Mobile or Manufactured Home Permit (with Foundation Permit if applicable) — Unincorporated Washington County, Colorado · Requirements sheet
Verified 2026-07-06 · Source: https://washingtoncounty.colorado.gov/sites/g/files/lrnvjt1191/files/MP%20Mobile%20Home%20Permit%20%20.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Mobile or Manufactured Home Permit (with Foundation Permit if applicable) in Unincorporated Washington County, Colorado
A separate application (distinct from the general Building Permit) for placing a mobile or manufactured home in unincorporated Washington County. Installation and inspection standards are set by the Colorado Division of Housing (state), not a county-adopted code; the County collects its own permit fee and the state's inspection/insignia fee, arranges the state-required inspection, and — if the unit will sit on a permanent foundation or basement — requires a separate Foundation Permit using the same County-designated inspector.
Verified 2026-07-06 · Source
When you need this permit
- Completed Mobile or Manufactured Home Permit Application (Rev. 09-12) — legal description, road/highway access, reason for application (new/addition/alteration/repair/move), type and year built of unit, size, acreage, sewer facility, and water source
- Evidence of the total value of the unit or home attached to the application (used to calculate use tax and the state inspection fee)
- Foundation Permit (Rev. 09-12), obtained separately or alongside this application, if the unit will be set on a permanent foundation or basement — inspected by the same County inspector before the home is set
- Evidence of a water source/well permit and either a Northeast Colorado Health Department (NCHD) septic permit or proof that process has begun
- A temporary permit must be posted on the unit after application and fee payment, per State of Colorado Division of Housing requirements (Division of Housing Resolution 38)
- Placement and inspection must be completed within six (6) months of the date the application is signed
- Contact the County-designated building inspector directly (contact info provided by the County after application) to arrange required inspections before occupancy; an installation insignia sticker is issued by the State once inspections are satisfactorily completed
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Foundation Inspection (if applicable)
Required before setting the home if it will sit on a permanent foundation or basement; performed by the same County-designated inspector who performs the mobile/manufactured-home inspection
- 2
State-Required Mobile/Manufactured Home Inspection
Arranged directly with the County-designated building inspector after permit issuance; the inspector completes State of Colorado Division of Housing checklist forms. Once satisfactorily completed, an installation insignia sticker is issued and must be placed on the unit as required by the State.
Tips
- Budget for three separate charges, not one: the $100 County permit fee, the $435 state Division of Housing inspection/insignia fee, and 1.5% use tax on the home's declared value — all combined into one 'TOTAL FEES' payment to Washington County on the application worksheet.
- If the home will sit on a permanent foundation or basement, apply for the separate $100 Foundation Permit at the same time — it is not included in the Mobile/Manufactured Home Permit fees.
- Start your Northeast Colorado Health Department well/septic application in parallel — the County requires evidence of that process before finalizing this permit.
- Installation standards (and the checklist the inspector uses) come from the State of Colorado Division of Housing, not a county-adopted building code — Washington County administers the paperwork and fee collection but does not set its own separate manufactured-home standard.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-06.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Unincorporated Washington County building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Unincorporated Washington County
Mobile or Manufactured Home Permit (with Foundation Permit if applicable) in other cities
Look up this fee in a different city →
Now live
Build your Unincorporated Washington County project checklist
Describe your project once and get every permit, document, and fee it triggers in Unincorporated Washington County — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →