Skip to main content
PermitBase

Rooftop Solar / Photovoltaic Permit in Lochbuie, Colorado

Required for solar panel installation or replacement in Lochbuie. Governed by SAFEbuilt's Photovoltaic System Submittal Requirements guide (last revised 10.22.2021), which cites '2020 NEC, 2018 International Codes' as the applicable current codes for this specific guide — yet another vintage than the live Building Department webpage's 2021 IPC/IECC + 2023 NEC statement (see codesAdopted currency note). Not listed among the One Stop Permit categories, implying plan review applies.

Verified 2026-07-20 · Source

When you need this permit

  • Permit application (emailed to Town or via online portal) fully completed, with valuation based on total contract cost to customer including materials, items, and labor
  • Separate plan review required for each building/address requiring a separate permit
  • Structural engineer's stamped letter required, stating design to a minimum ground snow load of 30 psf, wind speed of 115 mph Vult, wind exposure C, and Seismic Design Category B, addressing added roof weight and wind load from panels, and roof-connection/embedment type
  • Ground-mounted systems require a separate engineer-stamped letter for system support and wind load, using the same 30 psf/115 mph Vult/Exposure C/SDC B design basis
  • Electrical plans: four-line diagram (module count, circuit assignment, wire sizes/insulation, conduit sizes, junction boxes, inverter type, combiner panel, disconnect, meter, fuses/breakers, grounding), equipment ampacity/volts/wattage specification, wire/disconnect/fuse sizing calculations (roof-mount systems must use 56-60 degC worst-case ambient temperature for conductor ampacity derating), DC inverter selection calculation, current equipment cut sheets, equipment location plan, and all labeling/directories/plaques
  • Building/structural plans: roof layout with panel locations and roof dimensions, fire pathways/setbacks/equipment protection per the IRC or IFC as applicable, roof connection detail matching the engineer's letter and cut sheets, site plan showing equipment location and distances to property lines, and design criteria stated per the current codes
  • The color red may not be used anywhere on submitted plans by the applicant's design team — reserved exclusively for the plans examiner's markup
  • Zoning compliance is the applicant's responsibility to verify directly with the jurisdiction
  • Resubmittals must cloud all changed areas, include a detailed explanation of changes, note any additional costs, and be emailed to coloradoplanreview@safebuilt.com (not directly to the plans examiner)

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Electrical Permit Fee (Section applies to PV electrical scope)
Same state-board pass-through mechanism as the general Electrical Permit — no PV-specific flat fee exists. Show full citationSame state-board pass-through mechanism as the general Electrical Permit — no PV-specific flat fee exists. The April 2026 Town of Lochbuie Fees PDF's full Specialized Permit Fee Schedule (Fire Sprinkler, Fence, Evaporative Cooler, Spas/Hot Tubs, Water Heaters, Re-Roof, AC/Furnace, etc.) contains no 'Solar' or 'PV' or 'Photovoltaic' line item. Lochbuie also does not appear on SolarAPP+'s Colorado participant list (gosolarapp.org/landing-pages/solarapp-colorado; only Bennett, Wheat Ridge, Denver, Alamosa County, and Gilpin County offer full plan review there). Colorado's statewide solar-permit fee cap (C.R.S. 24-48.5-113, extended through 12-31-2029 by HB21-1284) sets a $500 residential/$1,000 nonresidential ceiling on the combined solar-related fees Lochbuie may charge, but the town's own actual combined dollar total (electrical state-board-plus-15% + valuation-based building fee) remains genuinely unpublished as a single figure. Base-rate figures per two current documents: the DORA State Electrical Board's own fee schedule (townoflarkspur.org/media/2901, Section B "Commercial and other fees": $100 base for valuation up to $2,000, plus $10/thousand above) and Larimer County's current Table 1-E (larimer.org/sites/default/files/2020_electrical_fee_table.pdf: $120 base, plus $9.60/thousand, with solar explicitly named in that bracket and the $500/$1,000 cap cited directly). Colorado Revised Statutes § 12-23-117 permits a municipality like Lochbuie to charge up to 1.15x the state schedule, consistent with Lochbuie's own "plus 15%" mechanism.
State Electrical Board valuation-based schedule, plus 15%: base fee ~$100-$120 (scales to ~$115-$138 with the 15% local surcharge) for job valuation up to $2,000, plus roughly $10-$11.50 per $1,000 of valuation above that (roughly $11.50-$13.25 with the 15% surcharge) — capped in aggregate at $500 residential/$1,000 commercial by C.R.S. § 24-48.5-113
Building Permit Fee (valuation-based, for the structural/roof-mount scope)Town of Lochbuie Building Permit Fees (updated April 2026). The structural and roof-mount scope carries no solar-specific line item; it is billed on the general valuation table, based on total contract cost to the customer. The electrical scope is permitted separately.
Per the general Building Permit Fee Schedule, based on total contract cost to customer

