Electric Vehicle (EV) Charger / EVSE Permit in Idaho City, Idaho

Idaho City does not issue electrical permits at all — electrical work, including EV charger/EVSE circuit installation, is issued and inspected by the State of Idaho Division of Occupational and Professional Licenses (DOPL, Bureau of Building and Construction Safety), the same statewide arrangement covering all electrical, plumbing, and mechanical/HVAC trade work in the city. No dedicated EV charger/EVSE fee category exists in IDAPA 24.39.10 (Rules of the Idaho Electrical Board) — an EV charger circuit added to an existing residence is billed under the flat $65 Existing Residential Dwelling Unit Permit fee, while a commercial or multi-family installation is billed under the Other Installation (Including Industrial and Commercial) Permit's wiring-cost-tiered schedule, both confirmed directly against DOPL's own published electrical board rules.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit for the EV charger circuit is obtained through Idaho DOPL, not the City of Idaho City — the City's own building permit only covers structural/mounting work, if any (e.g., a dedicated EV charger pedestal or canopy)
  • If a structural element (post-mount pedestal, canopy, or similar) is installed, a City of Idaho City building permit is required for that portion, per the City's general Building Permit Application
  • If the property is within the Idaho City Historic District, a Certificate of Appropriateness from the Historic Preservation Commission is required BEFORE any exterior structural element (e.g., a visible charger pedestal) can be permitted
  • Contact Idaho DOPL directly at (208) 334-3233 or dopl.idaho.gov for the electrical permit and current valuation-based fee

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Existing Residential Dwelling Unit Permit (DOPL) — applies to an EV charger circuit added to an existing homeIDAPA 24.39.10, Rules of the Idaho Electrical Board, Section 050.02 (Residential Permits, Existing Residential Dwelling Unit). No distinct EV charger/EVSE fee line is published by DOPL; a Level 2/EVSE circuit added to an existing residence falls under this flat existing-dwelling-unit fee rather than the new-construction, square-footage-tiered schedule. Confirmed 2026-07-20 directly against DOPL's own published Idaho Electrical Board rules text.
$65 per inspection
Other Installation (Including Industrial and Commercial) Permit (DOPL) — applies to commercial/multi-family EV charging installationsIDAPA 24.39.10, Rules of the Idaho Electrical Board, Section 050.06 (Other Installation, Including Industrial and Commercial, Permit). Applies to a commercial or multi-family EV charging station installation rather than the residential dwelling-unit fee. Confirmed 2026-07-20 directly against DOPL's own published Idaho Electrical Board rules text.
Wiring cost not exceeding $10,000: $60 plus 2% of wiring cost. $10,001-$100,000: $260 plus 1% of the amount over $10,000. Over $100,000: $1,160 plus 0.5% of the amount over $100,000.
Building Permit — total valuation $1.00 to $500.00 (City, structural/mounting portion only, if applicable)Only applies if a structural element (pedestal, canopy) requires a separate City building permit; City of Idaho City Building Permit Fee Schedule
$23.50

Review timeline

Plan review
Not published — contact the department

How long did your Electric Vehicle (EV) Charger / EVSE Permit permit actually take in Idaho City?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough Electrical (DOPL)

    Circuit, conduit, and disconnect placement before concealment, if applicable — inspected by the state-assigned DOPL electrical inspector for Boise County/Idaho City

  2. 2

    Final Electrical (DOPL)

    Charger mounted, circuit labeled, and installation verified per the National Electrical Code as adopted statewide by DOPL

See the full Idaho City inspection guide — scheduling & re-inspection fees →

Tips

  • Idaho City itself does not issue electrical permits of any kind, including for EV chargers — you must go through the State of Idaho DOPL (Bureau of Building and Construction Safety) directly, the same as for any other electrical work in the city.
  • If your installation is a simple wall-mounted charger on an existing structure with no new structural element, only the DOPL electrical permit applies; a separate City building permit is only needed if you are adding a structural element like a pedestal or canopy.
  • If your property is within the Idaho City Historic District and the installation includes any visible exterior structural element, secure your Certificate of Appropriateness from the Historic Preservation Commission BEFORE applying for a City building permit for that portion.

