EV Charger / EVSE Permit in Post Falls, Idaho

The City of Post Falls has no EV-charger-specific permit type or fee line — confirmed by direct review of the City's Fee Schedule (rev 10-1-2025), which contains no EV charger, electric vehicle, or EVSE line item anywhere. An EV charger circuit is filed as ordinary residential electrical work, governed by the 2023 NEC as adopted by the City, and billed under the 'Existing Residence/Modular, Manufactured, or Mobile Home/Detached Shop/Garage' fee category — the same flat fee (one circuit included, plus per-additional-circuit charge) used for any other existing-home electrical addition.

Verified 2026-07-20 · Source

When you need this permit

  • Electrical permit required for the EV charger circuit installation, filed as ordinary residential electrical work
  • Governed by the 2023 NEC as adopted by the City of Post Falls
  • Apply through the Community Development Portal; may be submitted alongside or after a Building Permit application if applicable

Required documents

Check off what you have — your progress is saved on this device.

Not ready yet0 of 1 required documents checked.

This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29

Fee schedule

Existing Residence/Modular, Manufactured, or Mobile Home/Detached Shop/Garage (applies to a new dedicated EV charger circuit; no EV-specific line item found)City of Post Falls Fee Schedule, rev 10-1-2025. Confirmed by direct review of the published fee schedule PDF: no EV charger, electric vehicle, or EVSE line item exists — an EV charger circuit is billed under this general existing-home electrical category.
$65.00 fee (one circuit included) plus $10.00 per additional branch circuit
Temporary Service (if applicable during installation)City of Post Falls Fee Schedule, rev 10-1-2025
$100.00

Review timeline

Plan review
Not published — contact the department

How long did your EV Charger / EVSE Permit permit actually take in Post Falls?

Anonymous — one question, no email. Answers are combined and only shown once at least 5 people have reported.

Inspection process

  1. 1

    Rough-In

    EVSE circuit wiring, box placement, and service connections before walls are closed

  2. 2

    Final

    Charger installed, panel labeled, protections verified per the 2023 NEC

See the full Post Falls inspection guide — scheduling & re-inspection fees →

Tips

  • There is no dedicated EV-charger permit fee line in Post Falls — a new EVSE circuit at an existing home is billed as ordinary 'Existing Residence' electrical work: $65.00 (one circuit included) plus $10.00 per additional branch circuit.
  • Failure to obtain a permit before starting work results in a fee equal to double the standard permit fee, per the City's Fee Schedule.

Frequently asked questions

Post Falls requires an ev charger / evse permit for: Electrical permit required for the EV charger circuit installation, filed as ordinary residential electrical work; Governed by the 2023 NEC as adopted by the City of Post Falls; Apply through the Community Development Portal; may be submitted alongside or after a Building Permit application if applicable. If your project isn't listed, confirm with City of Post Falls Community Development Department, Building Division at (208) 773-8708 before starting work.

No. The City of Post Falls Fee Schedule has no EV-charger, electric-vehicle, or EVSE line item. An EV charger circuit is permitted as ordinary residential electrical work under the 'Existing Residence/Modular, Manufactured, or Mobile Home/Detached Shop/Garage' category — $65.00 (one circuit included) plus $10.00 per additional branch circuit.

Post Falls does not publish a plan-review timeline for this permit. Contact City of Post Falls Community Development Department, Building Division at (208) 773-8708 for current turnaround.

You'll need: Electrical Permit Application. See the required-documents checklist on this page for details on each.

Post Falls requires 2 inspection(s) for an ev charger / evse permit, in order: Rough-In, Final. Schedule each through City of Post Falls Community Development Department, Building Division ((208) 773-8708).

Apply through City of Post Falls Community Development Department, Building Division at 1st Floor of City Hall, 408 N Spokane St, Post Falls, ID 83854. Phone: (208) 773-8708, email: permits@postfalls.gov. Office hours: 8:00 a.m. to 5:00 p.m., Monday through Friday. Dedicated Building Inspections line: (208) 457-3334 — leave permit number, job address, inspection type, and desired inspection date; requests left after midnight the night before cannot be scheduled for the following day.. Official information: https://www.postfalls.gov/175/Building.

Post Falls, Idaho has adopted: Idaho has a mandatory statewide building code administered by the Idaho Division of Building Safety (DBS, now organizationally under the Division of Occupational and Professional Licenses / DOPL) under the Idaho Building Code Act, Idaho Code Title 39, Chapter 41, negotiated and adopted through the Idaho Building Code Board. Local jurisdictions that adopt and locally administer the code must enforce it at least as strictly as the state minimum; Post Falls administers its own Building Division for building, electrical, plumbing, and mechanical permitting within city limits. Source: City of Post Falls Current Adopted Codes and Design Criteria (Community Development Department, rev 02/16/25), https://www.postfalls.gov/DocumentCenter/View/750/Current-Codes-and-Design-Criteria-PDF; 2018 IBC (International Building Code), as adopted by the State of Idaho Building Code Board and locally administered by the City of Post Falls. Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2018 IRC (International Residential Code), as adopted by the State of Idaho Building Code Board and locally administered by the City of Post Falls. Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2018 IEBC (International Existing Building Code). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2018 IECC with 2012 Amendments for Residential (International Energy Conservation Code). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2018 IMC (International Mechanical Code). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2017 ISPC (Idaho State Plumbing Code) — Idaho's own state-amended plumbing code, not the Uniform or International Plumbing Code. Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2018 IFGC (International Fuel Gas Code). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2023 NEC (National Electrical Code). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); ICC A117.1-2009 (Accessibility). Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); 2009 IPMC (International Property Maintenance Code), with amendments. Source: City of Post Falls Current Adopted Codes and Design Criteria (rev 02/16/25); The City of Post Falls Building Division directly issues and inspects electrical and plumbing permits within city limits (the Division's own permit-fee schedule lists dedicated Electrical Permits and Plumbing Permits fee tables administered by the City); this reflects local administration rather than direct-state DOPL/Division of Building Safety issuance for in-city work. Source: City of Post Falls Fee Schedule (Community Development Department, rev 10-1-2025), https://www.postfalls.gov/DocumentCenter/View/815/Fee-Schedule-PDF. Local amendments apply — see the Post Falls overview page for the full list.

Sources & verification

Verified against official sources. Last reviewed 2026-07-20.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Post Falls building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.