Change of Use / Certificate of Occupancy — West Bountiful, Utah · Requirements sheet
Reviewed 2026-07-22 · Source: https://wbcityut.gov/business-license/
PermitBase is an independent reference and is not affiliated with any government agency. Requirements change and vary by project — confirm current details with the building department before you submit.
Change of Use / Certificate of Occupancy in West Bountiful, Utah
West Bountiful does not publish a standalone change-of-use or certificate-of-occupancy permit or fee. A live review of the City's Building Permits page, Forms & Permits index, and the Consolidated Fee Schedule (all) found no distinct change-of-use or certificate-of-occupancy line item anywhere. In practice, a change of occupancy or use in an existing commercial building is verified through West Bountiful's Commercial Business License process (WBMC Title 5, fee schedule ref. WBMC 5.04.04): the license application itself carries 'For Official Use Only' sign-off fields for Health Department inspection/approval, Fire Inspection date(s), Fire Marshal approval, and Conditional Use requirement/approval, so a new business cannot legally begin operating in a space — including one with a different use than its prior occupant — without passing through this sign-off chain. This is documented here as the closest functional equivalent to a change-of-use/CO process, not as a dedicated permit type in its own right.
Reviewed 2026-07-22 · Source
When you need this permit
- No standalone change-of-use or certificate-of-occupancy permit or fee is published by West Bountiful; verify occupancy compliance through the Commercial Business License application instead (WBMC Title 5)
- A Commercial Business License is required before commencing operations at any location, including a new occupant moving into an existing building for the same or a different use
- Mandatory Fire Inspection and Fire Marshal approval prior to license issuance, per the application's own 'For Official Use Only' sign-off fields
- Health Department inspection/approval where applicable to the proposed use (e.g., food service), per the same sign-off fields
- Conditional Use requirement/approval sign-off where the proposed use is not permitted outright in the zone
Required documents
Check off what you have — your progress is saved on this device.
Not ready yet — 0 of 1 required documents checked.
This checker covers one permit. A full project usually triggers several — our checklist will assemble all of them, free →
Fee schedule
West Bountiful Consolidated Fee Schedule, Business Licensing Fees section (WBMC 5.04.04): 'Commercial Business License - annual fee (WBMC 5.04.04)... Show full citationHide
West Bountiful Consolidated Fee Schedule, Business Licensing Fees section (WBMC 5.04.04): 'Commercial Business License - annual fee (WBMC 5.04.04)... $50.00' plus '$5.00' per full-time employee and '$2.50' per part-time employee, with a 50% discount on or after October 1. The Commercial Business License Application PDF carries the same figures. The fee schedule contains no separate change-of-use or certificate-of-occupancy fee line item.Review timeline
Inspection process
- 1
Fire Inspection
Required prior to business license issuance, performed by South Davis Metro Fire; recorded on the application's 'Fire Inspection Date(s)' and 'Fire Marshall Approval Date' fields.
- 2
Health Department Inspection
Required where the proposed use is health-regulated (e.g., food service); recorded on the application's 'Health Dept Inspect/Approval' field. Not applicable to every business type.
See the full West Bountiful inspection guide — scheduling & re-inspection fees →
Tips
- Do not file for one; instead, the Commercial Business License application functions as the city's practical occupancy/use verification step.
- The Commercial Business License Application's own 'For Official Use Only' section is the tell: it has dedicated sign-off fields for Health Department, Fire Inspection, Fire Marshal approval, and Conditional Use requirement — a new occupant cannot get a license, and therefore cannot legally operate, without clearing these.
- If the new use is not permitted outright in the property's zone, a separate Conditional Use Permit application is required in addition to the business license.
Frequently asked questions
Sources & verification
Key facts verified against official sources. Last reviewed 2026-07-22.
Fee schedules
Applications & forms
Fees, timelines, and adopted codes are researched from each jurisdiction's published records — see how we verify. Requirements change and vary by project, so always confirm the current details with the West Bountiful building department before you submit. PermitBase is an independent reference and is not affiliated with any government agency.
West Bountiful's permit history isn't searchable here yet
This page covers what the permit requires. What we don't have for West Bountiful yet is the record of permits actually issued — the history you'd search by street address. That is a gap in our coverage, not a statement about any particular property.
Your email, and the place — never an address. We only use it to tell you when West Bountiful lands. Privacy.
Other permits in West Bountiful
Change of Use / Certificate of Occupancy in other cities
Compare change of use / certificate of occupancy fees across Utah →