Frequently asked questions

Idaho City requires an electric vehicle (ev) charger / evse permit for: Electrical permit for the EV charger circuit is obtained through Idaho DOPL, not the City of Idaho City — the City's own building permit only covers structural/mounting work, if any (e.g., a dedicated EV charger pedestal or canopy); If a structural element (post-mount pedestal, canopy, or similar) is installed, a City of Idaho City building permit is required for that portion, per the City's general Building Permit Application; If the property is within the Idaho City Historic District, a Certificate of Appropriateness from the Historic Preservation Commission is required BEFORE any exterior structural element (e.g., a visible charger pedestal) can be permitted; Contact Idaho DOPL directly at (208) 334-3233 or dopl.idaho.gov for the electrical permit and current valuation-based fee. If your project isn't listed, confirm with City of Idaho City — Building Permits and Inspections Department at (208) 392-4584 before starting work.

In Idaho City, the published Existing Residential Dwelling Unit Permit (DOPL) — applies to an EV charger circuit added to an existing home is: $65 per inspection. Additional published fees: Other Installation (Including Industrial and Commercial) Permit (DOPL) — applies to commercial/multi-family EV charging installations — Wiring cost not exceeding $10,000: $60 plus 2% of wiring cost. $10,001-$100,000: $260 plus 1% of the amount over $10,000. Over $100,000: $1,160 plus 0.5% of the amount over $100,000.; Building Permit — total valuation $1.00 to $500.00 (City, structural/mounting portion only, if applicable) — $23.50. These are the jurisdiction's own published figures — see the fee schedule table and source citations on this page.

Idaho City does not publish a plan-review timeline for this permit. Contact City of Idaho City — Building Permits and Inspections Department at (208) 392-4584 for current turnaround.

You'll need: Contractor Electrical Permit Application (Idaho DOPL). Depending on your project, Idaho City may also ask for: Building Permit Application (2025-26). See the required-documents checklist on this page for details on each.

Idaho City requires 2 inspection(s) for an electric vehicle (ev) charger / evse permit, in order: Rough Electrical (DOPL), Final Electrical (DOPL). Schedule each through City of Idaho City — Building Permits and Inspections Department ((208) 392-4584).

Apply through City of Idaho City — Building Permits and Inspections Department at 511 Main St., PO Box 130, Idaho City, ID 83631. Phone: (208) 392-4584, email: idahocityclerk@cityofic.org. Office hours: Mon–Thu 8:00 AM – 4:30 PM (closed 12:00–1:00 PM); Fri by appointment. Official information: https://idahocity.municipalimpact.com/building-permits-and-inspections.

Idaho City, Idaho has adopted: 2015 International Building Code (IBC), including rules for ADA and Federal Fair Housing Act accessibility equivalency, as adopted per Idaho City Code 8-1-2 and Idaho Code section 39-4116(1); 2017 Idaho Residential Code (IRC), Parts I-IV and IX; 2017 Idaho Energy Conservation Code (IECC); Per Idaho City Code 8-1-2, adopted codes are automatically superseded by successive versions as approved by the Idaho Building Code Board — confirm current statewide-mandated edition with the City or the Idaho Building Code Board before relying on a specific year; Idaho City Code Title 8 — Building Regulations. Local amendments apply — see the Idaho City overview page for the full list.

No. Idaho City does not issue electrical permits of any kind. EV charger/EVSE electrical work is permitted and inspected by the State of Idaho DOPL (Division of Occupational and Professional Licenses), the same statewide arrangement that covers all electrical, plumbing, and mechanical/HVAC trade work in the city. A City building permit is only needed if the installation includes a structural/mounting element.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Idaho City building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare electric vehicle (ev) charger / evse permit fees across Idaho

Look up this fee in a different city →

Embed this data card →

Related guides

Now live

Build your Idaho City project checklist

Describe your project once and get every permit, document, and fee it triggers in Idaho City — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →