Installing a Level 2 (240V) EV charger circuit at an existing residence in Greenleaf is electrical work, and since Greenleaf has no electrical-permit program of its own, it requires a State of Idaho DOPL Contractor (or Homeowner) Electrical Permit -- the same statewide authority that issues the electrical permit for solar installations. Idaho's DOPL Electrical Permit Worksheet (Fee Schedule, Rev. 8/17/2022) has no dedicated 'EV charger,' 'EVSE,' or 'electric vehicle' checkbox -- confirmed by direct text search of the current worksheet PDF, which does have a dedicated checkbox for 'Solar, Renewable Energy, power generation, power production, or energy storage systems' but none for EV charging. A standalone EV charger circuit added to an existing home is instead billed under the worksheet's general 'Existing Residence' branch-circuit line item, not the Other-Installations/Renewable-Energy valuation formula used for solar. No City of Greenleaf Building Permit is needed for a simple wall/pedestal charger with no new structure -- unlike solar, which needs a City structural/racking permit for the panel mounting.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical work must be permitted through the State of Idaho DOPL, not the City of Greenleaf -- the City issues only structural/building permits, and an EV charger circuit with no new structure does not require a City Building Permit at all
  • On the DOPL Electrical Permit Worksheet, a new dedicated EV charger circuit added to an existing single-family residence falls under the 'Existing Residence -- Modular, Manufactured or Mobile Homes -- Detached Shop' line item: a $65 base fee plus $10 per additional branch circuit beyond the one included in the base fee
  • There is no Solar/Renewable-Energy-style checkbox or valuation-based formula for EV chargers on the state worksheet -- do not check that box for a standalone EV charger installation, since EVSE is treated as ordinary branch-circuit wiring, not power generation/storage
  • As of January 1, 2023, all DOPL permits must be purchased online at dbs.idaho.gov rather than by mailed paper application
  • A City of Greenleaf Building Permit IS required in addition only if the EV charger installation includes new structural work (e.g., a new carport or accessory structure to house it) -- routed through the City's contracted Building Official (Idaho Building Inspection Services, Inc.) using the same ICC-valuation/Permit-Fee-Multiplier formula documented in this corpus's residential-building-permit and solar-pv-permit entries for Greenleaf

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Existing Residence -- new branch circuit (e.g., a single new EV charger circuit)Idaho DOPL Contractor Electrical Permit Worksheet (Fee Schedule), Rev. 8/17/2022, 'Existing Residence — Modular, Manufactured or Mobile Homes — Detached Shop' line -- no distinct 'EV charger'/'EVSE' line item exists on the statewide worksheet, confirmed by direct text search of the current PDF. A single new EV charger circuit at an existing home would be $65 + $10 = $75.
$65 base fee + $10 per additional branch circuit (one circuit included in the $65 base)
Requested Inspection (Findings or Inspector Consultation)Idaho DOPL Contractor Electrical Permit Worksheet, Rev. 8/17/2022
$65.00 per hour
City Building Permit Application Fee (only if new structural work, e.g. carport, is built to house the charger)City of Greenleaf Consolidated Fee Schedule, Resolution #223 'Exhibit A', effective 10/01/2025 -- applies only if new structural work is involved; a standalone wall/pedestal charger with no new structure does not require this
$50.00 flat, due upon submission (credited against the total building permit fee)

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / Electric Vehicle Charging Station Permit permit actually take in Greenleaf?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    State Electrical Inspection

    Performed by an Idaho DOPL inspector; new circuit, breaker sizing, and disconnect (if required) verified before the charger is energized

See the full Greenleaf inspection guide — scheduling & re-inspection fees →

Tips

  • Do not check the 'Solar, Renewable Energy, power generation, power production, or energy storage systems' box on the DOPL worksheet for a standalone EV charger -- that box routes the job to a different valuation-based fee formula meant for generation/storage systems, not simple branch-circuit wiring.
  • A single new EV charger circuit added to an existing Greenleaf home is one of the cheapest state electrical permits available -- $75 total ($65 base + $10 for the one additional circuit) versus the percentage-of-cost formula used for solar.
  • No City of Greenleaf Building Permit is needed for a wall-mounted or pedestal EV charger with no new structure -- only pull a City permit as well if you're also constructing a new carport or similar structure to house it, mirroring the same rule already documented for solar racking.
  • As of January 1, 2023, DOPL permits must be purchased online at dbs.idaho.gov rather than mailed in.

