Solar PV Permit (Split City/State Jurisdiction) — Driggs, Idaho · Requirements sheet
Verified 2026-07-23 · Source: https://driggsidaho.org/departments/planning-and-building/building-information-applications/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Solar PV Permit (Split City/State Jurisdiction) in Driggs, Idaho
Required for installation of rooftop or ground-mounted solar photovoltaic systems in Driggs. The City of Driggs Planning & Building Department's own Building Information page states directly: 'Plumbing and Electrical permits are issued by the State of Idaho Division of Building Safety and are required for any plumbing and electrical work' — the City itself does not issue electrical permits. The structural/racking portion of a solar installation is billed on the City's standard valuation-based Building Permit fee schedule (calculated per the International Code Council's Building Safety Journal valuation tables); no dedicated solar/photovoltaic fee line was located as of this review.
Verified 2026-07-23 · Source
When you need this permit
- Obtain a City of Driggs Building Permit for the structural/racking portion of the installation via the City's Application Portal, including a completed Building Permit & Site Plan Checklist
- A licensed electrical contractor must separately obtain an electrical permit from the Idaho Division of Building Safety (DBS) for the interconnection/electrical work — the City of Driggs does not issue electrical permits
- Building permits are required for construction, addition, alteration, repair, relocation, demolition, or change in occupancy within City limits; minor exempt projects (e.g., small tool sheds, low fences) do not apply to solar installations
- Impact fees may apply to new construction associated with the project, per the City's Impact Fee schedule (deed-restricted affordable housing developments are exempt)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 3 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
City Building Inspection (Structural/Racking)
City of Driggs inspects the structural/racking portion of the installation
- 2
State Electrical Inspection
Idaho Division of Building Safety inspects the interconnection/electrical work, since this is not handled by the City
See the full Driggs inspection guide — scheduling & re-inspection fees →
Tips
- Driggs splits solar permitting between two authorities: the City handles the structural/racking Building Permit, while a licensed electrical contractor must separately obtain an Idaho Division of Building Safety electrical permit for the interconnection — the City's own Building Information page states this directly.
- Idaho's electrical licensing has a dedicated Solar Photovoltaic category requiring NABCEP (or equivalent) certification; confirm your installer holds the correct DBS license classification for PV work.
- Because the electrical/interconnection side of this permit is state-administered, budget separate time and separate applications for the City Building Permit and the Idaho DBS Electrical Permit.
- Check whether Impact Fees apply to your project — the City's Impact Fee schedule generally applies to new construction, though deed-restricted affordable housing is exempt; confirm with Planning & Building whether a solar retrofit on an existing structure triggers this.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-23.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Driggs building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Driggs
Solar PV Permit (Split City/State Jurisdiction) in other cities
Compare solar pv permit (split city/state jurisdiction) fees across Idaho →
Look up this fee in a different city →