Required for electrical service changes, wiring, and related electrical work in Lochbuie. Fee-setting is explicitly deferred to the Colorado State Electrical Board (DORA) schedule plus a 15% Town surcharge — Lochbuie does NOT run its own locally-set electrical fee table, per the Town's April 2026 Fee Schedule. Electrical Service Change (residential only, by amp upgrade count) qualifies as a One Stop Permit not requiring plan review.

Verified 2026-07-23 · Source

When you need this permit

  • Fee calculated per the State of Colorado Electrical Board's own fee schedule (CRS 12-23-117(3)) plus a 15% Town surcharge — confirms Colorado-specific rule #3 (state board default) applies to Lochbuie electrical permits
  • Electrical contractors must hold current Colorado Electrical Board (DORA) licensure and register with the Town (Class E registration)
  • Residential Electrical Service Change qualifies as a One Stop Permit (no plan review required, typically issued within 24 hours) — application must state the number of amps being upgraded
  • Other electrical work not meeting the One Stop criteria is processed as a standard permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Electrical Permit FeeTown of Lochbuie Fees, updated April 2026, Section C item 7 — this is a direct pass-through of the CRS 12-23-117(3) state-mandated schedule, not a locally-set fee table
Electrical Permit fees as charged by the State of Colorado Electrical Board, plus 15%
Class E (Electrical) Contractor License — All Classes Registration Fee
The Contractor Licenses webpage (lochbuie.org/community-dev/page/contractor-licenses) and the April 2026 Town Fees PDF (lochbuie.org/media/16666) agree and reconcile cleanly once the table structure… Show full citationThe Contractor Licenses webpage (lochbuie.org/community-dev/page/contractor-licenses) and the April 2026 Town Fees PDF (lochbuie.org/media/16666) agree and reconcile cleanly once the table structure is read correctly: (1) a flat 'All Classes Registration Fee (incl. Class E)' of $15.00/year applies to every contractor class, Class E included; (2) a SEPARATE per-class 'Registration' fee line applies on top of that for Classes A/B/C/D/P/M/MP ($150/$100/$75/$50/$75/$75/$100 respectively) but Class E is the only class with NO separate per-class registration line (i.e. its per-class add-on is $0.00) — so Class E's total is $15.00 (flat fee) + $0.00 (class add-on) = $15.00. This is confirmed arithmetically by both sources' own quarterly proration tables, which each show Class E's total due as a flat $15.00 in every quarter (Jan-Mar, Apr-Jun, Jul-Sep, Oct-Dec) — unlike every other class, whose quarterly total steps down each quarter (because their nonzero per-class fee is prorated while the $15 flat registration fee is not). The apparent 'discrepancy' between the two sources is two different, correctly-priced line items compared as if they were the same line item. Total current cost for Class E: $15.00/year, no proration variance.
$15.00 per calendar year, flat and NOT prorated by quarter

Review timeline

Plan review
Not published — contact the department

How long did your Electrical Permit permit actually take in Lochbuie?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment

  2. 2

    Final Inspection

    Devices installed, panel labeled, system energized and verified

See the full Lochbuie inspection guide — scheduling & re-inspection fees →

Tips

  • Lochbuie's electrical fees are a direct pass-through of the Colorado State Electrical Board's own fee schedule plus the Town's 15% surcharge — do not expect a locally-published flat-rate electrical fee table; the applicable base rate is set by the State of Colorado, not the Town.
  • The apparent 'discrepancy' between the Contractor Licenses webpage ($0.00 Class E registration) and the April 2026 Fee Schedule PDF ($15.00 All Classes Registration Fee incl. Class E) is not actually a conflict — both sources agree Class E's total annual cost is a flat $15.00 (the $15 flat 'All Classes' fee plus a $0.00 Class-E-specific add-on, borne out by both documents' own quarterly proration tables showing $15.00 due in every quarter for Class E). Contractor
  • A residential Electrical Service Change (amp upgrade) qualifies for the faster One Stop Permit track — state the number of amps being upgraded on your application to use this track.

Frequently asked questions

Lochbuie requires an electrical permit for: Fee calculated per the State of Colorado Electrical Board's own fee schedule (CRS 12-23-117(3)) plus a 15% Town surcharge — confirms Colorado-specific rule #3 (state board default) applies to Lochbuie electrical permits; Electrical contractors must hold current Colorado Electrical Board (DORA) licensure and register with the Town (Class E registration); Residential Electrical Service Change qualifies as a One Stop Permit (no plan review required, typically issued within 24 hours) — application must state the number of amps being upgraded; Other electrical work not meeting the One Stop criteria is processed as a standard permit. If your project isn't listed, confirm with Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 before starting work.

