EV Charger / EVSE Permit in Platteville, Colorado

Platteville has no EV-charger-specific permit type or fee line. An EV charger (EVSE) circuit is electrical work and follows the Town's general Electrical Permit path: filed on the combined Building Permit Application's Electrician field, with the Town performing contemporaneous verification of the installing electrician's Colorado State Electrical Board (DORA) license per CRS 12-23-116, and billed under the Electrical line item on the SAFEbuilt-administered fee block. Appendix A of the Municipal Code IS now confirmed live and publicly reachable (2026-07-23, via the Browser pane against Municode Library) and carries no EV-charger-specific or standalone electrical-only dollar line — a verified-negative that Platteville does not price EV-charger electrical work separately. Colorado's HB24-1173, which mandates EV-charger permit checklists and a 3-business-day decision timeline, only applies to municipalities with 10,000+ residents; Platteville's population (roughly 3,000) is below that threshold, so the statewide mandate does not currently bind the Town. The technical NEC edition governing EVSE circuit installation is now confirmed: 2023 NEC (Chapter 18, Article V, Sec. 18-5-10).

Verified 2026-07-23 · Source

When you need this permit

  • Electrician's name and Colorado DORA electrical/contractor license number must be listed on the permit application before issuance Contractor
  • Town verifies the listed electrician's license is active via the Colorado DORA online license lookup before processing
  • If the electrician performing/overseeing the EVSE work changes during the project, the applicant must notify the Town of the new electrician's name and license number
  • No separate EV-charger checklist or expedited track is published — Colorado's HB24-1173 model-code/3-business-day-decision mandate applies only to municipalities with 10,000+ residents, and Platteville (population roughly 3,000) is below that threshold

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

SAFEbuilt electrical permit fee (no EV-specific line item found)Listed as a distinct line item ('Electrical') on the combined Building Permit Application fee block, the same line item used for any other electrical work; no EV-charger-specific fee was found on the Building Permit Application, the SAFEBuilt Permits page, the Town's guide series, OR (confirmed 2026-07-23) Appendix A - Fee Schedule (live-checked via Municode Library) or a live full-text search of the entire current Code of Ordinances. Billed under the same general Electrical/Chapter-18-referenced fee structure as any other electrical work.
No distinct EV-charger or standalone electrical dollar figure is separately published — verified-negative, confirmed 2026-07-23

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Platteville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical

    EVSE circuit wiring and panel connections before concealment; may be combined with rough frame/trade inspection

  2. 2

    Final Inspection

    Charger installed, system energized and verified; inspector may verify electrician identity/licensure at this stage

See the full Platteville inspection guide — scheduling & re-inspection fees →

Tips

  • There is no standalone EV-charger permit in Platteville — apply using the combined Building Permit Application with the Electrician field completed, the same as any other electrical work.
  • Colorado's HB24-1173 (EV charger permit checklists, 3-business-day decisions) does not currently bind Platteville because the Town's population is below the law's 10,000-resident municipal threshold.

Frequently asked questions

Platteville requires an ev charger / evse permit for: Electrician's name and Colorado DORA electrical/contractor license number must be listed on the permit application before issuance; Town verifies the listed electrician's license is active via the Colorado DORA online license lookup before processing; If the electrician performing/overseeing the EVSE work changes during the project, the applicant must notify the Town of the new electrician's name and license number; No separate EV-charger checklist or expedited track is published — Colorado's HB24-1173 model-code/3-business-day-decision mandate applies only to municipalities with 10,000+ residents, and Platteville (population roughly 3,000) is below that threshold. If your project isn't listed, confirm with Town of Platteville — SAFEbuilt Permits (contracted building department services) at 970-785-2245 before starting work.

No. Platteville has no EV-charger-specific permit type or published fee. An EV charger circuit is permitted the same as any other electrical work — filed on the combined Building Permit Application with contemporaneous DORA license verification, billed under the general Electrical fee line item.

Platteville does not publish a plan-review timeline for this permit. Contact Town of Platteville — SAFEbuilt Permits (contracted building department services) at 970-785-2245 for current turnaround.

You'll need: Town of Platteville Building Permit Application (Electrician field). See the required-documents checklist on this page for details on each.

Platteville requires 2 inspection(s) for an ev charger / evse permit, in order: Rough Electrical, Final Inspection. Schedule each through Town of Platteville — SAFEbuilt Permits (contracted building department services) (970-785-2245).

Apply through Town of Platteville — SAFEbuilt Permits (contracted building department services) at 400 Grand Avenue, Platteville, CO 80651. Phone: 970-785-2245, email: kcampos@plattevillegov.org. Office hours: Town Hall main line 970-785-2245 (fax 970-785-2476). Building permit applications and plan-review submittals are emailed to kcampos@plattevillegov.org; SAFEbuilt plans examiners (coloradoplanreview@safebuilt.com for resubmittals) interpret International Codes and conduct building inspections on the Town's behalf. No separate SAFEbuilt local office address or in-person hours are published on the Town's site; all intake is via Town Hall or email.. Official information: https://platteville.colorado.gov/safebuilt-permits.

