Skip to main content
PermitBase

Commercial Building Permit (New Construction, Shell, Tenant Finish, Remodel/Addition) in Platteville, Colorado

Required for new commercial construction, shell buildings, tenant finish, and remodels or additions to commercial, industrial, or institutional structures in the Town of Platteville. There is no separate commercial-building-permit application or guide — commercial work is filed on the same combined Building Permit Application used for residential projects, checked under its COMMERCIAL block (Shell Only, Tenant Finish, Remodel/Addition, New Building, Electrical Valuation) rather than the RESIDENTIAL block, and reviewed by SAFEbuilt under the adopted 2024 International Building Code (Chapter 18, Article II, Sec. 18-2-10 Adoption). Before this permit can be issued, most commercial, industrial, institutional, and multi-family projects must first clear a separate, Town-administered Site Plan approval (Chapter 16, Sec. 16-5-40) — a distinct zoning/development review with its own fee and procedure, not a building-code review, and not something a single-family or two-family residential applicant has to do.

Verified 2026-08-26 · Source

When you need this permit

  • Town of Platteville Building Permit Application with the COMMERCIAL Proposed-Use block checked (Shell Only, Tenant Finish, Remodel/Addition, New Building, or Electrical Valuation, as applicable) rather than a RESIDENTIAL checkbox on the same form
  • Site Plan approval under Chapter 16, Sec. 16-5-40 obtained before this permit is issued, for any construction, remodel, or expansion other than a single-family or two-family dwelling; the Town Manager may waive this step for a remodel or expansion that adds no occupancy, density, on-site employees, or parking
  • Fair market value of all materials and labor stated on the application as the valuation basis for the permit fee
  • General Contractor, plus Electrician, Plumber, and HVAC contractor listed with license numbers where applicable; a listed electrician or plumber must hold an active Colorado DORA license, verified by the Town before the permit is processed and again if the tradesperson changes
  • Construction documents (architectural, structural, and applicable trade plans) reviewed by SAFEbuilt for compliance with the adopted 2024 IBC and the commercial provisions of the 2024 IECC (Chapter 18, Articles II and XIV)
  • A separate Fire Protection System Permit from the Platteville-Gilcrest Fire Protection District is required in addition to this permit whenever the project includes a new or modified fire alarm, fire sprinkler, or kitchen hood system
  • Construction must commence within 180 days of permit issuance or the permit is automatically void; work stoppage for 180 continuous days also voids the permit

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 3 required documents checked.

This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →

Fee schedule

Building Permit fee (valuation-based, adopted 2024 IBC fee schedule by reference)
Appendix A - Fee Schedule (Town of Platteville Code of Ordinances, Municode Library, Sec. Show full citationAppendix A - Fee Schedule (Town of Platteville Code of Ordinances, Municode Library, Sec. 16-3-10) reads: 'Building Permit | Per Chapter 18 + $50.00 to determine compliance with zoning applied to residential applications ONLY.' The $50.00 add-on is scoped to residential applications only, so a commercial building permit is billed on the same Per-Chapter-18 base fee without it.
Follows the fee schedule embedded in the adopted 2024 International Building Code, incorporated by reference; no separate Town-published valuation table exists, and a commercial permit is not subject to the $50.00 zoning-compliance surcharge that applies to residential applications
Investigation fee (work commenced without a permit)Town of Platteville Code of Ordinances, Chapter 18, Article II - Building Code, Sec. 18-2-30, Amendments, carries this fee for commercial and general building scope, matching the identical amendment at Sec. 18-10-30 for residential scope.
100% of the original building permit fee, in addition to the required permit fees
Development impact fees (nonresidential rates)
Town of Platteville Code of Ordinances, Appendix A - Fee Schedule, Development Impact Fees subsection (cross-referencing Chapter 4-9), which prices these lines by dwelling unit for residential… Show full citationTown of Platteville Code of Ordinances, Appendix A - Fee Schedule, Development Impact Fees subsection (cross-referencing Chapter 4-9), which prices these lines by dwelling unit for residential projects and by square foot for nonresidential projects; the Schools impact fee line is published only as a per-dwelling-unit residential figure, with no nonresidential per-square-foot rate listed.
Police Facilities $0.54 per sq ft; Public Facilities $1.50 per sq ft; Parks $0.00 per sq ft; Transportation $2.50 per sq ft; Storm Drainage $1.14 per sq ft; Platteville-Gilcrest Fire Protection District Impact Fee 1.65 (nonresidential rate)
Construction use tax
The Town of Platteville Building Permit Application lists 'Use Tax' as one of the blank 'TOTAL Platteville Fees' line items collected alongside the building permit; Show full citationThe Town of Platteville Building Permit Application lists 'Use Tax' as one of the blank 'TOTAL Platteville Fees' line items collected alongside the building permit; Appendix A - Fee Schedule (Municode Library) publishes no corresponding rate or formula. Confirm the current rate with Town Hall for a specific project.
Collected as part of the combined fee block, but no use-tax rate or percentage is published in Appendix A or elsewhere in the Code of Ordinances
Appeal of Building Official rulingTown of Platteville Code of Ordinances, Appendix A - Fee Schedule, Building and Construction section.
$200.00
Site Plan review fee (Chapter 16, Sec. 16-5-40 — a separate Town Planning approval, not part of this permit)
Town of Platteville Code of Ordinances, Appendix A - Fee Schedule, Planning and Development Review section, lists 'Minor or Major Site Plan | $500.00' under a Sec. Show full citationTown of Platteville Code of Ordinances, Appendix A - Fee Schedule, Planning and Development Review section, lists 'Minor or Major Site Plan | $500.00' under a Sec. 16-3-20 code-section reference that appears to be an outdated cross-reference to the substantive Sec. 16-5-40 Site Plan requirement. Paid to the Town's Planning process ahead of this permit, not to SAFEbuilt.
$500.00

Review timeline

Plan review
Not published — contact the department

How long did your Commercial Building Permit (New Construction, Shell, Tenant Finish, Remodel/Addition) permit actually take in Platteville?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Foundation

    After trenches excavated, reinforcement steel in place, forms erected, prior to placing concrete

  2. 2

    Underground Plumbing

    Prior to covering of any piping or wiring and prior to placing concrete

  3. 3

    Rough Trade (plumbing, mechanical, electrical)

    May be performed with the rough frame inspection

  4. 4

    Rough Frame

    After roof, framing, fire stopping, sheathing, draft stopping, bracing, and fasteners are in place

  5. 5

    Final

    After construction is fully complete; a separate Fire Protection System inspection applies if the project includes a fire alarm, sprinkler, or kitchen hood system

See the full Platteville inspection guide — scheduling & re-inspection fees →

Tips

  • There is no separate commercial building permit form or fee table in Platteville — check the COMMERCIAL block on the same combined Building Permit Application used for residential work, and expect the Per-Chapter-18 base fee without the $50.00 zoning-compliance surcharge that applies only to residential applications.
  • Budget separately for the $500.00 Site Plan review — Sec. 16-5-40 makes it a prerequisite for this permit on essentially any project other than a single-family or two-family dwelling. Ask the Town Manager whether a small tenant-finish remodel with no change in occupancy, density, employees, or parking qualifies for the Sec. 16-5-40(a)(2) waiver before assuming full Site Plan review is required.
  • A fire alarm, sprinkler, or kitchen hood system needs its own Fire Protection System Permit from the Platteville-Gilcrest Fire Protection District, in addition to this permit — its fees scale by project square footage and are billed separately from anything SAFEbuilt or the Town charges.
  • Nonresidential development-impact fees are billed per square foot rather than per dwelling unit, and the Parks impact fee is $0.00 per sq ft for nonresidential projects specifically.

Frequently asked questions

Platteville requires a commercial building permit (new construction, shell, tenant finish, remodel/addition) for: Town of Platteville Building Permit Application with the COMMERCIAL Proposed-Use block checked (Shell Only, Tenant Finish, Remodel/Addition, New Building, or Electrical Valuation, as applicable) rather than a RESIDENTIAL checkbox on the same form; Site Plan approval under Chapter 16, Sec. 16-5-40 obtained before this permit is issued, for any construction, remodel, or expansion other than a single-family or two-family dwelling; the Town Manager may waive this step for a remodel or expansion that adds no occupancy, density, on-site employees, or parking; Fair market value of all materials and labor stated on the application as the valuation basis for the permit fee; General Contractor, plus Electrician, Plumber, and HVAC contractor listed with license numbers where applicable; a listed electrician or plumber must hold an active Colorado DORA license, verified by the Town before the permit is processed and again if the tradesperson changes; Construction documents (architectural, structural, and applicable trade plans) reviewed by SAFEbuilt for compliance with the adopted 2024 IBC and the commercial provisions of the 2024 IECC (Chapter 18, Articles II and XIV); A separate Fire Protection System Permit from the Platteville-Gilcrest Fire Protection District is required in addition to this permit whenever the project includes a new or modified fire alarm, fire sprinkler, or kitchen hood system; Construction must commence within 180 days of permit issuance or the permit is automatically void; work stoppage for 180 continuous days also voids the permit. If your project isn't listed, confirm with Town of Platteville — SAFEbuilt Permits (contracted building department services) at 970-785-2245 before starting work.

