Commercial Building Permit (New Construction / Addition / Alteration / Tenant Improvement) in Shelby, Montana
Required for new construction, additions, and structural alterations of commercial and industrial structures within Shelby city limits. Shelby's Montana DLI certification for Building (B) carries no residential-only or commercial-only qualifier, so the same City Building Official, the same Building Permit Application, and the same valuation-based fee table at Shelby Municipal Code 1-12-13 that govern the Building Permit (New Construction / Addition / Structural Alteration) permit type above apply to commercial work as well -- Shelby publishes no separate commercial application or commercial-specific fee line. Outside Shelby's incorporated city limits, in unincorporated Toole County, commercial building permits are instead issued by Toole County under its own, narrower Montana DLI certification for Building, commercial only (certified official Kyle Harlan, 424-8310) -- a county-level certification scoped to commercial work only, which is unusual: most Montana counties and cities holding a Building certification carry it without an occupancy qualifier, or not at all. Electrical, plumbing, and mechanical/HVAC work on a commercial project inside Shelby city limits is not covered by this permit and remains with the Montana DLI Building Codes Bureau, the same split documented for residential work.
Verified 2026-08-26 · Source
When you need this permit
- Applies to commercial and industrial structures located inside the incorporated city limits of Shelby; a commercial project in unincorporated Toole County is not covered by this permit and instead requires a separate Toole County building permit issued under the County's own Building (commercial only) certification, Kyle Harlan, (406) 424-8310
- Application for a building permit submitted to the City Building Official; plans reviewed against the state-adopted 2021 International Building Code (IBC) as administratively adopted by Shelby Municipal Code 10-1-1 (Ord. 803, 9-20-2010)
- Building plan review completed by the building official within 30 working days of submittal of a complete application (Shelby Municipal Code 10-1-2.C), the same clock documented for residential work above; the building official may lengthen this if the aid of the Montana Building Codes Bureau, other state agencies, or professional consultants is requested (10-1-2.D)
- Building official may submit plans to other affected city departments for review and approval before permit issuance (10-1-2.B)
- This permit covers the Building trade only -- electrical, plumbing, and mechanical/HVAC permits for the same commercial project are issued directly by the Montana DLI Building Codes Bureau in Helena, since Shelby's local certification does not extend to those trades
- Fire-protection systems (sprinklers, alarms) are reviewed for code compliance as part of this Building Permit rather than through a separate fire-authority permit, because no distinct sprinkler/alarm permit product exists locally or at the state level for a Building-only-certified city
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
Shelby Municipal Code 1-12-13, Plan Review And Building Permit Fees (Ord. Show full citationHide
Shelby Municipal Code 1-12-13, Plan Review And Building Permit Fees (Ord. 780, 5-21-2007) -- one citywide valuation table with no residential/commercial split; the same table documented under the Building Permit (New Construction / Addition / Structural Alteration) permit type aboveShelby Municipal Code Title 8 (Fire Regulations) publishes no sprinkler/alarm permit process or fee, and the Montana DLI Building Codes Bureau's certified-jurisdictions roster has no separate Fire… Show full citationHide
Shelby Municipal Code Title 8 (Fire Regulations) publishes no sprinkler/alarm permit process or fee, and the Montana DLI Building Codes Bureau's certified-jurisdictions roster has no separate Fire trade code in its key statewide -- the same finding documented under the fire-sprinkler-alarm-permit typeReview timeline
Inspection process
- 1
Department Coordination Review
Building official submits plans to any other affected city department for review and approval before permit issuance, per Shelby Municipal Code 10-1-2.B
- 2
Construction Inspections
Conducted by the building official or other appropriately qualified and authorized personnel per Shelby Municipal Code 10-1-3, including fire-protection-system compliance since no separate fire-authority inspection track exists locally
See the full Shelby inspection guide — scheduling & re-inspection fees →
Tips
- Shelby's Building (B) certification carries no residential-only or commercial-only qualifier -- the same Building Official, application, fee table (Shelby Municipal Code 1-12-13), and 30-working-day review clock (10-1-2.C) documented for the Building Permit (New Construction / Addition / Structural Alteration) permit type above apply equally to commercial construction inside city limits.
- Toole County's own Montana DLI certification is scoped to Building, commercial only -- a narrower certification than Shelby's plain Building certification, and worth noting because most Montana jurisdictions with a Building certification hold it without any occupancy qualifier at all. Confirm which authority applies by checking whether the project address is inside or outside Shelby's incorporated city limits.
- Electrical, plumbing, and mechanical/HVAC permits for a commercial project inside Shelby are not part of this permit -- they route directly to the Montana DLI Building Codes Bureau in Helena, the same as for residential work, since Shelby's local certification does not cover those trades.
- There is no separate fire department plan-review authority in Shelby -- fire-protection-system compliance (sprinklers, alarms) for a commercial project is reviewed by the City Building Official as part of the standard Building Permit process.
Frequently asked questions
Sources & verification
Verified against official sources. Last reviewed 2026-08-26.
Fee schedules
Codes & ordinances
Department & other records
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the Shelby building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
This one’s complicated · Get an expediter
Tell us about your project and we’ll connect you with a permit expediter who works in Shelby.
PermitBase may receive a referral fee from the expediter. This is a service introduction, not verified permit data or legal advice.
Other permits in Shelby
Commercial Building Permit (New Construction / Addition / Alteration / Tenant Improvement) in other cities
Look up this fee in a different city →
Now live
Build your Shelby project checklist
Describe your project once and get every permit, document, and fee it triggers in Shelby — in one checklist. Free, for any city and any number of projects.
Get started →