Change of Use Permit in Unincorporated Washington County, Colorado
Unincorporated Washington County has no distinct 'Change of Use Permit' application, procedure, or fee. Neither the current Planning & Zoning department webpage nor the Planning and Zoning Forms page lists any change-of-use-specific document among the County's full published set of land-use forms (Building Permit, Foundation Permit, Mobile/Manufactured Home Permit, USBR and its Amend/Extinguish forms, Subdivision Exemption, Temporary Use, Road Access, Road Cut, Petition for Vacation, Request for Address). A change of use is instead handled through one of two existing mechanisms, depending on what is actually changing: (1) a change to a commercial, mixed-use, or industrial USE of land (as distinct from the building itself) requires a 'Use by Special Review' (USBR) application — a public-hearing zoning-approval process under Resolution 2004-68 with its own $500.00 Administrative Review Fee, $150.00 Sign Posting Fee, and recording fees; or (2) a physical remodel/change tied to an existing building routes through the County's general Building Permit Application (Rev. 06-14), whose 'Class of work' options include 'Remodel' as one of only four checkboxes. Neither mechanism is labeled or fee-structured as a dedicated 'change of use permit' the way, for example, Northglenn's UDO Sec. 11-6-5(d) is.
Verified 2026-08-14 · Source
When you need this permit
- No standalone Change of Use Permit application exists — neither the County's current Planning & Zoning webpage nor its Forms page publishes one
- A change to a commercial, mixed-use, or industrial USE of unincorporated county land requires a Use by Special Review (USBR) application instead — a site-plan/public-hearing process through the Planning Commission then Board of County Commissioners (appeal to District Court), per Resolution 2004-68 and its amendments
- USBR's 'Principal Permitted Uses' categories (Community Business, Mixed Use Development, Industrial Uses) define what triggers this path — see the USBR-related documentation under residential-building-permit elsewhere in this record for the full enumerated list
- A physical remodel or interior change tied to an existing building (without a change in the land-use category itself) is filed as 'Remodel,' one of the four Class of Work options on the general Building Permit Application (Rev. 06-14) — the same form used for new construction and additions
- For any change requiring a building permit, County practice (per the general Building Permit Application) does not describe a separate change-of-use sign-off distinct from the building permit approval itself
Required documents
Check off what you have — your progress is saved on this device.
Fee schedule
No distinct change-of-use permit or fee exists. Show full citationHide
No distinct change-of-use permit or fee exists. If the change involves commercial/mixed-use/industrial use of the land, USBR's own published fees apply instead: $500.00 Administrative Review/Application Fee, Recording Fees ($13 first page + $5 each additional page), and a $150.00 Sign Posting Fee, all stated directly on the USBR application form. If the change is a physical remodel of an existing building, the general Building Permit Fee applies instead ($100.00, or $150.00 for a Use-by-Special-Review/commercial building, per the Building Permit Application's own fee grid — see residential-building-permit elsewhere in this record).Review timeline
Inspection process
See the full Unincorporated Washington County inspection guide — scheduling & re-inspection fees →
Tips
- Don't look for a 'Change of Use Permit' by that name in unincorporated Washington County — it doesn't exist. If you're changing a property's use to something commercial, mixed-use, or industrial, you need a Use by Special Review (USBR) application instead, with its own public hearing and $500+ fee set.
- If your project is really just a remodel or interior change to an existing building without a change in the underlying land use, the ordinary Building Permit Application (checked as 'Remodel') is the only step — no separate change-of-use paperwork is layered on top.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-14.
Applications & forms
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washington County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Unincorporated Washington County's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Unincorporated Washington County yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Unincorporated Washington County lands. Privacy.
Other permits in Unincorporated Washington County
Change of Use Permit in other cities
Compare change of use permit fees across Colorado →
Look up this fee in a different city →
Now live
Build your Unincorporated Washington County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Washington County — in one checklist. Free, for any city and any number of projects.
Get started →