Skip to main content
PermitBase

Demolition Permit in Lochbuie, Colorado

Required to demolish a building or structure in Lochbuie. Governed by the Town's Building Division Plan Submittal Checklist for Demolition Permits, a distinct and comparatively light document set relative to new-construction plan review.

Verified 2026-07-23 · Source

When you need this permit

  • Complete Building Application
  • Contractor's License (if applicable) Contractor
  • Contractor's Liability insurance, minimum $100,000
  • Note from the (county) assessor's office stating all property taxes are paid
  • Certificate of asbestos inspection and abatement, if required
  • Plans/documents will not be accepted in part — the checklist states plan review will not take place, nor will any partial submittal be held, until all required documents are received
  • Applicant must post the issued inspection card in a location visible from the street and is responsible for calling the Building Division to request the required inspection

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 2 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Demolition permit feeVerified-negative, closed 2026-07-23 after an exhaustive new re-chase beyond the original pass: (1) independently re-fetched and re-read the live April 2026 Fee Schedule PDF (lochbuie.org/media/16666) in full, line by line — no 'Demolition' item anywhere among Sections A-F; (2) re-fetched the live Demolition Requirements checklist (lochbuie.org/media/5281) — lists required submittal documents only, states no fee figure; (3) re-fetched the live general Building Permit Application PDF (lochbuie.org/media/6036) — its fee-line boxes (Building Permit, Plan Review, Use Tax, Admin Fee, itemized utility fees) are generic to all permit types including demolition, with no demolition-specific box; (4) re-fetched the live Guides and Checklists page and the live Permit Fees landing page — neither adds any demolition fee info beyond linking the same two PDFs; (5) probed the CommunityConnect/CommunityCore applicant portal (app.communitycore.com) directly — public root loads only an authenticated SPA shell, no public fee API surfaced, and the jurisdiction-specific path returns 404 without login, so this avenue is a dead end without contractor credentials; (6) NEW avenue not previously tried: rendered the Town's actual codified ordinance, Municipal Code Chapter 18 (Building Regulations), live via a JS-capable browser at library.municode.com (version dated Feb 9, 2026, current) rather than relying on a curl shell or Wayback snapshot as the prior pass did — confirmed Chapter 18, Article I (Code Adoptions) amends IBC 109.4/109.6 and IRC R108.4-108.6 to authorize the Town to charge an 'investigation fee' for unpermitted work and to set/refund permit fees generally, but nowhere codifies a specific dollar figure for demolition (or any other permit type) in the ordinance itself; fee dollar amounts are delegated entirely to the administratively-set Fee Schedule, which itself (per items 1-4 above) has no demolition line. Article II's manufactured-home-specific 'building (move-out) permit' fee (set by separate Board of Trustees resolution) is the only demolition-adjacent fee actually named in the Municipal Code, and it applies only to manufactured/mobile homes being demolished/removed, not general building demolition (see the existing $300 Move-Out Fee entry under permitTypes for the manufactured-housing category). Conclusion: this is a genuine, actively confirmed gap in what the Town publishes -- not an omission on this file's part -- so demolition permits are billed under the general/catch-all mechanism per the department's own practice.
No dedicated dollar figure exists anywhere Lochbuie publishes; billed under the general valuation-based Building Permit Fee Schedule or, absent a stated valuation, the $50.00 'Building permits which no fee is specifically indicated' catch-all rate (Specialized Permit Fee Schedule item 12)

Review timeline

Plan review
Not published — contact the department

How long did your Demolition Permit permit actually take in Lochbuie?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Final Inspection

    Only required inspection listed on the Demolition Permit checklist

See the full Lochbuie inspection guide — scheduling & re-inspection fees →

Tips

  • Gather all five required items (application, contractor's license if applicable, $100,000 minimum liability certificate, assessor's tax-paid note, and asbestos certificate if required) before submitting — the Town explicitly will not accept a partial demolition submittal for review. Contractor
  • Confirmed 2026-07-23 (re-checked every Town-published fee document plus the codified Municipal Code itself, rendered live): Lochbuie genuinely does not publish a specific demolition fee amount anywhere. Budget for either the general valuation-based Building Permit Fee Schedule or the $50.00 catch-all rate, and confirm the exact amount directly with the Building Department (303-990-5776) before applying.

Frequently asked questions

Lochbuie requires a demolition permit for: Complete Building Application; Contractor's License (if applicable); Contractor's Liability insurance, minimum $100,000; Note from the (county) assessor's office stating all property taxes are paid; Certificate of asbestos inspection and abatement, if required; Plans/documents will not be accepted in part — the checklist states plan review will not take place, nor will any partial submittal be held, until all required documents are received; Applicant must post the issued inspection card in a location visible from the street and is responsible for calling the Building Division to request the required inspection. If your project isn't listed, confirm with Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 before starting work.

