Inspection sequence, scheduling, and re-inspection fees for building permits in Kellogg, Idaho.

Reviewed 2026-07-23 · Source

How to schedule

Inspections are requested through the building department below.

Address
1007 McKinley Ave, Kellogg, ID 83837
Phone
(208) 786-9131
Office hours
Mon–Fri 8:00 AM – 4:00 PM

Published scheduling rules

  • Call the Building Official's cell, (208) 661-0494, at least 24 hours ahead to schedule the mandatory pre-reroof inspection. (Re-Roof Permit)
  • A pre-reroof inspection is required prior to application of new material — call (208) 661-0494 at least 24 hours in advance to schedule (Re-Roof Permit)

Inspection sequence

Applies to: Electric Vehicle (EV) Charger / EVSE Permit

  1. 1

    Rough-In (DOPL)

    Circuit, conduit, and disconnect placement before concealment, if applicable — inspected by Idaho DOPL

  2. 2

    Final (DOPL)

    Charger mounted, circuit labeled, and installation verified per the National Electrical Code as administered by DOPL

Applies to: Re-Roof Permit

  1. 1

    Pre-Reroof Inspection

    Required before new roofing material is applied; call (208) 661-0494 at least 24 hours in advance to schedule

  2. 2

    Final

    Verify flashing, underlayment, ice shield, ventilation, and proper installation per approved application

Applies to: Residential Building Permit (New Construction / Addition / Alteration)

  1. 1

    Building Department Sign-Off

    Building Official (Keith Teeters) inspection prior to final; applicant must obtain sign-off from all applicable entities listed on the permit application (Building Dept, Flood Plain, Planning & Zoning, fire district, water/sewer district, utilities) prior to final inspection

  2. 2

    Final

    Final inspection and sign-off by the City of Kellogg Building Official

Applies to: Solar Photovoltaic (PV) Permit

  1. 1

    Foundation/Footing (ground-mount) or Framing (rooftop racking)

    Structural attachment verified by the City Building Official (Keith Teeters) before panels are installed

  2. 2

    Final Electrical/Interconnection (State of Idaho DOPL)

    Performed by the State of Idaho, not the City, consistent with Kellogg's standing arrangement for electrical trade permits

Final inspection only: Fence Permit

Sources & verification

Key facts verified against official sources. Last reviewed 2026-07-23.

Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Kellogg building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.

Kellogg building permits

Get alerts for Kellogg

We'll email you when Kellogg's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.