicle,' or 'EVSE' line item; a dedicated Level 2 charger circuit is billed under the state's 'All other electrical fees' valuation-based tier (a flat $115 minimum plus $5.75 per $1,000 above $2,000 of installation value, per the fee schedule effective April 1, 2016 — Durango or a licensed contractor should confirm the current-year statewide figure directly with DORA, since the state revises this schedule periodically and only the mechanism, not the specific 2016 dollar amounts, is being relied on here).

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit issued by the Colorado State Electrical Board (DORA/DPO), not the City of Durango — apply online through DORA's electrical permit portal
  • The State of Colorado's own Electrical Permit Fees schedule (mechanism fixed by C.R.S. § 12-23-117) carries no distinct EV-charger/EVSE fee line; a dedicated charger circuit not tied to new residential square footage is billed on the 'All other electrical fees' valuation-based tier
  • Per C.R.S. § 12-23-117, the City of Durango may charge no more than 15% above the state's own electrical fee, and may not impose any additional separate fee or charge for electrical permits/inspections
  • Work must be performed by a Colorado-licensed electrical contractor, or by a homeowner personally on their own residence under Colorado's homeowner exemption Owner-builder
  • Confirm the current-year statewide fee figures directly with the State Electrical Board (303-894-7800, dora_electricalboard@state.co.us), since DORA revises the schedule periodically

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

All other electrical fees — valuation not more than $2,000 (typical dedicated EV charger circuit)
State of Colorado Electrical Permit Fees schedule, effective 4/1/2016 (mechanism fixed by C.R.S. Show full citationState of Colorado Electrical Permit Fees schedule, effective 4/1/2016 (mechanism fixed by C.R.S. § 12-23-117) — no distinct EV-charger/EVSE line item exists; confirm the current-year statewide figure directly with DORA, since fees are revised periodically and this is the most recent published schedule located
$115.00 (per the schedule effective April 1, 2016, scaled up to 1.15x by a municipality if it separately assesses inspection)
All other electrical fees — valuation $2,001 and aboveState of Colorado Electrical Permit Fees schedule
$115 plus $5.75 per $1,000 or fraction thereof of total valuation, plus $115.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit (State of Colorado Electrical Board) permit actually take in Durango?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    Wiring and conduit installed before walls closed (if applicable)

  2. 2

    Final

    Charger circuit/unit installed, breaker sized correctly, energized

See the full Durango inspection guide — scheduling & re-inspection fees →

Tips

  • Do not apply for an EV charger permit through the City of Durango Building Division — like the electrical/interconnection portion of a solar installation, it is a State of Colorado Electrical Board permit, not a City permit.
  • There is no distinct 'EV charger permit' anywhere in Colorado's statewide electrical fee schedule — a dedicated charger circuit not tied to new residential square footage is billed on the state's valuation-based 'All other electrical fees' tier.
  • Under C.R.S. § 12-23-117, no local government (including Durango) may charge more than 15% above the state's own electrical fee, or impose any separate additional electrical permit fee — this caps what Durango could ever charge on top of the state fee even if it chose to add a local surcharge.

Frequently asked questions

Durango requires an ev charger / evse permit (state of colorado electrical board) for: Electrical permit issued by the Colorado State Electrical Board (DORA/DPO), not the City of Durango — apply online through DORA's electrical permit portal; The State of Colorado's own Electrical Permit Fees schedule (mechanism fixed by C.R.S. § 12-23-117) carries no distinct EV-charger/EVSE fee line; a dedicated charger circuit not tied to new residential square footage is billed on the 'All other electrical fees' valuation-based tier; Per C.R.S. § 12-23-117, the City of Durango may charge no more than 15% above the state's own electrical fee, and may not impose any additional separate fee or charge for electrical permits/inspections; Work must be performed by a Colorado-licensed electrical contractor, or by a homeowner personally on their own residence under Colorado's homeowner exemption; Confirm the current-year statewide fee figures directly with the State Electrical Board (303-894-7800, dora_electricalboard@state.co.us), since DORA revises the schedule periodically. If your project isn't listed, confirm with City of Durango Community Development Department, Building Division at 970-375-5000 before starting work.

No. The State Electrical Board's fee schedule has no distinct EV-charger or EVSE line item. A dedicated charger circuit is billed on the state's valuation-based 'All other electrical fees' tier, and by state law (C.R.S. § 12-23-117) no municipality may charge more than 15% above the state's own fee.

Durango does not publish a plan-review timeline for this permit. Contact City of Durango Community Development Department, Building Division at 970-375-5000 for current turnaround.

You'll need: State of Colorado Electrical Permit Application. See the required-documents checklist on this page for details on each.

Durango requires 2 inspection(s) for an ev charger / evse permit (state of colorado electrical board), in order: Rough-In, Final. Schedule each through City of Durango Community Development Department, Building Division (970-375-5000).

Apply through City of Durango Community Development Department, Building Division at 949 E 2nd Avenue, Durango, CO 81301. Phone: 970-375-5000, email: Building@DurangoCo.Gov. Office hours: Not published on the Building Division pages as of the last verification; main City Hall line 970-375-5000. General building-permit questions: Building@DurangoCo.Gov. Fee-schedule calculation questions: 970-375-4850.. Official information: https://www.durangoco.gov/311/Applying-for-a-Building-Permit.

Durango, Colorado has adopted: 2024 International Building Code (IBC) — City of Durango Building Codes page, effective for new projects not already in a planning process prior to 01/01/2026; 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Energy Conservation Code (IECC); 2024 International Plumbing Code (IPC); 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2023 National Electrical Code (NEC); Colorado Model Electric Ready and Solar Ready Code (CMERSRC) — state-mandated, per City of Durango Building Codes page and Submittal Requirements page; Colorado Wildfire Resiliency Code (WRC) — state-mandated; City of Durango began enforcement April 1, 2026 per the Building Codes page and Do I Need a Permit? page; Transition provision: projects with full vertical construction drawings designed to the 2018 I-Codes and submitted to the Planning Division prior to January 1, 2026 may remain compliant with that older code cycle; all other new submittals must follow the 2024 I-Codes, 2023 NEC, CMERSRC, and Wildfire Resiliency Code; Code books available for review at Community Development and the City Clerk's Office; full municipal code at library.municode.com/co/durango. Local amendments apply — see the Durango overview page for the full list.

No. Electrical permits in Durango — including EV charger circuits — are issued by the State of Colorado Electrical Board (DORA), not the City. This mirrors the electrical/interconnection portion of a solar installation, which the solar-pv-permit entry also documents as state-administered.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Durango building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Durango's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Durango yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.