How to schedule
Inspections are requested through the building department below.
- Address
- 550 North 800 West, West Bountiful, UT 84087
- Phone
- (801) 292-4486
- info@wbcityut.gov
- Office hours
- Mon–Thu 7:30 AM – 5:00 PM; Fri 7:30 AM – 3:00 PM
- Website
- Official site
Published scheduling rules
- Schedule all inspections directly with Sunrise Engineering at 800-560-6151, at least 24 hours in advance, with the permit number, site address, and inspection type ready. (Residential Building Permit)
- West Bountiful is a confirmed-independent jurisdiction: the City issues its own permits and sets its own fee schedule, but contracts building code plan review and inspections to Sunrise Engineering (schedule inspections at 800-560-6151, not through City Hall). Do not confuse this with the much larger, separate city of Bountiful, UT, which has its own independent permitting. (General)
Inspection sequence
Applies to: Fire Sprinkler System Permit
- 1
Inspection 1 of 3
SDMF Fee Ordinance (04/2024) lists the $300 Fire Sprinkler System Permit as covering '(3 Inspections)' without naming each one individually; contact SDMF at 801-677-2400 for the specific inspection stages on a given project.
- 2
Inspection 2 of 3
Second of the 3 inspections included in the $300 permit fee, per the SDMF Fee Ordinance.
- 3
Inspection 3 of 3 (Final)
Third of the 3 inspections included in the $300 permit fee, per the SDMF Fee Ordinance. Final inspections will not be scheduled until SDMF's pre-check list is complete.
Applies to: Change of Use / Certificate of Occupancy
- 1
Fire Inspection
Required prior to business license issuance, performed by South Davis Metro Fire; recorded on the application's 'Fire Inspection Date(s)' and 'Fire Marshall Approval Date' fields.
- 2
Health Department Inspection
Required where the proposed use is health-regulated (e.g., food service); recorded on the application's 'Health Dept Inspect/Approval' field. Not applicable to every business type.
Applies to: Commercial Building Permit
- 1
Building, Electrical, Mechanical & Plumbing Inspections
Performed by Sunrise Engineering under contract to West Bountiful City. Schedule inspections by calling 800-560-6151 at least 24 hours in advance.
- 2
Final Inspection
A final inspection and approval by the building inspector (Sunrise Engineering) is required prior to occupying a new structure.
Applies to: Commercial Tenant Improvement / Tenant Finish Permit
- 1
Framing / Rough-In
Performed by Sunrise Engineering under contract to the City; schedule at 800-560-6151 at least 24 hours in advance.
- 2
Final Inspection
Final inspection and approval required prior to occupying the tenant space.
Applies to: Fire Alarm System Permit
- 1
First Inspection
Included in the $200 permit fee; SDMF fire alarm permits include 2 inspections total.
- 2
Final Inspection
Second of the 2 inspections included in the permit fee.
Applies to: Residential Building Permit
- 1
Building, Electrical, Mechanical & Plumbing Inspections
Performed by Sunrise Engineering under contract to West Bountiful City. It is the owner's or contractor's responsibility to schedule inspections by calling 800-560-6151 at least 24 hours in advance, providing the building permit number, site address, and inspection type needed.
- 2
Final Inspection
A final inspection and approval by the building inspector (Sunrise Engineering) is required prior to occupying a new structure, per West Bountiful's official Building Permits page.
Applies to: Swimming Pool Permit
- 1
Water Table / Pump Pit Inspection
Required for in-ground pools if a water table is found during the required 3-foot-below-depth pump pit check; sump pump provisions must be inspected.
- 2
Final Pool Inspection
Performed by Sunrise Engineering under contract to the City; schedule at 800-560-6151 at least 24 hours in advance.
Sources & verification
Verified against official sources. Last reviewed 2026-07-08.
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
West Bountiful building permits
Get alerts for West Bountiful
We'll email you when West Bountiful's fees, documents, or codes change — not often.
We only use your email to send permit updates. No spam, unsubscribe anytime. Privacy.