Residential Building Permit (New Single-Family Residence or Duplex) in Durango, Colorado

Required for new single-family homes, duplexes, and townhouses within Durango city limits, per the City's 'Do I Need a Permit?' table. Reviewed under the 2024 IRC/IBC as locally adopted, plus the state-mandated Colorado Model Electric Ready and Solar Ready Code and Colorado Wildfire Resiliency Code. Issued by the City of Durango Community Development Department, Building Division; electrical work on the project is permitted separately through the State of Colorado Electrical Board, not the City.

Verified 2026-07-06 · Source

When you need this permit

  • New projects not already in a planning process prior to 01/01/2026 must be designed to the 2024 I-Codes and 2023 NEC
  • Must additionally comply with the Colorado Wildfire Resiliency Code and the Colorado Model Electric Ready and Solar Ready Code (CMERSRC), both state-mandated for new 2026-and-beyond projects
  • Full submittal package required per Section 107 IBC / Section 106 IRC: cover sheet with title block, sheet/drawing index, project/building data block, site vicinity map, civil or architectural site plan, foundation plan, floor plans, structural design sheets, elevations and sections, mechanical design sheets, electrical design sheets, plumbing design sheets, reflected ceiling plan, roof/ceiling design sheets, and IECC energy code compliance documentation
  • Most projects require an architect or engineer stamp; minor IRC-only projects may be done by a draftsperson, though engineered elements (shear walls, moment frames) still need a professional engineer's stamp
  • MEP (mechanical/electrical/plumbing) design sheets are required at initial submittal for both residential and commercial projects and may NOT be submitted as deferred submittals (fire sprinkler design, truss design sheets, and fire protection engineering may be deferred)
  • Sky Ridge and Rock Ridge subdivision projects require professionally engineered foundation systems
  • Three Springs and Twin Buttes projects require their own Design Review Committee approval, documented at submittal
  • Public improvements (sidewalk, curb and gutter, street trees) may be required as a condition of any building permit
  • Contractors must hold a valid City of Durango Business License
  • Applications submitted through the City's OpenGov online portal (durangoco.portal.opengov.com)
  • All electrical work on the project is separately permitted and inspected by the State of Colorado Electrical Board (DORA), not included in this City building permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Building Permit Fee — valuation $1 to $500Building Permit Fee Schedule, effective July 1, 2026, fees adopted under Resolution R-2017-42
$24.00
Building Permit Fee — valuation $501 to $2,000
$24 for the first $500 plus $3 for each additional $100 (rounded up to next $100 interval)
Building Permit Fee — valuation $2,001 to $40,000
$69 for the first $2,000 plus $11 for each additional $1,000 (rounded up to next $1,000 interval)
Building Permit Fee — valuation $40,001 to $100,000
$487 for the first $40,000 plus $9 for each additional $1,000 (rounded up)
Building Permit Fee — valuation $100,001 to $500,000
$1,027 for the first $100,000 plus $7 for each additional $1,000 (rounded up)
Building Permit Fee — valuation $500,001 to $1,000,000
$3,827 for the first $500,000 plus $5 for each additional $1,000 (rounded up)
Building Permit Fee — valuation $1,000,001 to $5,000,000
$6,327 for the first $1,000,000 plus $3 for each additional $1,000 (rounded up)
Building Permit Fee — valuation $5,000,001 and over
$18,327 for the first $5,000,000 plus $1 for each additional $1,000 (rounded up)
Use TaxHalf of building-project valuation is assumed to be labor; use tax applies only to the materials half at the combined 3.5% sales/use tax rate
1.75% of total project valuation
Water Plant Investment Fee (PIF) — Single Unit Dwelling, 3/4-inchResolution R-2019-46; varies by meter size and residential/non-residential/mixed-use classification
$5,320
Sewer Plant Investment Fee (PIF) — Single Unit DwellingResolution R-2019-47; South Durango Sanitation District (Three Springs and areas south of Bodo Industrial Park) charges separately, not through the City
$2,500
Tap Fee — 3/4-inch
$334 per tap
Major Street Impact Fee — Single-Family Detached, 1,000-1,499 sq ft living areaVaries by living-area tier; additions to existing single-family units are often exempt if the majority of the original structure is preserved
$2,050 per dwelling unit
Park Fee$300 for 1 residential unit in the City's own worked example
Per-unit fee for new residential units; Three Springs, Twin Buttes, and SkyRidge carry specific exemptions
School Land Dedication or In-Lieu Fee — Single Family
$945 per unit
Durango Fire Protection District (DFPD) Impact Fee — residentialCollected by DFPD directly, not included in the City's building permit total; Ordinance No. O-2023-0010
$1,317.00 per unit