Review timeline

Plan review
Not published — contact the department

How long did your Rooftop Solar / Photovoltaic Permit permit actually take in Lochbuie?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, and disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified against the engineer-stamped letter and approved plans

See the full Lochbuie inspection guide — scheduling & re-inspection fees →

Tips

  • Solar/PV submittals require BOTH a structural engineer letter (roof weight/wind load) AND full electrical plan documentation (four-line diagram, cut sheets, ampacity calculations) — this is a more document-intensive submittal than the One Stop-eligible trades.
  • Never use red ink/markup on submitted plans — SAFEbuilt reserves that color exclusively for the plans examiner's own comments.
  • Resubmittals must go to coloradoplanreview@safebuilt.com, not directly to your assigned plans examiner, and must clearly cloud all changed plan areas.
  • The PV Submittal Requirements guide (last revised 2021) cites '2020 NEC, 2018 International Codes' — neither matches the live Building Department webpage's current 2021 IPC/IECC + 2023 NEC statement. Confirm the governing code edition directly with SAFEbuilt (coloradoplanreview@safebuilt.com) before finalizing engineering calculations.

Frequently asked questions

Lochbuie requires a rooftop solar / photovoltaic permit for: Permit application (emailed to Town or via online portal) fully completed, with valuation based on total contract cost to customer including materials, items, and labor; Separate plan review required for each building/address requiring a separate permit; Structural engineer's stamped letter required, stating design to a minimum ground snow load of 30 psf, wind speed of 115 mph Vult, wind exposure C, and Seismic Design Category B, addressing added roof weight and wind load from panels, and roof-connection/embedment type; Ground-mounted systems require a separate engineer-stamped letter for system support and wind load, using the same 30 psf/115 mph Vult/Exposure C/SDC B design basis; Electrical plans: four-line diagram (module count, circuit assignment, wire sizes/insulation, conduit sizes, junction boxes, inverter type, combiner panel, disconnect, meter, fuses/breakers, grounding), equipment ampacity/volts/wattage specification, wire/disconnect/fuse sizing calculations (roof-mount systems must use 56-60 degC worst-case ambient temperature for conductor ampacity derating), DC inverter selection calculation, current equipment cut sheets, equipment location plan, and all labeling/directories/plaques; Building/structural plans: roof layout with panel locations and roof dimensions, fire pathways/setbacks/equipment protection per the IRC or IFC as applicable, roof connection detail matching the engineer's letter and cut sheets, site plan showing equipment location and distances to property lines, and design criteria stated per the current codes; The color red may not be used anywhere on submitted plans by the applicant's design team — reserved exclusively for the plans examiner's markup; Zoning compliance is the applicant's responsibility to verify directly with the jurisdiction; Resubmittals must cloud all changed areas, include a detailed explanation of changes, note any additional costs, and be emailed to coloradoplanreview@safebuilt.com (not directly to the plans examiner). If your project isn't listed, confirm with Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 before starting work.

In Lochbuie, the published Electrical Permit Fee (Section applies to PV electrical scope) is: State Electrical Board valuation-based schedule, plus 15%: base fee ~$100-$120 (scales to ~$115-$138 with the 15% local surcharge) for job valuation up to $2,000, plus roughly $10-$11.50 per $1,000 of valuation above that (roughly $11.50-$13.25 with the 15% surcharge) — capped in aggregate at $500 residential/$1,000 commercial by C.R.S. § 24-48.5-113. Additional published fees: Building Permit Fee (valuation-based, for the structural/roof-mount scope) — Per the general Building Permit Fee Schedule, based on total contract cost to customer. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Lochbuie does not publish a plan-review timeline for this permit. Contact Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 303-655-9308 for current turnaround.

