Solar PV Permit — Durango, Colorado · Requirements sheet
Verified 2026-07-20 · Source: https://www.durangoco.gov/683/Do-I-Need-a-Permit
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit in Durango, Colorado
Required for all solar panel installations in Durango. As of April 1, 2026, solar permits use the same new streamlined flat-fee-plus-use-tax structure as roofing. Electrical interconnection work associated with the solar installation is permitted separately by the State of Colorado Electrical Board, not the City.
Verified 2026-07-20 · Source
When you need this permit
- All solar panel installations require a solar permit from the City
- Applicants should review the solar permit checklist before submitting an application (referenced on the Do I Need a Permit? page; its contents are not summarized here — see the accompanying note)
- May also be required to go through the Commercial Design Review process for certain projects
- New flat-fee pricing structure effective 04/01/2026, same schedule as roofing
- Photovoltaic (solar) electrical installation work is separately permitted and inspected by the State of Colorado Electrical Board (DORA), per the City's Do I Need a Permit? page, which lists 'photovoltaic installation' explicitly under the state-handled Electrical permit category
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Review timeline
Inspection process
- 1
Final Inspection (mounting/roof penetrations)
Racking and roof-penetration compliance verified by the City
See the full Durango inspection guide — scheduling & re-inspection fees →
Tips
- The City's solar permit covers the physical mounting/roofing scope; the electrical interconnection portion of a solar project is separately permitted and inspected by the State of Colorado Electrical Board — plan for two separate permitting tracks, not one.
- Check whether your project needs to go through the Commercial Design Review process in addition to the base solar permit before assuming the flat $125/$175 fee is the whole cost.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fee schedules
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Durango building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Durango's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Durango yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Durango lands. Privacy.
Other permits in Durango
Solar PV Permit in other cities
Compare solar pv permit fees across Colorado →
Look up this fee in a different city →