Review timeline

Plan reviewDurango’s published plan-review target
0–30 business days

How long did your Residential Building Permit (New Single-Family Residence or Duplex) permit actually take in Durango?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    Before concrete pour

  2. 2

    Rough Framing

    Structural framing complete before cover

  3. 3

    Rough Plumbing / Mechanical

    Trade rough-ins before concealment (plumbing and mechanical are inspected by the City; electrical rough-in is inspected separately by the State of Colorado Electrical Board)

  4. 4

    Final Inspection

    All City-permitted work (building, plumbing, mechanical) complete per approved plans and applicable codes; a separate final electrical inspection and sign-off is required from the State of Colorado Electrical Board before occupancy

See the full Durango inspection guide — scheduling & re-inspection fees →

Tips

  • Durango's own review-time commitment is a single general figure — 'a minimum of 30 business days for all submittals' — not a new-construction-specific number; budget schedule accordingly and expect resubmittals to extend it further.
  • Electrical work on your new home is NOT part of this City building permit. You must separately obtain an electrical permit directly from the State of Colorado Electrical Board (DORA) at dpo.colorado.gov/EandP/Permits and schedule state electrical inspections independently of the City's building-permit inspection sequence.
  • MEP (mechanical/electrical/plumbing) design sheets must be included at initial submittal — they cannot be deferred, unlike truss design sheets or fire sprinkler design, which can be submitted later.
  • If your project is in Sky Ridge or Rock Ridge, budget for a professionally engineered foundation system as a mandatory local requirement, not just a recommendation.
  • Confirm which subdivision-specific fee exemptions (Three Springs, Twin Buttes, SkyRidge, Phases 1-4a) may apply to your Major Street Impact, Park, or School fees before finalizing your budget — several standard fees are waived in those areas.

Frequently asked questions

Durango requires a residential building permit (new single-family residence or duplex) for: New projects not already in a planning process prior to 01/01/2026 must be designed to the 2024 I-Codes and 2023 NEC; Must additionally comply with the Colorado Wildfire Resiliency Code and the Colorado Model Electric Ready and Solar Ready Code (CMERSRC), both state-mandated for new 2026-and-beyond projects; Full submittal package required per Section 107 IBC / Section 106 IRC: cover sheet with title block, sheet/drawing index, project/building data block, site vicinity map, civil or architectural site plan, foundation plan, floor plans, structural design sheets, elevations and sections, mechanical design sheets, electrical design sheets, plumbing design sheets, reflected ceiling plan, roof/ceiling design sheets, and IECC energy code compliance documentation; Most projects require an architect or engineer stamp; minor IRC-only projects may be done by a draftsperson, though engineered elements (shear walls, moment frames) still need a professional engineer's stamp; MEP (mechanical/electrical/plumbing) design sheets are required at initial submittal for both residential and commercial projects and may NOT be submitted as deferred submittals (fire sprinkler design, truss design sheets, and fire protection engineering may be deferred); Sky Ridge and Rock Ridge subdivision projects require professionally engineered foundation systems; Three Springs and Twin Buttes projects require their own Design Review Committee approval, documented at submittal; Public improvements (sidewalk, curb and gutter, street trees) may be required as a condition of any building permit; Contractors must hold a valid City of Durango Business License; Applications submitted through the City's OpenGov online portal (durangoco.portal.opengov.com); All electrical work on the project is separately permitted and inspected by the State of Colorado Electrical Board (DORA), not included in this City building permit. If your project isn't listed, confirm with City of Durango Community Development Department, Building Division at 970-375-5000 before starting work.

