Change Of Use / Certificate Of Occupancy Permit — Shelby, Montana · Requirements sheet
Verified 2026-07-22 · Source: https://codelibrary.amlegal.com/codes/shelbymt/latest/shelby_mt/0-0-0-5644
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change Of Use / Certificate Of Occupancy Permit in Shelby, Montana
Two governing layers apply to a commercial change of use or occupancy change in Shelby. First, Shelby Municipal Code 13-12-2.A requires a ZONING PERMIT from the Zoning Administrator prior to 'any change of use of any building or land,' and 13-12-2.C requires a CERTIFICATE OF COMPLIANCE before any nonconforming structure or use is changed or extended. Second, the state-adopted 2021 IBC (Montana Building Code, administratively adopted by Shelby Municipal Code 10-1-1) Section 111 (Certificate of Occupancy) independently requires the City Building Official to issue a certificate of occupancy before a 'change of occupancy' of a building or structure is made. Because Shelby's Zoning Administrator 'may also serve as the building inspector for the city' (13-12-1.A), both reviews are typically conducted by the same city office.
Verified 2026-07-22 · Source
When you need this permit
- A zoning permit must be secured from the Zoning Administrator prior to any change of use of any building or land (Shelby Municipal Code 13-12-2.A); the zoning permit application may be combined with the building permit application (13-12-2.B.4)
- A Certificate of Compliance is required before any nonconforming structure or use is changed or extended: at the time a building permit is requested, the Zoning Administrator surveys the structure and its use for conformity with applicable zoning ordinances, and the certificate must state specifically wherein the nonconforming use differs from Title 13's provisions (Shelby Municipal Code 13-12-2.C)
- Under the state-adopted 2021 IBC (Montana Building Code) Section 111.1 (Change Of Occupancy): 'A building or structure shall not be used or occupied in whole or in part, and a change of occupancy of a building or structure or portion thereof shall not be made, until the building official has issued a certificate of occupancy therefor' (Section 111.2 governs issuance; Montana's amendment ties issuance to Mont. Code Ann. § 50-60-107)
- Zoning permits expire if the described work has not begun within 6 months of issuance; a single 6-month extension may be granted by the Zoning Administrator (13-12-2.D.1)
- Applications for a zoning permit (other than temporary-use permits) must be accompanied by plans in duplicate showing lot dimensions, existing structures, and the proposed change (13-12-2.B.1-2)
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our paid checklist will assemble all of them, from $29 →
Fee schedule
Review timeline
Inspection process
- 1
Zoning Administrator Compliance Survey
Zoning Administrator surveys the structure and its use for zoning conformity at the time a building permit is requested, per Shelby Municipal Code 13-12-2.C
- 2
Building Official Certificate of Occupancy Inspection
Where a change of occupancy classification is involved, the City Building Official inspects for compliance before issuing a certificate of occupancy under the state-adopted 2021 IBC Section 111
See the full Shelby inspection guide — scheduling & re-inspection fees →
Tips
- Two distinct legal triggers can both apply to the same tenant/use change: Shelby's own zoning-permit requirement for 'any change of use' (13-12-2.A) and the state-adopted IBC's separate certificate-of-occupancy requirement for a 'change of occupancy' (Section 111) — confirm with the Building Official which (or both) apply to a specific project.
- Because Shelby's Zoning Administrator 'may also serve as the building inspector for the city' (13-12-2.A... 13-12-1.A), both the zoning and building-code sides of a change-of-use review are typically handled by the same city office — call (406) 434-5222.
- A Certificate of Compliance (13-12-2.C) is specifically required before a NONCONFORMING structure or use may be changed or extended — this is distinct from, and in addition to, the general change-of-use zoning permit.
- Confirm the current zoning-permit fee with City Hall, since it is not published as a fixed table in the code; if a Building Permit is also triggered, that fee IS published on the valuation-based schedule at 1-12-13.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-07-22.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Shelby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
Other permits in Shelby
Change Of Use / Certificate Of Occupancy Permit in other cities
Compare change of use / certificate of occupancy permit fees across Montana →