How to schedule

Inspections are requested through the building department below.

Address
171-A State Rd. 344, Edgewood, NM 87015-3610
Phone
(505) 286-4518
Office hours
Not published on the Town's Planning & Zoning page as of 2026-07-18 — call (505) 286-4518 to confirm current hours.

Inspection sequence

Applies to: State Building Permit (NM Construction Industries Division)

  1. 1

    Foundation Inspection

    After excavation for footings is complete and required reinforcing steel is in place; concrete forms must be in place before inspection.

  2. 2

    Concrete Slab / Under-Floor Inspection

    After in-slab or under-floor service equipment, conduit, and piping are in place, before concrete is placed or floor sheathing is installed.

  3. 3

    Frame Inspection

    After the roof, framing, fire blocking, and bracing are in place and the rough electrical, plumbing, and heating work is complete and approved.

  4. 4

    Weather-Resistive Barrier Inspection

    After installation of the weather-resistive barrier and before it is covered.

  5. 5

    Final Inspection

    After finish grading, with the building complete and ready for occupancy; final electrical, plumbing, and mechanical inspections must pass first. CID issues the Certificate of Occupancy after this inspection.

Applies to: Fire Sprinkler & Fire Alarm System Permit (Santa Fe County Fire Department — Fire Prevention/Risk Reduction Division)

  1. 1

    Rough-in Inspection (Sprinkler)

    Required before concealment of sprinkler piping; the SFCFD-stamped plan set must be on site or the inspection will not be performed.

  2. 2

    Final Inspection (Sprinkler)

    Installation company representative must be present; requires a signed Contractor's Material & Test Certificate for Above Ground Piping.

  3. 3

    Final Inspection (Fire Alarm / Alternative Suppression Systems)

    Installation company representative must be present; fire alarm final additionally requires a 'System of Record Completion' from the alarm company plus an emailed monitoring-service report.

Re-inspection fees

Electrical Permit (NM Construction Industries Division — Electrical Bureau)Reinspection Fee · CID Fees page, Electrical Bureau schedule, updated 2025-11-19.
$80
EV Charger / EVSE Permit (NM Construction Industries Division — Electrical Bureau)Reinspection Fee · CID Fees page, Electrical Bureau schedule, updated 2025-11-19
$80
Mechanical/Plumbing Permit (NM Construction Industries Division — Mechanical Plumbing Bureau)Each Re-Inspection (2nd re-inspection $120.00) · CID Fees page, Mechanical Plumbing Bureau schedule, updated 2025-11-19.
$80.00

Edgewood building permits

Get alerts for Edgewood

We'll email you when Edgewood's fees, documents, or codes change — not often.

We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.