In Durango, the published Building Permit Fee — valuation $1 to $500 is: $24.00. Additional published fees: Building Permit Fee — valuation $501 to $2,000 — $24 for the first $500 plus $3 for each additional $100 (rounded up to next $100 interval); Building Permit Fee — valuation $2,001 to $40,000 — $69 for the first $2,000 plus $11 for each additional $1,000 (rounded up to next $1,000 interval); Building Permit Fee — valuation $40,001 to $100,000 — $487 for the first $40,000 plus $9 for each additional $1,000 (rounded up); Building Permit Fee — valuation $100,001 to $500,000 — $1,027 for the first $100,000 plus $7 for each additional $1,000 (rounded up); Building Permit Fee — valuation $500,001 to $1,000,000 — $3,827 for the first $500,000 plus $5 for each additional $1,000 (rounded up); Building Permit Fee — valuation $1,000,001 to $5,000,000 — $6,327 for the first $1,000,000 plus $3 for each additional $1,000 (rounded up); Building Permit Fee — valuation $5,000,001 and over — $18,327 for the first $5,000,000 plus $1 for each additional $1,000 (rounded up); Use Tax — 1.75% of total project valuation; Water Plant Investment Fee (PIF) — Single Unit Dwelling, 3/4-inch — $5,320; Sewer Plant Investment Fee (PIF) — Single Unit Dwelling — $2,500; Tap Fee — 3/4-inch — $334 per tap; Major Street Impact Fee — Single-Family Detached, 1,000-1,499 sq ft living area — $2,050 per dwelling unit; Park Fee — Per-unit fee for new residential units; Three Springs, Twin Buttes, and SkyRidge carry specific exemptions; School Land Dedication or In-Lieu Fee — Single Family — $945 per unit; Durango Fire Protection District (DFPD) Impact Fee — residential — $1,317.00 per unit. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

The City's own published minimum is 30 business days for all submittals, with resubmittals extending that timeline further. Colorado is a home-rule state with no statewide review-time statute, so this City-published figure is the governing number.

You'll need: Building Permit Application (OpenGov portal); Full Construction Drawing Set; DFPD Fire Code Plan Review receipt. Depending on your project, Durango may also ask for: Three Springs / Twin Buttes Design Review Committee approval. See the required-documents checklist on this page for details on each.

Durango requires 4 inspection(s) for a residential building permit (new single-family residence or duplex), in order: Foundation, Rough Framing, Rough Plumbing / Mechanical, Final Inspection. Schedule each through City of Durango Community Development Department, Building Division (970-375-5000).

Apply through City of Durango Community Development Department, Building Division at 949 E 2nd Avenue, Durango, CO 81301. Phone: 970-375-5000, email: Building@DurangoCo.Gov. Office hours: Not published on the Building Division pages as of this review; main City Hall line 970-375-5000. General building-permit questions: Building@DurangoCo.Gov. Fee-schedule calculation questions: 970-375-4850.. Official information: https://www.durangoco.gov/311/Applying-for-a-Building-Permit.

The City of Durango Community Development Department, Building Division issues building, plumbing/gas, and mechanical permits for all work within Durango city limits. Durango is a home-rule city with its own department; La Plata County's Building Division covers only unincorporated county areas, not the City of Durango.

No. All electrical permits and inspections in Durango are handled by the Colorado Department of Regulatory Agencies (DORA), State of Colorado Electrical Board, not the City Building Division. New electrical permits are obtained at dpo.colorado.gov/EandP/Permits.

Sources & verification

Verified against official sources. Last reviewed 2026-07-06.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Durango building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.