Platteville, Colorado has adopted: 2024 International Building Code (IBC), Chapters 1-35 — CONFIRMED 2026-07-23 directly from the Town's own codified ordinances (Sec. 18-2-10, 'Adoption', Chapter 18 — Building Regulations, Article II — Building Code): 'The International Building Code, 2024 Edition as published by the International Code Council, 4051 West Flossmoor Road, Country Club Hills, IL 60478, Chapters 1 through 35 inclusive...' Retrieved live via Municode Library (library.municode.com/co/platteville/codes/code_of_ordinances), Code of Ordinances Supplement 2, online content updated 2026-02-17, codified through Ordinance No. 2025-851 (enacted 2025-12-16) — the Dec-2025 code-adoption ordinance referenced in this corpus's Colorado research playbook.; 2024 International Residential Code (IRC), Chapters 1-43 — CONFIRMED 2026-07-23 via Sec. 18-10-10 'Adoption' (Chapter 18, Article X — Residential Code): 'The International Residential Code, 2024 Edition as published by the International Code Council... Chapters 1 through 43 inclusive...' Corroborates the SAFEbuilt guide series' consistent '2024 IRC' heading with a second, independent, directly-codified source.; 2024 International Mechanical Code (IMC), Chapters 1-15 — CONFIRMED 2026-07-23 via Sec. 18-3-10 'Adoption' (Chapter 18, Article III — Mechanical Code), live Municode text.; 2024 International Fuel Gas Code (IFGC), Chapters 1-8 — CONFIRMED 2026-07-23 via Sec. 18-9-10 'Adoption' (Chapter 18, Article IX — Fuel Gas Code), live Municode text.; 2024 International Fire Code (IFC), plus Appendix B-0 — CONFIRMED 2026-07-23 via Sec. 18-11-10 'Adoption' (Chapter 18, Article XI — Fire Code): 'chapters and appendices B-0 of the 2024 International Fire Code (the "IFC") are hereby adopted by reference as the Town of Platteville Fire Code...'; 2024 International Property Maintenance Code (IPMC), Chapters 1-8 — CONFIRMED 2026-07-23 via Sec. 18-12-10 'Adoption' (Chapter 18, Article XII — Property Maintenance Code), live Municode text.; 2024 International Existing Building Code (IEBC), Chapters 1-16 — CONFIRMED 2026-07-23 via Sec. 18-13-10 'Adoption' (Chapter 18, Article XIII — Existing Building Code); this code family was not previously identified in this file — new finding from the 2026-07-23 chase.; 2024 International Energy Conservation Code (IECC), Chapters 1-6 Commercial [+ Residential provisions] — CONFIRMED 2026-07-23 via Sec. 18-14-10 'Adoption' (Chapter 18, Article XIV — Energy Conservation Code), which ALSO adopts by reference 'Appendix CK Colorado Model Electric and Solar Ready Code-Commercial and Appendix RM Colorado Model Electric and Solar Ready Code-Residential' — this is the direct, specific HB22-1362 electric-ready/solar-ready citation that could not be located in 2026-07-06's chase (only the generic 'State of Colorado Electric Ready Code' guide reference was found then). Sec. 18-14-30 'Amendments' further amends the IECC to replace all references to 'ICC Electrical Code' with 'National Electrical Code as adopted by the State.'; National Electrical Code (NEC), 2023 Edition, exclusive of appendices — CONFIRMED 2026-07-23 via Sec. 18-5-10 'Adoption' (Chapter 18, Article V — Electrical Code): 'The National Electrical Code, 2023 Edition, exclusive of appendices, published by the National Fire Protection Association, 1 Batterymarch Park, Quincy, MA 02169, is hereby [adopted]...' This RESOLVES the gap flagged in the 2026-07-06 pass ('The NEC edition... could not be independently re-confirmed... omitted rather than guessed') — Platteville does codify its own NEC edition (2023) in Chapter 18 Article V, notwithstanding that day-to-day electrical licensing runs through DORA contemporaneous review rather than a Town trade-license program (see localAmendments).; All nine code-family adoptions above were retrieved 2026-07-23 from the Town's live, current Municode Library codification (library.municode.com/co/platteville/codes/code_of_ordinances), Supplement 2, online content updated 2026-02-17, 'Codified through Ordinance No. 2025-851, enacted December 16, 2025' — via that page's own full-text search API (localapi/search, clientId=19046, scoped to Platteville only), which returns live indexed section text. This is a second, independent, more authoritative confirmation of the 2024 cycle than the SAFEbuilt guide series alone, and definitively supersedes the stale 'Photovoltaic System Submittal Requirements' PDF (last revised 10.22.2021, citing '2020 NEC, 2018 International Codes') — that PDF's code-year language is now confirmed stale against the Town's own codified ordinances, not merely inferred against a differently-dated guide series.; Colorado is a home-rule state with no statewide-mandated building code edition; Platteville's own codified Chapter 18 adoption ordinances (as amended through Ord. No. 2025-851, Dec. 16, 2025) are the direct governing source, corroborated by the SAFEbuilt guide series.; HB22-1362 (Colorado's statewide minimum energy code floor for the July 2023-July 2026 window, requiring at least the 2021 IECC plus electric- and solar-ready / EV-ready provisions for jurisdictions issuing residential building permits) is satisfied and directly evidenced: Platteville's 2024 IECC adoption (Sec. 18-14-10) exceeds the 2021 IECC floor AND explicitly adopts by reference the Colorado Model Electric and Solar Ready Code Appendices CK (Commercial) and RM (Residential) — the specific state-mandated electric-ready/solar-ready provisions, confirmed 2026-07-23 directly from the ordinance text rather than inferred from a generic guide-page mention.. Local amendments apply — see the Platteville overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Platteville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.