Unlike the City-issued permits documented elsewhere in this record, fire sprinkler and fire alarm system plan review, permitting, and inspection for work in Durango are handled directly by the independent Durango Fire Protection District (DFPD) Fire Marshal Division — NOT the City of Durango Building Division. This mirrors the pattern already documented in the localAmendments and commercial-building-permit entry, where DFPD performs all Life Safety review for multifamily/commercial projects. DFPD maintains its own dedicated OpenGov portal (durangofireco.portal.opengov.com), separate from the City's own building/planning OpenGov instance, and its own detailed NFPA-based fee schedule (Resolution 2024-15, effective January 1, 2025) that is entirely separate from the City's valuation-based Building Permit Fee Schedule.

Verified 2026-08-13 · Source

When you need this permit

  • Fire sprinkler systems, fire alarm systems, commercial kitchen suppression systems, water suppression tanks, standpipes, underground fire service mains, and dedicated detection/releasing function systems are all permitted, plan-reviewed, and inspected by DFPD's own Fire Marshal Division, per DFPD's Fire Protection System Permit Applications page
  • Applications are submitted through DFPD's own dedicated OpenGov portal (durangofireco.portal.opengov.com) — a SEPARATE OpenGov instance from the City of Durango's own building/planning portal (durangoco.portal.opengov.com)
  • A complete submittal requires scaled plan sets (PDF), specifications (PDF), supporting documentation, a scope-of-work description, and applicable fees; the portal accepts files up to 16 MB, with shared-link options for larger uploads
  • New Fire Code Plan Review fee (new construction, remodels, additions) is calculated as: Gross Area x Square Foot Construction Cost (from DFPD's own IBC-occupancy-group table) x 0.00263 permit fee multiplier — a different formula from, but functionally cross-referenced by, the City's own Building Permit Fee Schedule, which separately lists a 'DFPD Plan Review Fee — Applicable to multi-family, commercial and tenant finish projects (Contact DFPD)' line with no dollar amount published on the City's own schedule
  • Two sources give different IFC editions and neither has been reconciled by the agencies themselves: DFPD's Resolution 2024-15 (adopted December 2024) recites that the City of Durango adopted the 2018 IFC by Ordinance No. O-2022-3 effective January 1, 2022, and that La Plata County adopted the 2015 IFC by Ordinance No. O-2023-01 effective August 1, 2023 for DFPD's broader unincorporated service territory; the codesAdopted list documents the City's currently-adopted 2024 IFC, effective for new submittals not already in process before 01/01/2026. The DFPD resolution's recitals predate that City code-cycle update and have not been reissued with a newer citation. Confirm the currently-enforced IFC edition directly with DFPD (970-382-6001) for a specific project
  • Only fire sprinkler design, truss design sheets, and fire protection engineering may be deferred submittals within the City Building Division's initial MEP review (already documented elsewhere in this record); the DFPD Fire Code Plan Review package itself must still be submitted directly to DFPD, and DFPD's receipt is a prerequisite for the City building-permit application on all multifamily/commercial projects
  • Fire Alarm Control Panel replacement with a NOT like-for-like panel is treated as a new installation (full new-system fee); replacement with the same panel model still requires a permit and inspection but is not treated as a new system
  • Small modification/addition fee tiers apply below certain thresholds: NFPA 13/13R/13D/Combination sprinkler systems — 6 or fewer heads relocated/deleted/added = $150 flat; 7-20 heads = $250 plus $3.00/head; NFPA 72 fire alarm systems — 5 or fewer devices modified = $150 flat (Small Fire Alarm Project)
  • Water tanks/cisterns required to hold water supply storage for fire suppression systems need their own DFPD plan-review/acceptance-test permit ($650), EXCEPT water supply tanks for single-family residential suppression systems, which are exempt from this fee
  • Underground fire service mains (installing, extending, or altering) are permitted separately from the sprinkler system itself under 'Fire Protection Underground' ($400-$800 depending on how many inspection rounds the project requires)
  • NFPA 14 standpipes and NFPA 20 fire pumps are each reviewed and permitted separately from the base automatic fire sprinkler system ($400 per standpipe riser; $550 for fire pumps, single-family residences excluded)
  • Performing work requiring DFPD permit/approval without first obtaining it doubles the applicable plan review fee ('Work without approval or permit')
  • An Expeditious Fee option exists at the Fire Marshal's discretion for projects on a more stringent timeline: review completed within 7 days for an additional 50% of the plan review fee cost
  • THE ELECTRICAL WIRING PORTION of a fire alarm installation is separately permitted through the State of Colorado Electrical Board (DORA), per the City's own Do I Need a Permit? page, which explicitly lists 'fire alarm installation' among the electrical scopes handled by the State, not the City — mirroring the electrical/solar authority split already documented elsewhere in this record. DFPD's NFPA 72 permit governs the fire-alarm SYSTEM's life-safety design, plan review, and inspection; it does not substitute for the separate State electrical wiring permit.

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet — 0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Fire Code Plan Review — New Construction, Remodels, and Additions
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Fire Code Plan Review — permit fee is gross area x square foot… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Fire Code Plan Review — permit fee is gross area x square foot construction cost x a multiplier of 0.003682. The schedule's worked example is a 2-storey R-2 type VB structure, 16,000 gross square feet x $149.80 x .003682 = $8,825.02. The 2025 schedule's 0.00263 multiplier and its $6,303.58 example are superseded, and its example named type IVB where the 2026 edition names VB.
Gross Area (sq ft) x Square Foot Construction Cost (by IBC occupancy group/construction type) x 0.003682 permit fee multiplier
Water Tanks for Fire Suppression Systems (plan review + acceptance test)Water supply tanks for single-family residential suppression systems are exempt from this fee
$650.00
NFPA 13D/Combination New System or Major Remodel
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New System or Major Remodel — NFPA 13D/Combination at a flat $450.00. Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New System or Major Remodel — NFPA 13D/Combination at a flat $450.00. The 2026 edition removed the under-3,600 / 3,601-6,000 / 6,001+ square-foot tiers and the per-head add-on that the 2025 schedule applied to 13D. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$450.00
NFPA 13/13R Base Fee (New System or Major Remodel)
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New System or Major Remodel — NFPA 13/13R base fee $650.00 plus $4.00… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New System or Major Remodel — NFPA 13/13R base fee $650.00 plus $4.00 per head added, deleted, or relocated. The per-head rate rose from $3.00. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$650.00 plus $4.00 per head added, deleted, or relocated
Small Project Modification — NFPA 13/13R/13D/Combination, Level I (1 to 20 heads)
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Small project modification/addition — level I, 1 to 20 sprinkler heads… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Small project modification/addition — level I, 1 to 20 sprinkler heads relocated, deleted or added, $350.00. The 2026 edition redefined level I from 6 heads to 20 and eliminated the separate level II tier. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$350.00
Fire Protection Underground (installing/extending/altering underground fire service mains)
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Fire Protection Underground — $500.00 for a single round of… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Fire Protection Underground — $500.00 for a single round of inspections, $750.00 if the project is broken into two sections, $900.00 if broken into three. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$500.00 (single inspection round) / $750.00 (2 sections) / $900.00 (3 sections)
NFPA 14 Standpipe Review, Permit, and Inspection
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), NFPA 14 Standpipe Review, Permit and Inspection — $500.00 for each… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), NFPA 14 Standpipe Review, Permit and Inspection — $500.00 for each standpipe riser in the facility. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$500.00 per standpipe riser
NFPA 20 Fire Pumps for NFPA 13/13R SystemSingle-family residences excluded
$550.00
Commercial Cooking Fire Suppression System Review, Permit, and InspectionDFPD Fee Schedule, Resolution 2024-15 Exhibit A, Commercial Cooking Fire Suppression System Review, Permit, and Inspection; carried forward unchanged in the 2026 schedule adopted by Resolution 2025-11
$400.00 per system
Other Fire Suppression Systems (e.g. Clean Agent)
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Other Fire Suppression Systems (clean agent) — $500.00 per system. Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Other Fire Suppression Systems (clean agent) — $500.00 per system. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$500.00 per system
NFPA 72 New Fire Alarm System or Major Remodel
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New Fire Alarm Systems or Major Remodels — $600.00 per system plus $3.00 per device. Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), New Fire Alarm Systems or Major Remodels — $600.00 per system plus $3.00 per device. The per-device rate is unchanged; the base rose from $500.00. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$600.00 per system plus $3.00 per device
Small Fire Alarm Project (5 or fewer devices modified)
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Small Fire Alarm Project — modification to an existing NFPA 72 system… Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Small Fire Alarm Project — modification to an existing NFPA 72 system with five or fewer devices, $200.00. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$200.00
Dedicated/Releasing Function Fire Alarm System
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Dedicated/Releasing Function Fire Alarm System — review and inspection, $200.00. Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01), Dedicated/Releasing Function Fire Alarm System — review and inspection, $200.00. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$200.00
Phased Project — Each Additional Inspection
Durango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01) — phased suppression and phased fire alarm projects are each additional inspection at $175.00. Show full citationDurango Fire Protection District 2026 Fee Schedule, Exhibit A to Resolution 2025-11 (adopted 2025-12-09, effective 2026-01-01) — phased suppression and phased fire alarm projects are each additional inspection at $175.00. The Fire Code Plan Review section of the same schedule still states $150.00 for its own phased inspections, so confirm which applies. This supersedes the figure in Resolution 2024-15, which the record previously carried.
$175.00
Work Without Approval or PermitDFPD Fee Schedule, Resolution 2024-15 Exhibit A, Work without approval or permit; carried forward unchanged in the 2026 schedule adopted by Resolution 2025-11
Double Fee (plan review fee x 2)
Expeditious Fee (optional 7-day review)At the discretion of the Fire Marshal
Additional 50% of the plan review fee

Review timeline

Plan reviewDurango’s published plan-review target
0–21 business days

How long did your Fire Sprinkler / Fire Alarm System Permit (Durango Fire Protection District) permit actually take in Durango?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In Inspection

    Piping, wiring, and device placement inspected before concealment, per the governing system's DFPD plan review/permit

  2. 2

    Acceptance Test / Final Inspection

    System operational and code-compliant, verified by DFPD before the permit closes; water-tank installations specifically require an acceptance test per the DFPD fee schedule's own description of that permit type

See the full Durango inspection guide — scheduling & re-inspection fees →

Tips

  • Submit fire-system plans through DFPD's own OpenGov portal (durangofireco.portal.opengov.com), not the City of Durango's building-permit portal. Durango splits fire-system review out to an independent special district rather than handling it in-house, which is a common point of confusion.
  • DFPD's 21-day review SLA is an unusually concrete, published figure compared to most permit types in this record — but it covers only DFPD's own fire-sprinkler/fire-alarm review track, which runs in parallel with (not instead of) the City's separate Building Division plan review and its own 30-business-day figure.
  • Watch the small-project fee cliffs carefully: modifying a sprinkler system at 7 heads instead of 6, or a fire alarm system at 6 devices instead of 5, jumps you out of the flat $150 small-project tier and into a materially different fee structure.
  • The electrical wiring portion of a fire alarm system is a separate State of Colorado Electrical Board (DORA) permit, not part of DFPD's NFPA 72 permit — DFPD reviews the fire-alarm system's life-safety design and inspects the installed system, but does not substitute for the State's electrical wiring permit.
  • DFPD's own December 2024 fee-schedule resolution cites the City's 2018 IFC adoption (by a 2022 ordinance) in its recitals, which predates the City's own subsequently-adopted 2024 IFC cycle documented elsewhere in this record — confirm the currently-enforced fire code edition directly with DFPD (970-382-6001) rather than assuming either document alone is current.

Frequently asked questions

Durango requires a fire sprinkler / fire alarm system permit (durango fire protection district) for: Fire sprinkler systems, fire alarm systems, commercial kitchen suppression systems, water suppression tanks, standpipes, underground fire service mains, and dedicated detection/releasing function systems are all permitted, plan-reviewed, and inspected by DFPD's own Fire Marshal Division, per DFPD's Fire Protection System Permit Applications page; Applications are submitted through DFPD's own dedicated OpenGov portal (durangofireco.portal.opengov.com) — a SEPARATE OpenGov instance from the City of Durango's own building/planning portal (durangoco.portal.opengov.com); A complete submittal requires scaled plan sets (PDF), specifications (PDF), supporting documentation, a scope-of-work description, and applicable fees; the portal accepts files up to 16 MB, with shared-link options for larger uploads; New Fire Code Plan Review fee (new construction, remodels, additions) is calculated as: Gross Area x Square Foot Construction Cost (from DFPD's own IBC-occupancy-group table) x 0.00263 permit fee multiplier — a different formula from, but functionally cross-referenced by, the City's own Building Permit Fee Schedule, which separately lists a 'DFPD Plan Review Fee — Applicable to multi-family, commercial and tenant finish projects (Contact DFPD)' line with no dollar amount published on the City's own schedule; Two sources give different IFC editions and neither has been reconciled by the agencies themselves: DFPD's Resolution 2024-15 (adopted December 2024) recites that the City of Durango adopted the 2018 IFC by Ordinance No. O-2022-3 effective January 1, 2022, and that La Plata County adopted the 2015 IFC by Ordinance No. O-2023-01 effective August 1, 2023 for DFPD's broader unincorporated service territory; the codesAdopted list documents the City's currently-adopted 2024 IFC, effective for new submittals not already in process before 01/01/2026. The DFPD resolution's recitals predate that City code-cycle update and have not been reissued with a newer citation. Confirm the currently-enforced IFC edition directly with DFPD (970-382-6001) for a specific project; Only fire sprinkler design, truss design sheets, and fire protection engineering may be deferred submittals within the City Building Division's initial MEP review (already documented elsewhere in this record); the DFPD Fire Code Plan Review package itself must still be submitted directly to DFPD, and DFPD's receipt is a prerequisite for the City building-permit application on all multifamily/commercial projects; Fire Alarm Control Panel replacement with a NOT like-for-like panel is treated as a new installation (full new-system fee); replacement with the same panel model still requires a permit and inspection but is not treated as a new system; Small modification/addition fee tiers apply below certain thresholds: NFPA 13/13R/13D/Combination sprinkler systems — 6 or fewer heads relocated/deleted/added = $150 flat; 7-20 heads = $250 plus $3.00/head; NFPA 72 fire alarm systems — 5 or fewer devices modified = $150 flat (Small Fire Alarm Project); Water tanks/cisterns required to hold water supply storage for fire suppression systems need their own DFPD plan-review/acceptance-test permit ($650), EXCEPT water supply tanks for single-family residential suppression systems, which are exempt from this fee; Underground fire service mains (installing, extending, or altering) are permitted separately from the sprinkler system itself under 'Fire Protection Underground' ($400-$800 depending on how many inspection rounds the project requires); NFPA 14 standpipes and NFPA 20 fire pumps are each reviewed and permitted separately from the base automatic fire sprinkler system ($400 per standpipe riser; $550 for fire pumps, single-family residences excluded); Performing work requiring DFPD permit/approval without first obtaining it doubles the applicable plan review fee ('Work without approval or permit'); An Expeditious Fee option exists at the Fire Marshal's discretion for projects on a more stringent timeline: review completed within 7 days for an additional 50% of the plan review fee cost; THE ELECTRICAL WIRING PORTION of a fire alarm installation is separately permitted through the State of Colorado Electrical Board (DORA), per the City's own Do I Need a Permit? page, which explicitly lists 'fire alarm installation' among the electrical scopes handled by the State, not the City — mirroring the electrical/solar authority split already documented elsewhere in this record. DFPD's NFPA 72 permit governs the fire-alarm SYSTEM's life-safety design, plan review, and inspection; it does not substitute for the separate State electrical wiring permit.. If your project isn't listed, confirm with City of Durango Community Development Department, Building Division at 970-375-5000 before starting work.

In Durango, the published Fire Code Plan Review — New Construction, Remodels, and Additions is: Gross Area (sq ft) x Square Foot Construction Cost (by IBC occupancy group/construction type) x 0.003682 permit fee multiplier. Additional published fees: Water Tanks for Fire Suppression Systems (plan review + acceptance test) — $650.00; NFPA 13D/Combination New System or Major Remodel — $450.00; NFPA 13/13R Base Fee (New System or Major Remodel) — $650.00 plus $4.00 per head added, deleted, or relocated; Small Project Modification — NFPA 13/13R/13D/Combination, Level I (1 to 20 heads) — $350.00; Fire Protection Underground (installing/extending/altering underground fire service mains) — $500.00 (single inspection round) / $750.00 (2 sections) / $900.00 (3 sections); NFPA 14 Standpipe Review, Permit, and Inspection — $500.00 per standpipe riser; NFPA 20 Fire Pumps for NFPA 13/13R System — $550.00; Commercial Cooking Fire Suppression System Review, Permit, and Inspection — $400.00 per system; Other Fire Suppression Systems (e.g. Clean Agent) — $500.00 per system; NFPA 72 New Fire Alarm System or Major Remodel — $600.00 per system plus $3.00 per device; Small Fire Alarm Project (5 or fewer devices modified) — $200.00; Dedicated/Releasing Function Fire Alarm System — $200.00; Phased Project — Each Additional Inspection — $175.00; Work Without Approval or Permit — Double Fee (plan review fee x 2); Expeditious Fee (optional 7-day review) — Additional 50% of the plan review fee. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

DFPD's own page states 'Allow 21 days for review after full submittal, including fees.' An optional Expeditious Fee (an additional 50% of the plan review fee, at the Fire Marshal's discretion) can compress this to a 7-day review for projects on a tighter timeline.

You'll need: Fire Protection System Permit Application (DFPD OpenGov portal); Scaled Plan Set and Specifications (PDF). See the required-documents checklist on this page for details on each.

Durango requires 2 inspection(s) for a fire sprinkler / fire alarm system permit (durango fire protection district), in order: Rough-In Inspection, Acceptance Test / Final Inspection. Schedule each through City of Durango Community Development Department, Building Division (970-375-5000).

Apply through City of Durango Community Development Department, Building Division at 949 E 2nd Avenue, Durango, CO 81301. Phone: 970-375-5000, email: Building@DurangoCo.Gov. Office hours: Not published on the Building Division pages as of the last verification; main City Hall line 970-375-5000. General building-permit questions: Building@DurangoCo.Gov. Fee-schedule calculation questions: 970-375-4850.. Official information: https://www.durangoco.gov/311/Applying-for-a-Building-Permit.

Durango, Colorado has adopted: 2024 International Building Code (IBC) — City of Durango Building Codes page, effective for new projects not already in a planning process prior to 01/01/2026; 2024 International Residential Code (IRC); 2024 International Fire Code (IFC); 2024 International Energy Conservation Code (IECC); 2024 International Plumbing Code (IPC); 2024 International Mechanical Code (IMC); 2024 International Fuel Gas Code (IFGC); 2023 National Electrical Code (NEC); Colorado Model Electric Ready and Solar Ready Code (CMERSRC) — state-mandated, per City of Durango Building Codes page and Submittal Requirements page; Colorado Wildfire Resiliency Code (WRC) — state-mandated; City of Durango began enforcement April 1, 2026 per the Building Codes page and Do I Need a Permit? page; Transition provision: projects with full vertical construction drawings designed to the 2018 I-Codes and submitted to the Planning Division prior to January 1, 2026 may remain compliant with that older code cycle; all other new submittals must follow the 2024 I-Codes, 2023 NEC, CMERSRC, and Wildfire Resiliency Code; Code books available for review at Community Development and the City Clerk's Office; full municipal code at library.municode.com/co/durango. Local amendments apply — see the Durango overview page for the full list.

No. Fire sprinkler and fire alarm system permits in Durango are issued directly by the Durango Fire Protection District (DFPD) Fire Marshal Division through DFPD's own separate OpenGov portal, not by the City of Durango Building Division. DFPD's Fire Code Plan Review receipt is a prerequisite for the City's own building-permit application on multifamily/commercial projects, but the systems themselves are DFPD's permit, not the City's.

Sources & verification

Verified against official sources. Last reviewed 2026-08-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Durango building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Durango's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Durango yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Durango lands. Privacy.