You'll need: Building/Electrical Permit Application — Solar/PV scope; Structural Engineer Stamped Letter; Four-Line Electrical Diagram and Equipment Cut Sheets. See the required-documents checklist on this page for details on each.

Lochbuie requires 2 inspection(s) for a rooftop solar / photovoltaic permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt (303-655-9308).

Apply through Town of Lochbuie Building Department (Community Development), building services contracted to SAFEbuilt at 703 Weld County Rd. 37 (WCR 37), Lochbuie, CO 80603. Phone: 303-655-9308, email: building@lochbuie.org. Office hours: Town of Lochbuie main line 303-655-9308 (fax 303-655-9311/9312), Monday-Thursday 7am-6pm (4-day/10-hour Town office schedule per site footer). Inspections are scheduled and performed by SAFEbuilt directly: 303-774-0454 or firestone-building@safebuilt.com. Chief Building Official (SAFEbuilt) Tim Moroney: 970-545-3555. Community Development Director Kevin Wrede: 303-990-5324. Community Development Technician Rachael Bender (fee payments): 303-990-5776.. Official information: https://www.lochbuie.org/community-dev/page/building-permits-and-inspections.

Lochbuie, Colorado has adopted: 2021 International Plumbing Code (IPC) — per the Town's live Building Department webpage (Adopted Building Codes section), the current governing statement; 2021 International Energy Conservation Code (IECC) — per the same live webpage statement; 2023 National Electrical Code (NEC) — per the same live webpage statement; Municipal Code Chapter 18 (Building Regulations), Town of Lochbuie — the Town's webpage directs to 'Chapter 18 - Building Regulations' of the Municode-hosted Municipal Code for local amendments. The department webpage's own explicit code-list statement (2021 IPC/IECC, 2023 NEC) is treated as the current, governing, actively-maintained source, since a live department page is a stronger authority than a static/undated artifact.; Document-currency conflict: three different code vintages appear across the Town's own published materials — the live Building Permits webpage states 2021 IPC/2021 IECC/2023 NEC; the 'Design Criteria Town of Lochbuie' PDF (undated) lists 2018 IRC/2018 IECC/2017 NEC for residential and 2018 IBC/IPC/IMC/IFGC/IECC/2017 NEC for commercial, plus 2018 IPMC/IEBC/Swimming Pool & Spa Code as 'Other Adopted Codes'; and SAFEbuilt's own trade-specific guidance documents cite yet other editions (PV Submittal Requirements, last revised 10.22.2021, cites '2020 NEC, 2018 International Codes'; the Re-Roof Requirements guide states 'Current code 2018 IRC'). No IBC or IRC edition is named anywhere on the live Building Permits webpage itself — only IPC, IECC, and NEC are explicitly stated there. Because the department's own webpage is the most current authority, this record treats 2021 IPC/2021 IECC/2023 NEC as current, and lists 2018-cycle IRC/IBC/IMC/IFGC/IPMC/IEBC/Swimming Pool & Spa Code from the Design Criteria PDF as the best-available (but visibly stale, per the department's own newer NEC/IPC/IECC citations) reference point for those code families pending confirmation directly with the Building Department.; 2018 International Residential Code (IRC) — per the Design Criteria Town of Lochbuie PDF (undated, 'Residential Construction' column); not restated on the live webpage, so carried at partial confidence pending direct confirmation; 2018 International Building Code (IBC), 2018 International Mechanical Code (IMC), 2018 International Fuel Gas Code (IFGC) — per the same Design Criteria PDF ('Commercial Construction' column); not restated on the live webpage, partial confidence; 2018 International Property Maintenance Code (IPMC), 2018 International Existing Building Code (IEBC), 2018 Swimming Pool & Spa Code — per the same Design Criteria PDF ('Other Adopted Codes' column); partial confidence. Local amendments apply — see the Lochbuie overview page for the full list.

Per SAFEbuilt's Photovoltaic System Submittal Requirements, the structural engineer's stamped letter must state a design basis of minimum 30 psf ground snow load, 115 mph Vult wind speed, wind exposure C, and Seismic Design Category B — for both roof-mounted and ground-mounted systems.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Lochbuie building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Lochbuie's permit history isn't searchable here yet

This page covers what the permit requires. What we don't have for Lochbuie yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.

Your email, and the place — never an address. We only use it to tell you when Lochbuie lands. Privacy.