In Lochbuie, the published Demolition permit fee is: No dedicated dollar figure exists anywhere Lochbuie publishes; billed under the general valuation-based Building Permit Fee Schedule or, absent a stated valuation, the $50.00 'Building permits which no fee is specifically indicated' catch-all rate (Specialized Permit Fee Schedule item 12). These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lochbuie does not publish a plan-review timeline for this permit. Contact Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 for current turnaround.

You'll need: Demolition Permit — Building Division Plan Submittal Checklist; Assessor's Office Tax-Paid Confirmation Letter. Depending on your project, Lochbuie may also ask for: Certificate of Asbestos Inspection and Abatement. See the required-documents checklist on this page for details on each.

A certificate of asbestos inspection and abatement is required 'if required' per the Demolition Permit checklist — meaning it applies when applicable (e.g., based on the structure's age/materials), not universally to every demolition, though the Town does not further define the trigger on the checklist itself.

Apply through Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 703 Weld County Rd. 37 (WCR 37), Lochbuie, CO 80603. Phone: 303-655-9308, email: building@lochbuie.org. Office hours: Town of Lochbuie main line 303-655-9308 (fax 303-655-9311/9312), Monday-Thursday 7am-6pm (4-day/10-hour Town office schedule per site footer). Inspections are scheduled and performed by SAFEbuilt directly: 303-774-0454 or firestone-building@safebuilt.com. Chief Building Official (SAFEbuilt) Tim Moroney: 970-545-3555. Community Development Director Kevin Wrede: 303-990-5324. Community Development Technician Rachael Bender (fee payments): 303-990-5776.. Official information: https://www.lochbuie.org/community-dev/page/building-permits-and-inspections.

Lochbuie, Colorado has adopted: 2021 International Plumbing Code (IPC) — per the Town's live Building Department webpage (Adopted Building Codes section), the current governing statement; 2021 International Energy Conservation Code (IECC) — per the same live webpage statement; 2023 National Electrical Code (NEC) — per the same live webpage statement; Municipal Code Chapter 18 (Building Regulations), Town of Lochbuie — the live webpage directs to 'Chapter 18 - Building Regulations' of the Municode-hosted Municipal Code for local amendments; Municode's library.municode.com renders chapter text via a JavaScript/Angular single-page application backed by a private API, which could not be retrieved directly (repeated 403s/404s on documented API-guess and Wayback Machine snapshot attempts, all of which returned only the unrendered JS shell, not chapter text) — the live department webpage's own explicit code-list statement (2021 IPC/IECC, 2023 NEC) is treated as the current, governing, actively-maintained source per this corpus's standing practice of trusting a live department page over a static/undated artifact, consistent with the Vail file's precedent.; Document-currency conflict noted honestly: three different code vintages appear across the Town's own published materials — the live Building Permits webpage states 2021 IPC/2021 IECC/2023 NEC; the 'Design Criteria Town of Lochbuie' PDF (undated) lists 2018 IRC/2018 IECC/2017 NEC for residential and 2018 IBC/IPC/IMC/IFGC/IECC/2017 NEC for commercial, plus 2018 IPMC/IEBC/Swimming Pool & Spa Code as 'Other Adopted Codes'; and SAFEbuilt's own trade-specific guidance documents cite yet other editions (PV Submittal Requirements, last revised 10.22.2021, cites '2020 NEC, 2018 International Codes'; the Re-Roof Requirements guide states 'Current code 2018 IRC'). No IBC or IRC edition is named anywhere on the live Building Permits webpage itself — only IPC, IECC, and NEC are explicitly stated there. Per the live-webpage-wins convention, this file treats 2021 IPC/2021 IECC/2023 NEC as verified-current, and lists 2018-cycle IRC/IBC/IMC/IFGC/IPMC/IEBC/Swimming Pool & Spa Code from the Design Criteria PDF as the best-available (but visibly stale, per the department's own newer NEC/IPC/IECC citations) reference point for those code families pending confirmation directly with the Building Department.; 2018 International Residential Code (IRC) — per the Design Criteria Town of Lochbuie PDF (undated, 'Residential Construction' column); not restated on the live webpage, so carried at partial confidence pending direct confirmation; 2018 International Building Code (IBC), 2018 International Mechanical Code (IMC), 2018 International Fuel Gas Code (IFGC) — per the same Design Criteria PDF ('Commercial Construction' column); not restated on the live webpage, partial confidence; 2018 International Property Maintenance Code (IPMC), 2018 International Existing Building Code (IEBC), 2018 Swimming Pool & Spa Code — per the same Design Criteria PDF ('Other Adopted Codes' column); partial confidence. Local amendments apply — see the Lochbuie overview page for the full list.