Inspection sequence, scheduling, and re-inspection fees for building permits in Greenleaf, Idaho.

Verified 2026-07-13 · Source

How to schedule

Inspections are requested through the building department below.

Address
20523 N. Whittier Dr., Greenleaf, ID 83626-9199
Phone
(208) 454-0552
Office hours
Not published; contact Greenleaf City Hall to reach the City Clerk or to schedule with the Building Official

Published scheduling rules

  • The applicant contacts the City Building Official directly to request/schedule inspections — the city clerk does not schedule inspections. (Residential Building Permit (New Construction / Addition / Alteration))

Inspection sequence

Applies to: Commercial Building Permit (New Construction / Exterior Remodel)

  1. 1

    Foundation

    Foundations inspection, per the city's Building Permit Information memo (30 Jun 2025) -- generic language covering any building permit, not use-specific

  2. 2

    Framing

    Framing inspection, per the city's Building Permit Information memo

  3. 3

    Final

    Final inspection before occupancy; all other fees (additional review/inspection/Building Official time) must be paid before a Certificate of Occupancy is issued

Applies to: Residential Building Permit (New Construction / Addition / Alteration)

  1. 1

    Foundation

    Foundations inspection, per the city's Building Permit Information memo (30 Jun 2025)

  2. 2

    Framing

    Framing inspection, per the city's Building Permit Information memo

  3. 3

    Final

    Final inspection before occupancy; all other fees (additional review/inspection/Building Official time) must be paid before a Certificate of Occupancy is issued

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection

  2. 2

    City Final Inspection (Building)

    Racking/roof-penetration attachment and structural compliance verified by the contracted Building Official

Re-inspection fees

Residential Building Permit (New Construction / Addition / Alteration)Additional Inspection Fee (re-inspections) · City of Greenleaf Consolidated Fee Schedule, Resolution #223 'Exhibit A', 'Building Permit Fees' — 'Other Inspections, Reviews and Fees' listing, p. 17 of 24
$100.00
Commercial Building Permit (New Construction / Exterior Remodel)Additional Inspection Fee (re-inspections) · City of Greenleaf Consolidated Fee Schedule, Resolution #223 'Exhibit A', 'Building Permit Fees' — 'Other Inspections, Reviews and Fees' listing, p. 17 of 24
$100.00

Sources & verification

Verified against official sources. Last reviewed 2026-07-13.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greenleaf building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Greenleaf building permits

Get alerts for Greenleaf

We'll email you when Greenleaf's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.