Residential Building Permit (New Construction) — Platteville, Colorado · Requirements sheet
Verified 2026-08-02 · Source: https://platteville.colorado.gov/safebuilt-permits
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Residential Building Permit (New Construction) in Platteville, Colorado
Required for new single-family home construction in the Town of Platteville. Reviewed under the 2024 IRC as adopted; plan review and inspections are performed by SAFEbuilt on the Town's behalf, while the Town separately assesses its own utility and impact fees on the same combined application.
Verified 2026-08-02 · Source
When you need this permit
- Completed Town of Platteville Building Permit Application, listing General Contractor plus Electrician, Plumber, and HVAC contractors and their license numbers where applicable
- Electrician and plumber (if listed) must hold active Colorado DORA electrical/plumbing and contractor licenses, contemporaneously verified by the Town per CRS 12-23-116 (electrical) and CRS 12-155-120(1)/HB19-1086 (plumbing) Contractor
- Site plan / survey showing setbacks, easements, and utility locations; a registered land surveyor's survey is required if the property is in a protected area
- Fair market value of all materials and labor must be stated on the application (valuation basis for fee calculation)
- Septic-served properties require Weld County health department approval prior to permit issuance
- Construction must commence within 180 days of permit issuance (six months, per SAFEbuilt guides) or the permit is automatically void; work stoppage for 180 continuous days also voids the permit
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Appendix A - Fee Schedule (Municode Library, Code of Ordinances Supp. Show full citationHide
Appendix A - Fee Schedule (Municode Library, Code of Ordinances Supp. 2, updated 2026-02-17) provides: 'Sec. 16-3-10 | Building Permit | Per Chapter 18 + $50.00 to determine compliance with zoning applied to residential applications ONLY.' No separate town-specific valuation table is published anywhere in the current Code of Ordinances (a full-text search for 'Table 1-A fee valuation' returns no hits); the base fee is calculated per the adopted 2024 IBC's own fee schedule, incorporated by reference through Chapter 18 rather than independently republished. This same 'Per Chapter 18' base fee line also governs commercial and tenant-finish (TI) building permits — Platteville has no distinct commercial-building-permit or tenant-improvement-permit fee, application, or guide; commercial/TI projects use this identical Building Permit Application and fee line, simply without the residential-only $50.00 zoning-compliance add-on. See the full sourced finding in this jurisdiction's top-level localAmendments and tipsAndGotchas. Note that this covers the building-PERMIT fee specifically: commercial/non-residential projects also separately face a genuinely distinct $500.00 Site Plan review (Chapter 16, Sec. 16-5-40) that residential (single/two-family) projects are explicitly exempt from — see the commercial-nonresidential-site-plan-review permitType entry.CONFIRMED 2026-07-23, live-quoted from Sec. Show full citationHide
CONFIRMED 2026-07-23, live-quoted from Sec. 18-10-30 'Amendments' (Chapter 18, Article X — Residential Code): 'necessary permits shall be subject to a fee established by the Town. The fee shall be equal to 100% of the original building fee in addition to the required permit fees.' Sec. 18-2-30 (Article II — Building Code) carries the same amendment for commercial/general building scope.CONFIRMED 2026-07-23, live-quoted verbatim from Appendix A - Fee Schedule, 'Development Impact Fees' subsection (cross-referencing Chapter 4-9): 'Collected by Town of Platteville with payment of… Show full citationHide
CONFIRMED 2026-07-23, live-quoted verbatim from Appendix A - Fee Schedule, 'Development Impact Fees' subsection (cross-referencing Chapter 4-9): 'Collected by Town of Platteville with payment of building permit, but forwarded in full to Weld County School District RE-1 & PGFPD' for the Schools line. These are the 'TOTAL Platteville Fees' side of the combined Building Permit Application's fee block (separate from the SAFEbuilt-administered code-review fee stream above); water/sewer tap, meter, and system-investment charges (also part of 'TOTAL Platteville Fees') are separately confirmed as Utilities-section line items in Appendix A but are use-driven (meter size, EQR) rather than flat per-permit fees and are not restated here.Review timeline
Inspection process
- 1
Foundation
After trenches excavated, reinforcement steel in place, forms erected, PRIOR to placing concrete
- 2
Underground Plumbing
Prior to covering of any piping or wiring and prior to placing concrete
- 3
Rough Trade (plumbing, mechanical, electrical)
May be performed with the rough frame inspection
- 4
Rough Frame
After roof, framing, fire stopping, sheathing, draft stopping, bracing, and fasteners are in place
- 5
Insulation
After insulation placed, PRIOR to covering walls
- 6
Final
After construction is fully complete
See the full Platteville inspection guide — scheduling & re-inspection fees →
Tips
- Platteville's building permits are reviewed and inspected by SAFEbuilt on the Town's behalf, but utility/impact fees are separately assessed and collected by the Town on the same application — expect two distinct fee totals ('TOTAL SAFEbuilt Fees' and 'TOTAL Platteville Fees') rather than one combined line.
- List your electrician and plumber (with Colorado DORA license numbers) on the application before submittal if known — Platteville will not process the permit until an active license is verified for each, and a changed tradesperson mid-project must be reported and re-verified.
- Budget a flat $50.00 zoning-compliance surcharge on top of the base valuation-based building permit fee for residential applications (Appendix A, Sec. 16-3-10); the base fee itself follows the adopted 2024 IBC's own fee schedule rather than a Town-published dollar table, so get a project-specific quote from Town Hall (970-785-2245) or kcampos@plattevillegov.org before budgeting.
- Development-impact fees (police, public facilities, parks, transportation, storm drainage, schools, PGFPD) are billed per dwelling unit or per square foot on top of the building permit fee — see Appendix A's 'Development Impact Fees' table for the current per-unit/per-sq-ft rates.
- Platteville has no separate commercial-building-permit or tenant-improvement (TI) permit — the Town's own Building Permit Application PDF has a 'COMMERCIAL' Proposed-Use checkbox block (Shell Only, Tenant Finish, Remodel/Addition, New Building, Electrical Valuation) on this SAME combined form. A commercial or tenant-finish project follows the identical SAFEbuilt/Chapter-18 review and 'Per Chapter 18' base fee as this residential entry, just without the $50.00 residential-only zoning-compliance add-on. See the top-level localAmendments for the full sourced finding.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-02.
Fee schedules
Applications & forms
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Platteville building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Platteville's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for Platteville yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when Platteville lands. Privacy.
Other permits in Platteville
Residential Building Permit (New Construction) in other cities
Compare residential building permit (new construction) fees across Colorado →
Look up this fee in a different city →
Related guides
Now live
Build your Platteville project checklist
Describe your project once and get every permit, document, and fee it triggers in Platteville — in one checklist. Free, for any city and any number of projects.
Get started →