In Platteville, the published Building Permit fee (valuation-based, adopted 2024 IBC fee schedule by reference) is: Follows the fee schedule embedded in the adopted 2024 International Building Code, incorporated by reference; no separate Town-published valuation table exists, and a commercial permit is not subject to the $50.00 zoning-compliance surcharge that applies to residential applications. Additional published fees: Investigation fee (work commenced without a permit) — 100% of the original building permit fee, in addition to the required permit fees; Development impact fees (nonresidential rates) — Police Facilities $0.54 per sq ft; Public Facilities $1.50 per sq ft; Parks $0.00 per sq ft; Transportation $2.50 per sq ft; Storm Drainage $1.14 per sq ft; Platteville-Gilcrest Fire Protection District Impact Fee 1.65 (nonresidential rate); Construction use tax — Collected as part of the combined fee block, but no use-tax rate or percentage is published in Appendix A or elsewhere in the Code of Ordinances; Appeal of Building Official ruling — $200.00; Site Plan review fee (Chapter 16, Sec. 16-5-40 — a separate Town Planning approval, not part of this permit) — $500.00. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Platteville does not publish a plan-review timeline for this permit. Contact Town of Platteville — SAFEbuilt Permits (contracted building department services) at 970-785-2245 for current turnaround.

You'll need: Town of Platteville Building Permit Application (COMMERCIAL block); Construction Plans; Approved Site Plan (or Town Manager waiver). See the required-documents checklist on this page for details on each.

Apply through Town of Platteville — SAFEbuilt Permits (contracted building department services) at 400 Grand Avenue, Platteville, CO 80651. Phone: 970-785-2245, email: kcampos@plattevillegov.org. Office hours: Town Hall main line 970-785-2245 (fax 970-785-2476). Building permit applications and plan-review submittals are emailed to kcampos@plattevillegov.org; SAFEbuilt plans examiners (coloradoplanreview@safebuilt.com for resubmittals) interpret International Codes and conduct building inspections on the Town's behalf. No separate SAFEbuilt local office address or in-person hours are published on the Town's site; all intake is via Town Hall or email.. Official information: https://platteville.colorado.gov/safebuilt-permits.

No. The Town's Building Permit Application has a COMMERCIAL Proposed-Use block (Shell Only, Tenant Finish, Remodel/Addition, New Building, Electrical Valuation) on the same form used for residential work, reviewed by SAFEbuilt under the adopted 2024 IBC (Chapter 18, Article II). It is billed on the same Per-Chapter-18 base fee as the residential permit, without the $50.00 zoning-compliance surcharge that applies only to residential applications.

Clear Site Plan approval (Chapter 16, Sec. 16-5-40) before this permit can be issued. That $500.00, Town Manager-administered review applies by default to any construction, remodel, or expansion other than a single-family or two-family dwelling, and can be waived only for a remodel or expansion that adds no occupancy, density, employees, or parking.

SAFEbuilt is the Town's contracted building-department-services provider: it reviews plans and conducts inspections for the building-code scope of a commercial project under the adopted 2024 IBC, for industrial, commercial, and residential projects alike. The Town itself separately administers Site Plan and zoning approval, its own utility and development-impact fees on the same application, and (through the Platteville-Gilcrest Fire Protection District) a standalone permit for fire alarm, sprinkler, or kitchen hood systems. A commercial applicant still files with and pays the Town, and still needs Town-level Site Plan approval before SAFEbuilt's building permit can issue.

Sources & verification

Verified against official sources. Last reviewed 2026-08-26.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Platteville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

This one’s complicated · Get an expediter

Tell us about your project and we’ll connect you with a permit expediter who works in Platteville.

PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.