Platteville building inspections

Verified

Inspection sequence, scheduling, and re-inspection fees for building permits in Platteville, Colorado.

Verified 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
400 Grand Avenue, Platteville, CO 80651
Phone
970-785-2245
Office hours
Town Hall main line 970-785-2245 (fax 970-785-2476). Building permit applications and plan-review submittals are emailed to kcampos@plattevillegov.org; SAFEbuilt plans examiners (coloradoplanreview@safebuilt.com for resubmittals) interpret International Codes and conduct building inspections on the Town's behalf. No separate SAFEbuilt local office address or in-person hours are published on the Town's site; all intake is via Town Hall or email.

Inspection sequence

Applies to: Residential Building Permit (New Construction)

  1. 1

    Foundation

    After trenches excavated, reinforcement steel in place, forms erected, PRIOR to placing concrete

  2. 2

    Underground Plumbing

    Prior to covering of any piping or wiring and prior to placing concrete

  3. 3

    Rough Trade (plumbing, mechanical, electrical)

    May be performed with the rough frame inspection

  4. 4

    Rough Frame

    After roof, framing, fire stopping, sheathing, draft stopping, bracing, and fasteners are in place

  5. 5

    Insulation

    After insulation placed, PRIOR to covering walls

  6. 6

    Final

    After construction is fully complete

Applies to: Residential Addition / Basement Finish Permit

  1. 1

    Foundation & Foundation Wall (additions with new footings)

    After trenches excavated, reinforcement steel in place, forms erected, PRIOR to concrete

  2. 2

    Underground Plumbing

    Prior to covering piping/wiring and prior to placing concrete

  3. 3

    Rough Trade / Rough Frame

    Plumbing, mechanical, electrical rough-in and framing, fire stopping, sheathing, bracing complete

  4. 4

    Insulation

    After insulation placed, prior to covering walls

  5. 5

    Final

    After the addition or basement finish is completed

Applies to: Accessory Structure Permit (Detached Garage, Shed, Pole Barn) & Accessory Dwelling Unit (ADU)

  1. 1

    Footings

    After trenches excavated, forms erected, PRIOR to placing concrete

  2. 2

    Slab

    Prior to placing concrete

  3. 3

    Frame/Rough (with utility inspections if installed)

    After roof, framing, bracing, fasteners in place

  4. 4

    Final

    After the structure is completed

Applies to: Deck, Patio Cover & Carport Permit

  1. 1

    Footings

    After trenches excavated, forms erected, PRIOR to placing concrete

  2. 2

    Framing

    Rim joist/ledger attachment, floor joists, beams, hangers (decks); roof, truss/ledger attachment, rafters/joists, beams and hangers, plus rough electric if applicable (patio covers/carports)

  3. 3

    Final

    After the deck or patio cover/carport is completed, including any final electrical

Applies to: Electrical Permit

  1. 1

    Rough Electrical

    Wiring and panel installed before concealment; may be combined with rough frame/trade inspection

  2. 2

    Final Inspection

    Devices installed, system energized and verified; inspector may verify electrician identity/licensure at this stage

Applies to: EV Charger / EVSE Permit

  1. 1

    Rough Electrical

    EVSE circuit wiring and panel connections before concealment; may be combined with rough frame/trade inspection

  2. 2

    Final Inspection

    Charger installed, system energized and verified; inspector may verify electrician identity/licensure at this stage

Applies to: Mechanical / HVAC Permit

  1. 1

    Rough Mechanical

    Ductwork, flues, equipment placement before concealment; may be combined with rough trade/frame inspection

  2. 2

    Final Inspection

    Equipment operational, combustion air and venting verified

Applies to: Plumbing Permit

  1. 1

    Underground / Rough Plumbing

    Prior to covering of any piping and prior to placing concrete

  2. 2

    Final Inspection

    Fixtures connected, no leaks, proper venting verified; inspector may verify plumber identity/licensure

Applies to: Re-Roof Permit

  1. 1

    Mid-Roof Inspection (if required)

    Per the guide: 'Mid-roof inspections are NOT required on residential projects' as a general rule, though the Building Department may require one for tile/metal/special roofing exceeding 7.5 psf

  2. 2

    Final Roof Inspection

    Required for all re-roof permits; permit holder must call for this inspection

Applies to: Rooftop Solar / Photovoltaic Permit

  1. 1

    Rough Electrical

    Conduit runs, wire sizing, disconnect placement before cover

  2. 2

    Final Inspection

    Racking, roof penetrations, and electrical connections verified

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Platteville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Platteville building permits

Get alerts for Platteville

We'll email you when Platteville's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.