Building Permit (New Construction / Addition / Structural Alteration) in Shelby, Montana
Required for new single-family home construction, additions, and structural alterations within Shelby city limits. Issued by the City of Shelby under its DLI-certified local Building (B) program, reviewed by the City's Building Official (named 'Keith Thaut' on the City's live Building & Zoning page as of 2026-07-16; the Montana DLI certified-jurisdictions roster spells the same position 'Ken Thaut' — see department record for this unresolved discrepancy) against the state-adopted building and technical codes referenced in Shelby Municipal Code Title 10, Chapter 1.
Verified 2026-07-03 · Source
When you need this permit
- Application for a building permit submitted to the City Building Official; plans reviewed for compliance with the applicable building/technical codes adopted by administrative reference under Shelby Municipal Code 10-1-1
- Building plan review completed by the building official within 30 working days of submittal of a complete application (10-1-2.C); the building official may submit plans to other affected city departments for review before permit issuance (10-1-2.B)
- Structural changes (any work increasing or decreasing the size of a structure) require a building permit and payment of the applicable fee per the valuation-based schedule in Shelby Municipal Code 1-12-13; whether contemplated work constitutes a 'structural change' is determined by the building inspector (10-1-9.B)
- Non-structural 'remodeling' of a single-family dwelling (siding, reroofing, cupboard/counter/countertop replacement, interior wall repair/replacement, and window/door replacement using the original opening) requires NO permit and NO fee, provided it does not affect the structural integrity of the dwelling (10-1-9.A)
- Factory-built buildings approved by the Montana Building Codes Bureau are subject to local inspection and fees for zoning, utility connections, and foundations only — not full plan review (10-1-5)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Department Coordination Review
Building official submits plans to any other affected city department for review and approval before permit issuance, per Shelby Municipal Code 10-1-2.B
- 2
Construction Inspections
Conducted by the building official or other appropriately qualified and authorized personnel per Shelby Municipal Code 10-1-3; where other departments require inspection, they must be completed within the same time frame allowed for plan review under 10-1-2
See the full Shelby inspection guide — scheduling & re-inspection fees →
Tips
- Shelby's 30-working-day plan review clock (Municipal Code 10-1-2) is faster than neighboring Conrad's 60-working-day clock — confirm current timelines directly with the Building Official, as small-town review capacity can vary project to project.
- Non-structural remodeling of a single-family home (siding, reroofing, cabinet/counter replacement, interior wall work, and same-opening window/door replacement) needs NO permit and NO fee under Shelby Municipal Code 10-1-9, as long as structural integrity is unaffected — confirm with the Building Official whether a specific project qualifies.
- Building of a fence is explicitly classified as a 'structural change' requiring a ZONING permit (not a building permit) per Shelby Municipal Code 10-1-9.B.
- Call the Building Official via Shelby City Hall, (406) 434-5222, for all building inspection and ordinance enforcement matters — named 'Keith Thaut' on the City's current website and 'Ken Thaut' on the Montana DLI's certified-jurisdictions roster (unresolved spelling discrepancy as of 2026-07-16).
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-03.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Shelby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Shelby
Building Permit (New Construction / Addition / Structural Alteration) in other cities
Compare building permit (new construction / addition / structural alteration) fees across Montana →
Look up this fee in a different city →
Now live
Build your Shelby project checklist
Describe your project once and get every permit, document, and fee it triggers in Shelby — in one checklist. Sign up and pay once to generate it, or go unlimited with Pro.
Get started →