Solar Photovoltaic (PV) Permit — Greenleaf, Idaho · Requirements sheet
Verified 2026-07-20 · Source: https://dopl.idaho.gov/wp-content/uploads/2023/11/ELE-Contractor-Electrical-Permit-Application.pdf
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar Photovoltaic (PV) Permit in Greenleaf, Idaho
Required for installation of rooftop or ground-mount solar photovoltaic systems within Greenleaf city limits. Requires a City Building Permit (structural/racking, valuation-based using the ICC Building Valuation Data plus the City's Permit Fee Multiplier formula) plus a State of Idaho electrical permit (wiring/interconnection) issued by the Division of Occupational and Professional Licenses (DOPL) -- Greenleaf has no electrical-permit program of its own. The state's Contractor Electrical Permit Worksheet has a dedicated checkbox and valuation-based fee formula for 'Solar, Renewable Energy, power generation, power production, or energy storage systems.'
Verified 2026-07-20 · Source
When you need this permit
- City Building Permit Application submitted to the City's contracted Building Official (Idaho Building Inspection Services, Inc.) for the structural/racking scope
- Building valuation set by the Building Official using the most current ICC Building Valuation Data as a guide, run through the City's Permit Fee Multiplier formula, per City of Greenleaf Consolidated Fee Schedule (Resolution #223)
- Electrical wiring/interconnection scope requires a State of Idaho DOPL Contractor Electrical Permit (or Homeowner Electrical Permit if self-installed) -- not a City permit, since Greenleaf has no electrical-permit program of its own
- On the DOPL Electrical Permit Worksheet, check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box under 'Other Installations including Commercial/Industrial/Solar/Renewable Energy' and enter the total cost of the electrical system
- Renewable energy installations require a plan check prior to final inspection, per the DOPL Electrical Permit Worksheet
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 2 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
State Electrical Inspection
Performed by an Idaho DOPL inspector; wiring, disconnect placement, and interconnection point verified before energizing; renewable energy installations require a plan check prior to this final inspection
- 2
City Final Inspection (Building)
Racking/roof-penetration attachment and structural compliance verified by the contracted Building Official
See the full Greenleaf inspection guide — scheduling & re-inspection fees →
Tips
- Greenleaf splits solar permitting across two agencies: the City issues the structural Building Permit, but the State of Idaho (DOPL, dbs.idaho.gov) issues the electrical permit, since Greenleaf has no electrical permitting program of its own.
- Greenleaf's building-permit fee is calculated with a formula (ICC valuation data run through a City-specific Permit Fee Multiplier), not a flat published dollar table -- ask the Building Official for a written estimate before budgeting.
- On the state electrical permit worksheet, be sure to check the dedicated 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box -- this routes the project to the correct valuation-based fee formula.
- Renewable energy installations require a plan check prior to final inspection under the state's own worksheet -- budget extra lead time for this step.
- Re-chase pass (2026-07-20): downloaded and read the current State of Idaho DOPL Application for Contractor Permit / Electrical Permit Worksheet (Fee Schedule) PDF directly from dopl.idaho.gov — live today, and its 'OTHER INSTALLATIONS including COMMERCIAL/INDUSTRIAL/SOLAR/RENEWABLE ENERGY' section matches this entry's tiered formula verbatim: (system cost x 0.02) + $60 up to $10,000; ((system cost - $10,000) x 0.01) + $260 for $10,001-$100,000; ((system cost - $100,000) x 0.005) + $1,160 over $100,001. This DOPL fee schedule is the explicit, statewide, currently-in-force state mechanism for the PV/renewable-energy electrical scope in any Idaho city (including this one) that has not independently certified its own electrical inspection program.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-20.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greenleaf building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Greenleaf
Solar Photovoltaic (PV) Permit in other cities
Compare solar photovoltaic (pv) permit fees across Idaho →
Look up this fee in a different city →