Inspection sequence, scheduling, and re-inspection fees for building permits in Sterling, Colorado.

Verified 2026-07-06 · Source

How to schedule

Inspections are requested through the building department below.

Address
421 N. 4th Street, P.O. Box 4000, Sterling, CO 80751
Phone
(970) 522-9700, ext. 1109 (Marianne, permits and licenses); main line (970) 522-9700; fax (970) 521-0632
Office hours
Not published on the Permits and Licenses page as of this review; inspection requests are scheduled by phone at (970) 522-9700, with a stated same-day/next-day cutoff (see reviewTimelineNote on inspections below).

Published scheduling rules

  • Schedule inspections by calling (970) 522-9700 at least half a day ahead: requests before noon are done that afternoon, after noon the following morning. (Residential Building Permit (New Construction))
  • No plan-review turnaround SLA is published by the City for ANY permit type. The only published timing commitment is for INSPECTION scheduling: requests received before noon are completed that same afternoon, requests after noon are completed the following morning — this is a field-inspection scheduling commitment, not a permit-issuance timeline, and this file does not conflate the two. (General)

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Footing

    After excavation is complete and reinforcing steel and forms are in place, but prior to placement of concrete

  2. 2

    Foundation Wall

    After forms and reinforcing steel are in place, but prior to placement of concrete

  3. 3

    Underfloor

    After all under-floor building service equipment, conduit, and piping are in place, but prior to installation of concrete or floor sheathing

  4. 4

    Rough Mechanical

    After all wiring, pipes, and ducts are in place, but prior to concealment

  5. 5

    Framing

    After the roof, all framing, fire-blocking, and bracing are in place, and all pipes, chimneys, and vents are complete, and rough mechanical/plumbing/electrical have been inspected and approved (state inspectors for plumbing/electrical), but prior to installation of insulation and wallboard

  6. 6

    Wall Board

    After all gypsum board or lathing (interior or exterior) is in place, but before plastering is applied or gypsum board fasteners are taped and finished

  7. 7

    Final Mechanical

    After all service equipment has been installed and is ready to be put in service

  8. 8

    Final Building Inspection

    After the final mechanical, electrical, and plumbing inspections have been completed and signed off (electrical/plumbing sign-off comes from the State of Colorado), and the building is complete and ready to occupy

Applies to: Residential Addition / Remodel Permit

  1. 1

    Footing (if new footings)

    Before concrete pour, for additions with new foundation elements

  2. 2

    Rough Mechanical

    Wiring, pipes, and ducts in place before concealment

  3. 3

    Framing

    Framing complete and tied into existing structure, rough mechanical/plumbing/electrical approved, before insulation/wallboard

  4. 4

    Wall Board

    Gypsum board/lathing in place before taping/finishing

  5. 5

    Final Building Inspection

    After final mechanical, electrical (state), and plumbing (state) inspections are signed off

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Conducted by State of Colorado electrical inspectors before concealment; City Framing inspection requires this to be signed off first

  2. 2

    Final Electrical

    Conducted by State of Colorado electrical inspectors; City Final Building Inspection requires this to be signed off first

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    Conducted by State of Colorado electrical inspectors before concealment

  2. 2

    Final Electrical

    Conducted by State of Colorado electrical inspectors; charging circuit energized and verified

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    After all wiring, pipes, and ducts are in place, but prior to concealment

  2. 2

    Final Mechanical

    After all service equipment has been installed and is ready to be put into service

Applies to: Plumbing Permit

  1. 1

    Rough Plumbing

    Conducted by State of Colorado plumbing inspectors before concealment; City Framing inspection requires this to be signed off first

  2. 2

    Final Plumbing

    Conducted by State of Colorado plumbing inspectors; City Final Building Inspection requires this to be signed off first

Applies to: Residential/Commercial Solar Photovoltaic (PV) Permit

  1. 1

    Rough Electrical (State)

    Conducted by State of Colorado electrical inspectors before concealment; part of the same state-inspected process documented for Sterling's general Electrical Permit entry.

  2. 2

    Final Building Inspection (City)

    City final inspection of the racking/mounting structural scope; requires the state rough/final electrical sign-off to already be in hand, per the same mechanism documented for Sterling's Residential Building Permit entry.

Applies to: Roofing Permit (Re-Roof)

  1. 1

    Pre-Mid-Roof Inspection

    Mandatory in-person inspection required before the roof can be completed; 'No final roofs will be completed without a pre-mid inspection'

  2. 2

    Final Roof Inspection

    Completed roof — tearoff, ice barrier, flashing, ventilation, and fastening compliance verified per 2018 IRC as locally amended

Final inspection only: Demolition Permit, Fence Permit

Sterling building permits

Get alerts for Sterling

We'll email you when Sterling's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.