In Lochbuie, the published Electrical Permit Fee is: Electrical Permit fees as charged by the State of Colorado Electrical Board, plus 15%. Additional published fees: Class E (Electrical) Contractor License — All Classes Registration Fee — $15.00 per calendar year, flat and NOT prorated by quarter. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lochbuie does not publish a plan-review timeline for this permit. Contact Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 for current turnaround.

You'll need: Building/Electrical Permit Application; Town of Lochbuie Contractor License (Class E - Electrical). See the required-documents checklist on this page for details on each.

Lochbuie requires 2 inspection(s) for an electrical permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt (303-655-9308).

Apply through Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 703 Weld County Rd. 37 (WCR 37), Lochbuie, CO 80603. Phone: 303-655-9308, email: building@lochbuie.org. Office hours: Town of Lochbuie main line 303-655-9308 (fax 303-655-9311/9312), Monday-Thursday 7am-6pm (4-day/10-hour Town office schedule per site footer). Inspections are scheduled and performed by SAFEbuilt directly: 303-774-0454 or firestone-building@safebuilt.com. Chief Building Official (SAFEbuilt) Tim Moroney: 970-545-3555. Community Development Director Kevin Wrede: 303-990-5324. Community Development Technician Rachael Bender (fee payments): 303-990-5776.. Official information: https://www.lochbuie.org/community-dev/page/building-permits-and-inspections.

Lochbuie, Colorado has adopted: 2021 International Plumbing Code (IPC) — per the Town's live Building Department webpage (Adopted Building Codes section), the current governing statement; 2021 International Energy Conservation Code (IECC) — per the same live webpage statement; 2023 National Electrical Code (NEC) — per the same live webpage statement; Municipal Code Chapter 18 (Building Regulations), Town of Lochbuie — the Town's webpage directs to 'Chapter 18 - Building Regulations' of the Municode-hosted Municipal Code for local amendments. The department webpage's own explicit code-list statement (2021 IPC/IECC, 2023 NEC) is treated as the current, governing, actively-maintained source, since a live department page is a stronger authority than a static/undated artifact.; Document-currency conflict: three different code vintages appear across the Town's own published materials — the live Building Permits webpage states 2021 IPC/2021 IECC/2023 NEC; the 'Design Criteria Town of Lochbuie' PDF (undated) lists 2018 IRC/2018 IECC/2017 NEC for residential and 2018 IBC/IPC/IMC/IFGC/IECC/2017 NEC for commercial, plus 2018 IPMC/IEBC/Swimming Pool & Spa Code as 'Other Adopted Codes'; and SAFEbuilt's own trade-specific guidance documents cite yet other editions (PV Submittal Requirements, last revised 10.22.2021, cites '2020 NEC, 2018 International Codes'; the Re-Roof Requirements guide states 'Current code 2018 IRC'). No IBC or IRC edition is named anywhere on the live Building Permits webpage itself — only IPC, IECC, and NEC are explicitly stated there. Because the department's own webpage is the most current authority, this record treats 2021 IPC/2021 IECC/2023 NEC as current, and lists 2018-cycle IRC/IBC/IMC/IFGC/IPMC/IEBC/Swimming Pool & Spa Code from the Design Criteria PDF as the best-available (but visibly stale, per the department's own newer NEC/IPC/IECC citations) reference point for those code families pending confirmation directly with the Building Department.; 2018 International Residential Code (IRC) — per the Design Criteria Town of Lochbuie PDF (undated, 'Residential Construction' column); not restated on the live webpage, so carried at partial confidence pending direct confirmation; 2018 International Building Code (IBC), 2018 International Mechanical Code (IMC), 2018 International Fuel Gas Code (IFGC) — per the same Design Criteria PDF ('Commercial Construction' column); not restated on the live webpage, partial confidence; 2018 International Property Maintenance Code (IPMC), 2018 International Existing Building Code (IEBC), 2018 Swimming Pool & Spa Code — per the same Design Criteria PDF ('Other Adopted Codes' column); partial confidence. Local amendments apply — see the Lochbuie overview page for the full list.

No. Per the Town's April 2026 Fee Schedule, electrical permit fees are 'as charged by the State of Colorado Electrical Board plus 15%' — Lochbuie defers fee-setting to the state board's own schedule (CRS 12-23-117(3)) and adds the maximum local surcharge the statute allows, rather than publishing its own locally-set electrical fee table.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lochbuie building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Lochbuie's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Lochbuie yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Lochbuie lands. Privacy.