Frequently asked questions

Greenleaf requires an ev charger / electric vehicle charging station permit for: Electrical work must be permitted through the State of Idaho DOPL, not the City of Greenleaf -- the City issues only structural/building permits, and an EV charger circuit with no new structure does not require a City Building Permit at all; On the DOPL Electrical Permit Worksheet, a new dedicated EV charger circuit added to an existing single-family residence falls under the 'Existing Residence -- Modular, Manufactured or Mobile Homes -- Detached Shop' line item: a $65 base fee plus $10 per additional branch circuit beyond the one included in the base fee; There is no Solar/Renewable-Energy-style checkbox or valuation-based formula for EV chargers on the state worksheet -- do not check that box for a standalone EV charger installation, since EVSE is treated as ordinary branch-circuit wiring, not power generation/storage; As of January 1, 2023, all DOPL permits must be purchased online at dbs.idaho.gov rather than by mailed paper application; A City of Greenleaf Building Permit IS required in addition only if the EV charger installation includes new structural work (e.g., a new carport or accessory structure to house it) -- routed through the City's contracted Building Official (Idaho Building Inspection Services, Inc.) using the same ICC-valuation/Permit-Fee-Multiplier formula documented in this corpus's residential-building-permit and solar-pv-permit entries for Greenleaf. If your project isn't listed, confirm with City of Greenleaf Building Department (contracted Building Official — Idaho Building Inspection Services, Inc.) at (208) 454-0552 before starting work.

$75 total for a single new circuit added to an existing home ($65 base fee plus $10 for the one additional branch circuit), per the Idaho DOPL Contractor Electrical Permit Worksheet (Rev. 8/17/2022) -- distinct from and much cheaper than the percentage-of-system-cost formula used for solar/renewable energy installations.

Greenleaf does not publish a plan-review timeline for this permit. Contact City of Greenleaf Building Department (contracted Building Official — Idaho Building Inspection Services, Inc.) at (208) 454-0552 for current turnaround.

You'll need: Idaho DOPL Contractor (or Homeowner) Electrical Permit Application. See the required-documents checklist on this page for details on each.

Greenleaf requires 1 inspection(s) for an ev charger / electric vehicle charging station permit, in order: State Electrical Inspection. Schedule each through City of Greenleaf Building Department (contracted Building Official — Idaho Building Inspection Services, Inc.) ((208) 454-0552).

Apply through City of Greenleaf Building Department (contracted Building Official — Idaho Building Inspection Services, Inc.) at 20523 N. Whittier Dr., Greenleaf, ID 83626-9199. Phone: (208) 454-0552, email: cityhall@greenleaf-idaho.us. Office hours: Not published; contact Greenleaf City Hall to reach the City Clerk or to schedule with the Building Official. Official information: https://mobile.greenleaf-idaho.us/city-government.

Greenleaf, Idaho has adopted: 2018 International Building Code (IBC), as adopted/amended by the State of Idaho or Idaho Building Code Board — Greenleaf City Code 8-1-1(A); 2018 International Residential Code (IRC), as adopted/amended by the State of Idaho or Idaho Building Code Board — Greenleaf City Code 8-1-1(B); 2009 International Energy Conservation Code (IECC), as amended by the Idaho Building Code Board — Greenleaf City Code 8-1-1(C); International Fire Code, adopted by the City of Greenleaf with local amendments — Greenleaf City Code 8-1A; Note: Greenleaf City Code 8-1-1 provides that adopted codes are deemed superseded by successive state-adopted versions in their entirety, effective January 1 of the year following state adoption — so the state's currently-in-force IBC/IRC/IECC edition governs even though the codified text still names the 2018/2009 editions. Local amendments apply — see the Greenleaf overview page for the full list.

No. Neither the State of Idaho DOPL nor the City of Greenleaf has a dedicated EV-charger or EVSE permit type or fee line. A home Level 2 charger circuit is permitted as ordinary electrical wiring under the state's standard Electrical Permit Worksheet 'Existing Residence' branch-circuit line item -- Greenleaf itself has no electrical permitting program, so this is state-issued, not city-issued.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Greenleaf building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Compare ev charger / electric vehicle charging station permit fees across Idaho

Look up this fee in a different city →

Embed this data card →

Related guides

Now live

Build your Greenleaf project checklist

Describe your project once and get every permit, document, and fee it triggers in Greenleaf — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.

Get started →